Question

Salanes of production labor supervisors: O direct labor hours 0 machine hours O setup hours O number of setups O number of un

0 0
Add a comment Improve this question Transcribed image text
Answer #1

1. Salaries of production labor supervisor:

Direct labor hours

Brief Explanation: Duties and time contribution of direct labor supervisors depends on the Direct labor hours. Hence, the salaries of direct labor supervisors should be distributed on the basis of direct labor hours.

2. Salaries of Machine technicians

Machine hours

Brief Explanation: As the machine technicians do the repair and maintenance of the machine, and the machine breakdowns depends on machine hours, their salaries should be distributed on the basis of machine hours.

3. Salaries of production support staff.

Setup hours

Brief Explanation: They set up the machines before production run, and it takes different times for different products. Hence, it should be distributed on the basis of set up times.

4. Design department costs.

Number of new product design

Brief Explanation: As it can be easily related with the number of new product designed, it would be appropriate to allocate design department's costs non that basis.

5. Call center costs.

Number of units

Brief Explanation: As the customer assistance services depends on number of units, the respective department's costs should be allocated on the basis of number of units.

** Please feel free to ask me if any more explanations are required. Thank You..!!

Add a comment
Know the answer?
Add Answer to:
Salanes of production labor supervisors: O direct labor hours 0 machine hours O setup hours O...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Question 1: Choosing activity cost drivers Choose the best cost driver for each pool: Salaries of...

    Question 1: Choosing activity cost drivers Choose the best cost driver for each pool: Salaries of production labor supervisors: O direct labor hours O machine hours setup hours O number of setups O number of units O number of new product designs Salaries of machine technicians (they repair the machines; on average, machines break down every 500 hours): direct labor hours O machine hours setup hours number of setups number of units number of new product designs Salaries of production...

  • Direct materials per unit Direct labor cost per unit Direct labor-hours per unit Estimated annual production...

    Direct materials per unit Direct labor cost per unit Direct labor-hours per unit Estimated annual production and sales Xactive $ 64.40 $ 17.80 1.4 DLHS 21,000 units Pathbreaker $ 50.60 $ 12.60 1 DLHS 71,000 units the company has a conventional costing system in which manufacturing overhead is applied to units based on jours. Data concerning manufacturing overhead and direct labor-hours for the upcoming year appear below: Estimated total manufacturing overhead Estimated total direct labor-hours $1,967,840 100,400 DLHS Required: -a....

  • Wings Co. budgeted $562,000 manufacturing direct wages, 2,000 direct labor hours, and had the following manufacturing...

    Wings Co. budgeted $562,000 manufacturing direct wages, 2,000 direct labor hours, and had the following manufacturing overhead: Overhead Cost Pool Materials handling Machine setup Machine repair Inspections Budgeted Overhead Cost $156,000 18,400 1,220 11,500 Budgeted Level for Cost Driver 3,900 pounds 460 setups 30,500 machine hours 230 inspections Overhead Cost Driver Weight of materials Number of setups Machine hours Number of inspections Requirements for Job #971 which manufactured 4 units of product: Direct labor Direct materials Machine setup Machine hours...

  • Wings Co. budgeted $555,600 manufacturing direct wages, 2,315 direct labor hours, and had the following manufacturing...

    Wings Co. budgeted $555,600 manufacturing direct wages, 2,315 direct labor hours, and had the following manufacturing overhead: Overhead Cost Pool Budgeted Overhead Cost Budgeted Level for Cost Driver Overhead Cost Driver Materials handling $ 160,000 3,200 pounds Weight of materials Machine setup 13,260 390 setups Number of setups Machine repair 1,380 30,000 machine hours Machine hours Inspections 10,560 160 inspections Number of inspections Requirements for Job #971 which manufactured 4 units of product: Direct labor 20 hours Direct materials 130...

  • Activity Cost Pool Activity Rate Labor-related per DLH Machine-related per MH Machine setups per setup Production...

    Activity Cost Pool Activity Rate Labor-related per DLH Machine-related per MH Machine setups per setup Production orders per order Product testing per test Packaging per package General factory per DLH 2. Required information [The following information applies to the questions displayed below.] Rustafson Corporation is a diversified manufacturer of consumer goods. The company's activity-based costing system has the following seven activity cost pools: Activity Cost Pool Estimated Overhead Cost Expected Activity Labor-related $ 19,600 10,000 direct labor-hours Machine-related $ 7,000...

  • Wings Co. budgeted $556,000 manufacturing direct wages, 2,500 direct labor hours, and had the following manufacturing...

    Wings Co. budgeted $556,000 manufacturing direct wages, 2,500 direct labor hours, and had the following manufacturing overhead: Overhead Cost Pool Materials handling Machine setup Machine repair Inspections Budgeted Overhead Cost $198,000 14,888 1,800 10,200 Budgeted Level for Cost Driver 3,300 pounds 400 setups 30,000 machine hours 17e inspections Overhead Cost Driver Weight of materials Number of setups Machine hours Number of inspections Requirements for Job #971 which manufactured 4 units of product: Direct labor Direct materials Machine setup Machine hours...

  • Wings Co. budgeted $555,600 manufacturing direct wages, 2,315 direct labor hours, and had the following manufacturing...

    Wings Co. budgeted $555,600 manufacturing direct wages, 2,315 direct labor hours, and had the following manufacturing overhead: Overhead Cost Pool Materials handling Budgeted Budgeted Level for Overhead Cost Overhead Cost Cost Driver Driver Weight of $160,000 3,200 pounds materials Number of 13,200 390 setups setups 1,380 30,000 machine hours Machine hours Machine setup Machine repair Number of Inspections inspections Requirements for Job #971 which manufactured 4 units of product: 10,560 160 inspections Direct labor 20 hours Direct materials 130 pounds...

  • Wings Co. budgeted $567,000 manufacturing direct wages, 2,000 direct labor hours, and had the following manufacturing...

    Wings Co. budgeted $567,000 manufacturing direct wages, 2,000 direct labor hours, and had the following manufacturing overhead: Overhead Cost Pool Budgeted Overhead Cost Budgeted Level for Cost Driver Overhead Cost Driver Materials handling $ 132,000 4,400 pounds Weight of materials Machine setup 15,300 510 setups Number of setups Machine repair 1,920 32,000 machine hours Machine hours Inspections 11,200 280 inspections Number of inspections Requirements for Job #971 which manufactured 4 units of product: Direct labor 20 hours Direct materials 250...

  • Wings Co. budgeted $562,000 manufacturing direct wages, 2,000 direct labor hours, and had the following manufacturing...

    Wings Co. budgeted $562,000 manufacturing direct wages, 2,000 direct labor hours, and had the following manufacturing overhead: Overhead Cost Pool Budgeted Overhead Cost Budgeted Level for Cost Driver Overhead Cost Driver Materials handling $ 156,000 3,900 pounds Weight of materials Machine setup 18,400 460 setups Number of setups Machine repair 1,220 30,500 machine hours Machine hours Inspections 11,500 230 inspections Number of inspections Requirements for Job #971 which manufactured 4 units of product: Direct labor 20 hours Direct materials 200...

  • department. The production department is estimated to require 4,000 direct labor hours. The total Indirect labor...

    department. The production department is estimated to require 4,000 direct labor hours. The total Indirect labor is budgeted to be $704,000 Direct Number of 1,100 2,000 80,000 Total,6001.000 160,000 allocation base. costing method results in the product with the larger number of setups receiving a larger portion of the setup activity cost. The

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT