Daily use of Item X-25 in a high-tech Manufacturing Process during the Delivery or Lead time for Item X-25 is 4 working days is given below:

1) Avg Daily Use = 200 2) Maximum Daily Use = 230 3) Minimum Daily Use = 160 and SD = +/- 20

SD = Standard Deviation

Calculate the Reorder Point (ROP) for X-25 with the Safety Stock (SS) at 97% Service Level in order to prevent Stock-out. In other word Stock-out at 3% level is acceptable.

a.

920

b.
c.

426

d.

559

e.

838

f.

800

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Reorder point = dL + zσd√L

where, where d = average daily demand = 200

σd = standard deviation of daily demand = 20

L = Lead Time = 4 days

z = number of standard deviations based on service level 97% = 1.88 from z table

Reorder Point = 200*4 + 1.88*20*√4 = 875.2

Add a comment
Know the answer?
Add Answer to:
X-25 Item is an important part used in the production of Laptops. Daily use of Item...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • A firm stocks a certain item, which is managed on a continuous review basis. Demand averages...

    A firm stocks a certain item, which is managed on a continuous review basis. Demand averages 230 units per day with a standard deviation of 45 units per day. Lead time is fixed at 10 day. If the firm sets the reorder point to 2400 units, the cycle-service level will be approximately?? (round down Z to 2 decimal places, and use normal distbn table). ROP = (Avg. Daily Demand rate * lead time) + safety stock Safety stock = Z...

  • Average daily sales of a product are 10 units. The actual number of units each day...

    Average daily sales of a product are 10 units. The actual number of units each day is 9, 10, or 11 with frequencies of 75, 90 and 85 respectively during the last 250 days. The lead time for delivery of this product averages 4 days, although the time may be 3, 4, or 5 days with frequencies of 25, 60 and 20 respectively as observed in 105 recent orders. The company plans to place an order when the inventory level...

  • please read instructions on the first picture and follow it Discussion Board: Chapter 1 Due: Jun...

    please read instructions on the first picture and follow it Discussion Board: Chapter 1 Due: Jun 28, 2019 at 11:59 PM Please read the article titled Evolution of Operations Planning and Control: from production to supply chains In at least three paragraphs, describe how and why the focus of operations planning and control has changed over time. While one might argue that answers consisting of sentences quoted from articles do not represent plagiarism, I do not consider them acceptable, and...

  • please read instructions on the first picture and follow it Discussion Board: Chapter 1 Due: Jun...

    please read instructions on the first picture and follow it Discussion Board: Chapter 1 Due: Jun 28, 2019 at 11:59 PM Please read the article titled Evolution of Operations Planning and Control: from production to supply chains In at least three paragraphs, describe how and why the focus of operations planning and control has changed over time. While one might argue that answers consisting of sentences quoted from articles do not represent plagiarism, I do not consider them acceptable, and...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT