given that:


Opening Estimated Inventory as on 1st August: 12000 units


Closing Estimated Inventory as on 31st Augst: 9000 units


Expected Sales Unit= 75,000 units


Unit produced= Sales units+ Closing units- Opening Units


= 75000+ 9000 - 12000


= 72000 units


Material A requirement = 3.0 lbs * 72000 = 2,16,000 lbs.


Material B requirement = 0.5 lbs * 72000 = 36,000 lbs.


Hence Option (b) is correct.


answered by: fatfish
Add a comment
Know the answer?
Add Answer to:
Calculator Production estimates for August for Jay Company are as follows: Estimated Inventory (units), August 1...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Purple Co.'s production budget for Product X for the year ended December 31 is as follows: Product X Sales (in units) 6...

    Purple Co.'s production budget for Product X for the year ended December 31 is as follows: Product X Sales (in units) 640,000 Plus desired ending inventory 85,000 Total 725,000 Less estimated beginning inventory, January 1 90,000 Total production 635,000 In Purple's production operations, Materials A, B, and C are required to make Product X. The quantities of direct materials expected to be used for each unit of product are as follows: Material A Material B Material C 0.50 lb. per...

  • Boulware Company's budgeted production calls for 6,000 units in October and 9,000 units in November. Each...

    Boulware Company's budgeted production calls for 6,000 units in October and 9,000 units in November. Each unit requires 7 pounds (lbs.) of raw material A. Each month's ending inventory of raw materials should equal 25% of the following month's budgeted materials requirements. The October 1 inventory for this material is 10,500 pounds. What is the budgeted materials purchases for this key material in pounds for October? Multiple Choice 1 0 57,750 lbs. 0 47,250 lbs. 0 68,250 lbs. 0 42,000...

  • Zortek Corp. budgets production of 490 units in January and 260 units in February. Each finished...

    Zortek Corp. budgets production of 490 units in January and 260 units in February. Each finished unit requires two pounds of raw material Z. which costs $3 per pound. Each month's ending inventory of raw materials should be 40% of the following month's budgeted production. The January 1 raw materials inventory has 200 pounds of Z. Prepare a direct materials budget for January ZORTEK CORP Direct Materials Budget For Month Ended January 31 Budget production (units) units Materials needed for...

  • Marino's Frozen Pizza Inc. has determined from its production budget the following estimated production volumes for...

    Marino's Frozen Pizza Inc. has determined from its production budget the following estimated production volumes for 12'' and 16'' frozen pizzas for June 2016: Units 12" Pizza 16" Pizza Budgeted production volume 13,800 20,800 There are three direct materials used in producing the two types of pizza. The quantities of direct materials expected to be used for each pizza are as follows: 12" Pizza 16" Pizza Direct materials: Dough 0.90 lb. per unit 1.50 lbs. per unit Tomato 0.60 1.00...

  • 1. 2. 3. 4. For February, sales revenue is $564,000, sales commissions are 4% of sales,...

    1. 2. 3. 4. For February, sales revenue is $564,000, sales commissions are 4% of sales, the sales manager's salary is $90,800, advertising expenses are $83,500, shipping expenses total 3% of sale, and miscellaneous selling expenses are $2,600 plus 1/2 of 1% of sales. Total selling expenses for the month of February are Oa. $199,460 Ob. $176,900 Oc. $216,380 Od. $219,200 Production estimates for August for Jay Company are as follows: Estimated inventory (units), August 1 Desired inventory (units), August...

  • Transferred to finished goods in August Inventory in process, August 31 Total units to be assigned...

    Transferred to finished goods in August Inventory in process, August 31 Total units to be assigned costs Cost Information Costs per equivalent unit: Total costs for August in Roasting Department Total equivalent units Cost per equivalent unit (2) Costs assigned to production: Direct Inventory in process, August 1 Costs incurred in August Total costs accounted for by the Roasting Department Costs allocated to completed and partially completed units: Inventory in process, August 1 balance To complete inventory in process, August...

  • Production and sales estimates for April are as follows: 9,000 8,000 Estimated inventory (units), April 1...

    Production and sales estimates for April are as follows: 9,000 8,000 Estimated inventory (units), April 1 Desired inventory (units), April 30 Expected sales volume (units): Area A Area B Area Unit sales price 3,500 4,750 4,250 $20 The budgeted total sales for Aprilis Ca. $270,000 b. $230,000 C. $200,000 d. $250,000 < Previous Next > All work saved Submit Test for Grading

  • Romano’s Frozen Pizza Inc. has determined from its production budget the following estimated production volumes for 12''...

    Romano’s Frozen Pizza Inc. has determined from its production budget the following estimated production volumes for 12'' and 16'' frozen pizzas for September: Units 12" Pizza 16" Pizza Budgeted production volume 13,600 20,500 There are three direct materials used in producing the two types of pizza. The quantities of direct materials expected to be used for each pizza are as follows: 12" Pizza 16" Pizza Direct materials: Dough 0.90 lb. per unit 1.50 lbs. per unit Tomato 0.60 1.00 Cheese...

  • Zira Co. reports the following production budget for the next four months. Production (units) April 662 May 690 June 69...

    Zira Co. reports the following production budget for the next four months. Production (units) April 662 May 690 June 696 July 676 Each finished unit requires four pounds of raw materials and the company wants to end each month with raw materials inventory equal to 30% of next month's production needs. Beginning raw materials inventory for April was 794 pounds. Assume direct materials cost $6 per pound. Prepare a direct materials budget for April, May, and June. (Round your intermediate...

  • CALCULATOR PRINTER VERSION BACK NEXT Exercise 5-13 Concord Auto has developed the following production plan for...

    CALCULATOR PRINTER VERSION BACK NEXT Exercise 5-13 Concord Auto has developed the following production plan for its new auto part, January 11,430 February March 8,880 9,300 April 13,700 Budgeted production (units) Each unit contains 3 pounds of raw material. The desired raw materials ending inventory is 125% of the next month's production needs, plus an additional 598 pounds. January's beginning inventory requirements equal 125% of the current month's production needs, plus an additional 598 pounds Prepare the direct materials purchases...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT