Saved Required information [The following information applies to the questions displayed below Hickory Company manufactures two products-13,000 units of Product Y and 5.000 units of Product Z The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all $829,500 of its manufacturing overhead to four cost pools. The following additional information s available for the company as a whole and for Products Y and 2 Estimated Overhead Activity Measure Activity Cost Pool Machining Machine setups Product design General factory Cost i Expected Activity Machine-hours Number of setups Number of products 5 246,000 12,00 MHs s 137,580 258 setups $ 89,000 2 products Direct lobor-hours s 357,000 14,00 OHs Product Y Product 2 Activity Measure Machine-hours Number of setups Number of products Direct labor-hours 7,588 40 4,5e0 210 8,s00 5,980 activity rate for the Machining activity cost pool? (Round your answer to 2 decimal places) per MH

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Activity rate = Estimated overhead cost / Machine hours
= $246,000 / 12,000
= $20.50 per MH

Add a comment
Know the answer?
Add Answer to:
Saved Required information [The following information applies to the questions displayed below Hickory Company manufactures two...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Savod Required information [The following information applies to the questions displayed below Hickory Company manufactures two...

    Savod Required information [The following information applies to the questions displayed below Hickory Company manufactures two products--13,000 units of Product Y and 5.000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABOC) system that allocates all $829,500 of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z Estimated Overhead Activity...

  • Hickory Company manufactures two products--15,000 units of Product Y and 7,000 units of Product Z. The...

    Hickory Company manufactures two products--15,000 units of Product Y and 7,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and 2. (The total estimated overhead cost may not agree with the sum of allocated overhead costs to...

  • Hickory Company manufactures two products—15,000 units of Product Y and 7,000 units of Product Z. The...

    Hickory Company manufactures two products—15,000 units of Product Y and 7,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: (The total estimated overhead cost may not agree with the sum of allocated overhead costs to...

  • Hickory Company manufactures two products—14,000 units of Product Y and 6,000 units of Product Z. The...

    Hickory Company manufactures two products—14,000 units of Product Y and 6,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool Machining Machine setups Production design General factory Activity Measure Machine-hours Number of setups...

  • Hickory Company

    Hickory Company manufactures two products—13,000 units of Product Y and 5,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all $813,600 of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost PoolActivity MeasureEstimated Overhead CostExpected ActivityMachiningMachine-hours$ 249,60012,000MHsMachine setupsNumber of setups$ 162,400280setupsProduct designNumber of products$ 92,0002productsGeneral...

  • Required information Hickory Company manufactures two products-14,000 units of Product Y and 6,000 units of Product...

    Required information Hickory Company manufactures two products-14,000 units of Product Y and 6,000 units of Product Z. The company uses a plantwide overhead rate based on direct labour-hours. It is considering implementing an activity based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Machining Machine setups Production design General factory Activity Measure Machine-hours Number of setups...

  • Hickory Company manufactures two products—15,000 units of Product Y and 7,000 units of Product Z. The...

    Hickory Company manufactures two products—15,000 units of Product Y and 7,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z. (The total estimated overhead cost may not agree with the sum of allocated overhead costs to...

  • Required information Hickory Company manufactures two products-14,000 units of Product Y and 6,000 units of Product...

    Required information Hickory Company manufactures two products-14,000 units of Product Y and 6,000 units of Product Z. The company uses a plantwide overhead rate based on direct labour-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Machining Machine setups Production design General factory Activity Measure Machin-hours Number of setups Number...

  • Required information The Foundational 15 [LO7-1, LO7-3, L07-4] [The following information applies to the questions displayed...

    Required information The Foundational 15 [LO7-1, LO7-3, L07-4] [The following information applies to the questions displayed below.] Hickory Company manufactures two products—15,000 units of Product Y and 7,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all $765,000 of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y...

  • Hickory Company manufactures two products—15,000 units of Product Y and 7,000 units of Product Z. The company uses a pla...

    Hickory Company manufactures two products—15,000 units of Product Y and 7,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all $674,000 of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool Activity Measure Estimated Overhead Cost Expected Activity Machining Machine-hours $ 216,700 11,000...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT