A production process consists of a three-step operation. The
scrap rate is 19 percent for the first step and 10 percent for the
other two steps.
a.If the desired daily output is 495 units, how
many units must be started to allow for loss due to scrap?
(Do not round intermediate calculations. Round up your
final answer to the next whole number.)
Number of units
b.If the scrap rate for each step could be cut
in half at every operation, how many units would this save in terms
of the scrap allowance? (Do not round intermediate
calculations. Round up your final answer to the next whole
number.)
Number of units
c.If the scrap represents a cost of $10 per
unit, how much is it costing the company per day for the original
scrap rate (i.e. the Part a scrap rate)? (Round your final
answer to the nearest whole number. Omit the "$" sign in your
response.)
Cost $
A. Let X be the original quantity.
The first operation has scrap rate = 19% of original quantity
Scrap = 0.19x
After the first step, quantity remains = original quantity - scrap
= x - 0.19x
= 0.81x
After second operation, scrap of 10%
Scrap = 10% of quantity remaining after operation 1
= 0.10 x 0.81x
=0.081x
Quantity remaining = quantity after operation 1 -scrap
= 0.81x - 0.081x
=0.729x
After third operation, scrap of 10%
Scrap = 10% of quantity remaining after operation 2
Scrap = 0.10 x 0.729x
Scrap = 0.0729x
Quantity remaining = quantity after operation 2 - scrap
= 0.729x - 0.0729x
=0.6561x
Now given that this final quantity remaining is equal to 495 units.
So framing this equation, we get
0.6561x = 495
X = 495/0.6561
X = 754.458
Hence to get 495 units, the original quantity required js 754.48 units or 755 units.
2. The scrap rate is cut in half.
Scrap rate at first operation is = 19/2 = 9.5%
Scrap rate at second and third operation = 10/2 = 5% each
Now let us follow the same process as above.
Let the original quantity be x.
Scrap rate at the end of operation 1 = 9.5% of original quantity.
Scrap rate = 0.095x
Remaining quantity = original quantity - scrap
= x - 0.095x
= 0.905 x
Scrap rate at the end of operation 2 = 5% of quantity remaining after operation 1.
Scrap rate = 0.05 * 0.905x
= 0.04525x
Quantity remaining = Quantity after operation 1 - scrap
= 0.905x - 0.04525x
= 0.85975x
Scrap at the end of operation 3 = 5% of quantity remaining of operation 2
= 0.05 * 0.85975x
= 0.0429875x
Quantity after operation 3 = quantity remaining after operation 2 - scrap
= 0.85975x - 0.0429875x
= 0.8167625x
So the end number of units is given as equal to 495 units.
Or, 0.8167625x = 495
Or, x = 495/0.8149625
X = 606.05 units or 607 units
With the original scrap rate, the units to be introduced were 754 units and now it is 607 units.
Savings in term of scrap allowance = 754 - 607
=147 units.
3. At the original scrap rate, the quantity to be introduced is 754 units.
The quantity remaining after the third operation is 495 units.
Scrap = 754 - 495 = 259 units.
Cost of each unit of scrap = $10
Total scrap cost = 259 x 10 = $2590
A production process consists of a three-step operation. The scrap rate is 19 percent for the...
A production process consists of a three-step operation. The scrap rate is 11 percent for the first step and 8 percent for the other two steps. a.If the desired daily output is 495 units, how many units must be started to allow for loss due to scrap? (Do not round intermediate calculations. Round up your final answer to the next whole number.) Number of units b.If the scrap rate for each step could be cut in half at...
A production process consists of a three-step operation. The scrap rate is 16 percent for the first step and 6 percent for the other two steps. a.If the desired daily output is 485 units, how many units must be started to allow for loss due to scrap? (Do not round intermediate calculations. Round up your final answer to the next whole number.) Number of units b.If the scrap rate for each step could be cut in half at every operation,...
A production process consists of a three-step operation. The scrap rate is 16 percent for the first step and 11 percent for the other two steps. a.If the desired daily output is 494 units, how many units must be started to allow for loss due to scrap? (Do not round intermediate calculations. Round up your final answer to the next whole number.) Number of units b.If the scrap rate for each step could be cut in half at every operation,...
A production process consists of a three-step operation. The scrap rate is 17 percent for the first step and 10 percent for the other two steps. a.If the desired daily output is 484 units, how many units must be started to allow for loss due to scrap? (Do not round intermediate calculations. Round up your final answer to the next whole number.) Number of units 720 b.If the scrap rate for each step could be cut in half at every...
A production process consists of a three-step operation. The scrap rate is 15 percent for the first step and 11 percent for the other two steps. a.lf the desired daily output is 460 units, how many units must be started to allow for loss due to scrap? (Do not round intermediate calculations. Round up your final answer to the next whole number.) Number of units b.lf the scrap rate for each step could be cut in half at every operation,...
A production process consists of a three-step operation. The scrap rate is 12 percent for the first step and 8 percent for the other two steps. a.lf the desired daily output is 482 units, how many units must be started to allow for loss due to scrap? (Do not round intermediate calculations. Round up your final answer to the next whole number.) Number of units b.lf the scrap rate for each step could be cut in half at every operation,...
Problem 10-18 25 A production process consists of a three-step operation. The scrap rate is 12 percent for the first step and 11 percent for the other two steps. 6 points a.lf the desired daily output is 474 units, how many units must be started to allow for loss due to scrap? (Do not round intermediate calculations. Round up your final answer to the next whole number) 0114:45 Number of units b.lf the scrap rate for each step could be...
A production process consist of a three-step operation. The scrap rate is 16% for the first step and 10% for the other two steps a. if they desire daily output is 496 units, how many units must be started to allow for the loss due to the scrap? Do not round intermediate calculations round up your final answer to the next whole number b. if the scrap rate for each step could be cut in half at every operation, how...
Problem 7-11 How many observations should a time study analyst plan for in an operation that has a standard deviation of 1.4 minutes per piece if the goal is to estimate the mean time per piece to within .3 minute with a confidence of 95.5 percent? (Do not round intermediate calculations. Round up your final answer to the next whole number.) Number of observations
Problem 7-11 How many observations should a time study analyst plan for in an operation that...
How many observations should a time study analyst plan for in an operation that has a standard deviation of 1.8 minutes per piece if the goal is to estimate the mean time per piece to within .4 minute with a confidence of 95.5 percent? (Do not round intermediate calculations. Round up your final answer to the next whole number.)