This is a transportation linear programming problem.
a. In order to solve the problem we need to identify decision variables as number of units transported from source to destination. Since there are three sources and four destinations, the number of decision variables will be 3*4 = 12.
b. In order to determine the number of constraints we need to consider the explicit and implicit constraints. Now we know from the table that the supply is limited. Hence using the supply we can see that there will be three constraints. On the other hand, the demand has to be met so there are four destinations and four constraints. These are the 3+4 = 7 explicit constraints. There are also other constraints such as a decision variable cannot be negative and the value of decision variable must be a whole number. However, these are most likely implied so overall we can say that there will be 7 constraints.
After where they need to go (destinations) and distance between sites Baker Hall 10 35 Tirey...
AV Center: Introduction The next four questions refer to the following information: After some special presentations, the employees of the AV Center have to move projectors back to classrooms. The table below indicates the buildings where the projectors are now (the sources), where they need to go (the destinations), and a measure of the distance between sites. Education Parsons Hall Holmstedt Hall Supply Destination Business 10 12 Source Baker Hall Tirey Hall Arena Demand 35 11 10 20 AV Center:...
a. After some special presentations, the employees of the AV Center have to move overhead projectors back to classrooms. The table below indicates the buildings where the projectors are now (the origins), where they need to go (the destinations), and a measure of the distance between sites. Table Q4.a Destination Origin WXY Z Supply 10 95 245 12 1 1615 15 14 78 35 Demand 12 25 18 10 Determine the transport arrangement that minimizes the total transport distance.
a....
Create a worksheet called "Transport a. Enter the following transportation model into excel following the linear programming layout. Hint: this is unbalanced Make sure to include your 1) decision variables, 2) objective function, 3) constraints, 4) inequalities, 5) confounds, 6) and solution b. c. Once you run your model, select "keep solver solution". Name the sheet that's created "solution_basic" DESTINATIONS 13 20 20 25 10 12 30 16 35 20 30 25
The vertical distance between points A and B represents a tax in the market. Price 15 14 13 12t Supply 10 Demand s 10 15 20 25 30 35 40 4 50 35 60 65 70 75 80 8 uantity Refer to Figure 8-4. The price that buyers effectively pay after the tax is imposed is $12. between $8 and $12. between $5 and $8. S5 Previous Page Next Page
Hey guys, I am struggling with this problem. I dont know where
to begin with. I have to make a model in excel for this problem and
solve from A to D. Can someone help me solving this problem by
showing each step please ? I would really apprecite it. PS: please
make to put a clear picture and a good explanation about the answer
you come up with.
Problem 4 (6 points Baseball umpiring crews are currently in four...
(I just need Question 2)Please show the steps
clearly
contract to produce 10 items of x per week for a particular customer. • Part (a). Formulate the problem of deciding how much to produce per week as a linear program. • Part (b). Draw the feasible region of your LP formulation. • Part (c). Find the optimal solution of your LP model using graphical solution method. 2. Consider a factory that produces tables. The demand for the tables is known...
1. Refer to the Class Commute Data, and let the independent variable Distance (between home and school) and the dependent variable Leave (one-way commute time to school). Using matrix method and the selected variables from the Class Data, obtain the following for an OLS simple linear regression model: Matrices Y, X and ß a. ons developed by the method of least squares c. Get B from (b), and write the fitted regression line. Return Home Leave Home to From Schoo...
5. Charming City Foods manufactures a snack bar by blending two ingredients: a nut mix and a granola mix. Information about the two ingredients (per ounce) is shown below Ingredient Nut Mi:x Granola Mix Cost In Dollars 0.90 0.50 Fat Grams 24 4 Calories 650 60 Protein Grams The company needs to develop a linear programming model whose solution would tell them how many ounces of each mix to put into the snack bar. The blend should contain no more...
1. A manufacturing company would like to maximize the profit of manufacturing four products. The time in hours required for each product in each production department is tabled below, along with the profit for each product. Product 1 Product 2 Product 3 Product 4 Department A 25 20 30 15 Department B 12 10 10 15 Department C 8 7 5 6 Profit $110 $90 100 95 Currently, labor assignments provide for 4800 hours in Department A, 3000 hours in Department...
QUESTION 7 Figure: The vertical distance between points A and C represents a tax in the market. T Price Supply 1000 900+ 800 700+ 600 + 500+ 400 300 C 200+ 100 Demand 10 20 30 40 50 60 70 80 90 100110 Quantty Refer to Figure. After the taxes a. there will be a loss to the consumers of the amount $4,000. Б. there will be a loss to the consumers of the amount S6,000. Cthere will be a...