Total time taken from A-F is 120+80+100+120+60+40+60+40+40=660 seconds
A) operating speed = 3250/660 = 4=92m/s
Cycle time = 480+240+150*2 = 1020 seconds
B)
Question 1 A rail shuttle line with a length L-3250m has 6 stations. The travel time...
Question 1- Assembly Line Balancing A ball-bearing assembly firm wants to set up an assembly line that must have an output of 60 units per hour. The work elements, task times and their precedence relationships are shown in Table 1: Table 1 Work Element Time (sec.) Immediate Predecessor(s) A 40 NONE B 30 A C 50 A D 40 B E 6 B F 25 C G 15 C H 20 D, E I 18 F, G J 30 H,...