Question

D E F G H K G#: Copy Formulas A B C 1 Chapter 3: Applying Excel Name: 2 3 Data 4 Allocation base Machine-hours Estimated manuA B C L D G H к Req. 1: Enter 60,000 machine hours in the estimated total amount of the allocation base cell in the data sectA B D E G H к Req. 2 Enter the data from requirement 2 on page 133 of the textbook in the green data cells on the left of thiA B C F D E G H J K Req. 3: Enter 40,000 machine hours in the estimated total amount of the allocation base cell In the dataA B C E G H K Req. 4: Enter $100,000 in the actual manufacturing overhead cost base cell in the data section at the left. Wha

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Data
Allocation Base Machine-Hours
Estimated Manufacturing Overhead Cost $300,000
Estimated Total amount of the allocation base 75,000 machine-hours
Actual Manufacturing Overhead Cost $290,000
Actual Total Amount of the allocation base 68,000 machine-hours
Computation of the predetermined overhead rate
Estimated Manufacturing Overhead Cost $300,000
Estimated Total amount of the allocation base 75,000 machine-hours
Predetermined Overhead Rate $4 per machine -hour
Computation of underapplied or overappplied manufacturing overhead
Actual Manufacturing Overhead Cost $290,000
Manufacturing Overhead Cost applied to work in process during the year
   Predetermined Overhead Rate $4
   Actual Total Amount of the allocation base 68,000
   Manufacturing Overhead Applied $272,000
Underapplied (overapplied) Manufacturing Overhead $18,000

You may look the following for the formulae reference:

Data
Allocation Base Machine-Hours
Estimated Manufacturing Overhead Cost 300000
Estimated Total amount of the allocation base 75000 machine-hours
Actual Manufacturing Overhead Cost 290000
Actual Total Amount of the allocation base 68000 machine-hours
Computation of the predetermined overhead rate
Estimated Manufacturing Overhead Cost =D245
Estimated Total amount of the allocation base =D246 machine-hours
Predetermined Overhead Rate =D251/D252 per machine -hour
Computation of underapplied or overappplied manufacturing overhead
Actual Manufacturing Overhead Cost =D247
Manufacturing Overhead Cost applied to work in process during the year
   Predetermined Overhead Rate =D253
   Actual Total Amount of the allocation base =D248
   Manufacturing Overhead Applied =D258*D259
Underapplied (overapplied) Manufacturing Overhead =D256-D260
Add a comment
Know the answer?
Add Answer to:
D E F G H K G#: Copy Formulas A B C 1 Chapter 3: Applying...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • A B C D E F H J M N Name: G# 1 Chapter 3: Applying...

    A B C D E F H J M N Name: G# 1 Chapter 3: Applying Excel 2 3 Data 4 Allocationibus 5 Estimated manufacturing overhead cost 6 Estimated total amount of the allocation base 7 Actual manufacturing overhead cost B Actual total amount of the allocation base Machine-hours $300,000 75,000 machine-hours $290,00D 68,00D machine-hours Copy Formulas 10 Enfer a formula into each of the green cells marked with a 7 below. Once complete use the "Copy Formula" button. 11...

  • Chapter 3: Applying Excel Data Allocation base Machine-hours Estimated manufacturing overhead cost $300,000 Estimated total amount...

    Chapter 3: Applying Excel Data Allocation base Machine-hours Estimated manufacturing overhead cost $300,000 Estimated total amount of the allocation base 60,000 machine-hours Actual manufacturing overhead cost $290,000 Actual total amount of the allocation base 68,000 machine-hours Enter a formula into each of the cells marked with a ? below Computation of the predetermined overhead rate Estimated manufacturing overhead cost ? Estimated total amount of the allocation base ? machine-hours Predetermined overhead rate ? per machine-hour Computation of underapplied or overapplied...

  • A B C 1 2 3 4 5 6 7 8 Chapter 3: Applying Excel Data...

    A B C 1 2 3 4 5 6 7 8 Chapter 3: Applying Excel Data Allocation base Machine-hours Estimated manufacturing overhead cost $290,700 Estimated total amount of the allocation base 57,000 machine-hours Actual manufacturing overhead cost $273,700 Actual total amount of the allocation base 60,000 machine-hours (a) By how much is the manufacturing overhead underapplied or overapplied? (b) Why is the amount of underapplied (overapplied) manufacturing overhead different from Requirement 2 above? (you can select one or more) The...

  • Where the ? marks are, there needs to be a formula. Thanks! Thanks for the Help...

    Where the ? marks are, there needs to be a formula. Thanks! Thanks for the Help :) A 1 Chapter 3: Applying Excel 3 Data 4 Allocation base 5 Estimated manufacturing overhead cost 6 Estimated total amount of the allocation base 7 Actual manufacturing overhead cost 8 Actual total amount of the allocation base 9 10 Enter a formula into each of the cells marked with a ? below Machine-hours $300,000 75,000 machine-hours $290,000 68,000 machine-hours 11 ? machine-hours ?...

  • Data Allocation base Machine-hours Estimated manufacturing overhead cost $300,000 Estimated total amount of the allocation base...

    Data Allocation base Machine-hours Estimated manufacturing overhead cost $300,000 Estimated total amount of the allocation base 75,000 machine-hours Actual manufacturing overhead cost $290,000 Actual total amount of the allocation base 68,000 machine-hours Computation of the predetermined overhead rate Estimated manufacturing overhead cost ? Estimated total amount of the allocation base ? machine-hours Predetermined overhead rate ? per machine-hour Computation of underapplied or overapplied manufacturing overhead Actual manufacturing overhead cost ? Manufacturing overhead cost applied to Work in Process during the...

  • Chapter 3: Applying Excel: Exercise 2. Change all of the numbers in the data area of...

    Chapter 3: Applying Excel: Exercise 2. Change all of the numbers in the data area of your worksheet so that it looks like this: с 1 Chapter 3: Applying Excel 2 3 4 5 Data Allocation base Estimated manufacturing overhead cost Estimated total amount of the allocation base Actual manufacturing overhead cost Actual total amount of the allocation base 6 Machine-hours $ 275,600 52.000 machine-hours $ 261,600 50,000 machine-hours 7 00 If your formulas are correct, you should get the...

  • A B C 1 2 3 4 5 6 7 8 Chapter 3: Applying Excel Data...

    A B C 1 2 3 4 5 6 7 8 Chapter 3: Applying Excel Data Allocation base Machine-hours Estimated manufacturing overhead cost $290,700 Estimated total amount of the allocation base 57,000 machine-hours Actual manufacturing overhead cost $281,700 Actual total amount of the allocation base 60,000 machine-hours (a) What is the Predetermined overhead rate? (Round your answer to 2 decimal places. (b) By how much is the manufacturing overhead underapplied or overapplied?

  • A B C 1 2 3 4 5 6 7 8 Chapter 3: Applying Excel Data...

    A B C 1 2 3 4 5 6 7 8 Chapter 3: Applying Excel Data Allocation base Machine-hours Estimated manufacturing overhead cost $290,700 Estimated total amount of the allocation base 51,000 machine-hours Actual manufacturing overhead cost $281,700 Actual total amount of the allocation base 60,000 machine-hours (a) By how much is the manufacturing overhead underapplied or overapplied? (b) Why is the amount of underapplied (overapplied) manufacturing overhead different from Requirement 2 above? (you can select one or more below)...

  • Required information Chapter 3: Applying Excel Step 1: Download the Applying Excel form located on the...

    Required information Chapter 3: Applying Excel Step 1: Download the Applying Excel form located on the left-hand side, under files. If you have trouble, the file is also located in D2L under Course Administration. Step 2: Then enter formulas in all cells that contain question marks. For example, in cell B13 enter the formula "=B5". Step 3: Check your worksheet by changing the estimated total amount of the allocation base in the Data area to 50,000 machine-hours, keeping all of...

  • help me do the journal entry Given Data for Lab 2 This company applies manufacturing overhead...

    help me do the journal entry Given Data for Lab 2 This company applies manufacturing overhead on the basis of machine-hours. Below is information for the most recently completed year of operations. Bellingham Manufacturing, Inc. Estimated total manufacturing overhead cost Estimated total amount of allocation base $ 510,000 75,000 machine-hours Actual total manufacturing overhead cost Actual total machine-hours $ 468,000 72,000 Bellingham Manufacturing, Inc. Manufacturing Overhead Report For the year ended Dec. 31, 2019 Computation of Predetermined Overhead Rate (POHR):...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT