Edelman Engineering is considering including two pieces of equipment, a truck and an overhead pulley system, in this year's capital budget. The projects are independent. The cash outlay for the truck is $17,100 and that for the pulley system is $22,430. The firm's cost of capital is 14%. After-tax cash flows, including depreciation, are as follows:
Year | Truck | Pulley | ||
1 | $5,100 | $7,500 | ||
2 | 5,100 | 7,500 | ||
3 | 5,100 | 7,500 | ||
4 | 5,100 | 7,500 | ||
5 | 5,100 | 7,500 |
Calculate the IRR for each project. Round your answers to two decimal places.
Truck: %
What is the correct accept/reject decision for this project?
-Select-AcceptRejectItem 2
Pulley: %
What is the correct accept/reject decision for this project?
-Select-AcceptRejectItem 4
Calculate the NPV for each project. Round your answers to the nearest dollar, if necessary. Enter each answer as a whole number. For example, do not enter 1,000,000 as 1 million.
Truck: $
What is the correct accept/reject decision for this project?
-Select-AcceptRejectItem 6
Pulley: $
What is the correct accept/reject decision for this project?
-Select-AcceptRejectItem 8
Edelman Engineering is considering including two pieces of equipment, a truck and an overhead pulley system, in this year's capital budget. The projects are independent. The cash outlay for the truck is $17,100 and that for the pulley system is $22,430. The firm's cost of capital is 14%. After-tax cash flows, including depreciation, are as follows:
Year | Truck | Pulley | ||
1 | $5,100 | $7,500 | ||
2 | 5,100 | 7,500 | ||
3 | 5,100 | 7,500 | ||
4 | 5,100 | 7,500 | ||
5 | 5,100 | 7,500 |
Calculate the IRR for each project. Round your answers to two decimal places.
Truck: %
What is the correct accept/reject decision for this project?
-Select-AcceptRejectItem 2
Pulley: %
What is the correct accept/reject decision for this project?
-Select-AcceptRejectItem 4
Calculate the NPV for each project. Round your answers to the nearest dollar, if necessary. Enter each answer as a whole number. For example, do not enter 1,000,000 as 1 million.
Truck: $
What is the correct accept/reject decision for this project?
-Select-AcceptRejectItem 6
Pulley: $
What is the correct accept/reject decision for this project?
-Select-AcceptRejectItem 8
1.
IRR of project
Truck
=IRR({-17100;5100;5100;5100;5100;5100})
=14.99%
Pulley
=IRR({-22430;7500;7500;7500;7500;7500})
=20.00%
2.
Truck Accept
Pulley Accept
3.
NPV of project
Truck
=NPV(14%,{-17100;5100;5100;5100;5100;5100})*(1+14%)
=408.71294
Pulley
=NPV(14%,{-22430;7500;7500;7500;7500;7500})*(1+14%)
=3318.10727
4.
Truck Accept
Pulley Accept
Edelman Engineering is considering including two pieces of equipment, a truck and an overhead pulley system,...
Edelman Engineering is considering including two pieces of equipment, a truck and an overhead pulley system, in this year's capital budget. The projects are independent. The cash outlay for the truck is $18,000, and that for the pulley system is $22,000. The firm's cost of capital is 14%. After-tax cash flows, including depreciation, are as follows: Year Truck Pulley 1 $5,100 $7,500 2 5,100 7,500 3 5,100 7,500 4 5,100 7,500 5 5,100 7,500 Calculate the IRR, the NPV, and...
Edelman Engineering is considering including two pieces of equipment, a truck and an overhead pulley system, in this year's capital budget. The projects are independent. The cash outlay for the truck is $15,000 and that for the pulley system is $21,000. The firm's cost of capital is 11%. After-tax cash flows, including depreciation, are as follows: Year Truck Pulley 1 $5,100 $7,500 2 5,100 7,500 3 5,100 7,500 4 5,100 7,500 5 5,100 7,500 Calculate the IRR for each project....
Edelman Engineering is considering including two pieces of equipment, a truck and an overhead pulley system, in this year's capital budget. The projects are independent. The cash outlay for the truck is $15,000 and that for the pulley system is $21,000. The firm's cost of capital is 11%. After-tax cash flows, including depreciation, are as follows: Year Truck Pulley 1 $5,100 $7,500 2 5,100 7,500 3 5,100 7,500 4 5,100 7,500 5 5,100 7,500 Calculate the IRR for each project....
NPVs, IRRs, and MIRRs for Independent Projects Edelman Engineering is considering including two pieces of equipment, a truck and an overhead pulley system, in this year's capital budget. The projects are independent. The cash outlay for the truck is $18,000 and that for the pulley system is $22,000. The firm's cost of capital is 14%. After-tax cash flows, including depreciation, are as follows: Year Truck Pulley 1 $5,100 $7,500 2 5,100 7,500 3 5,100 7,500 4 5,100 7,500 5 5,100...
NPVS, IRRs, and MIRRs for Independent Projects Edelman Engineering is considering including two pieces of equipment, a truck and an overhead pulley system, in this year's capital budget. The projects are independent. The cash outlay for the truck is $19.000 and that for the puley system is $20,000. The firm's cost of capitals 12%. After-tax cash flows, including depreciation, are as follows: Year Truck Pulley 1 $5,100 $7,500 2 5 ,100 7,500 3 5 ,100 7,500 4 5,100 7,500 5,100...
*accept/reject decision for each NPVS IRRs and MIRRs for Independent Projects - 3 points Edelman Engineering is considering including two pieces of equipment, a truck and an overhead pulley system, in this year's capital budget. The projects are independent. The cash outlay for the truck is $17,100 and that for the pulley system is $22,430. The firm's cost of capital is 14%. After tax cash flows including depreciation are as follows: Year Truck Pulley 1 5,100 7,500 2 5,100 7,500...
Part C: Calculate MIRR for Puley also. Its cut off from the picture. Thanks Problem 10-08 NPVS, IRRS, and MIRRS for Independent Projects Edelman Engineering is considering including two pieces of equipment, a truck and an overhead pulley system, in this year's capital budget. The projects are independent. The cash outlay for the truck is $17,100 and that for the pulley system is $22,430. The firm's cost of capital is 14 %. After - tax cash flows, including depreciation, are...
for the truck $17,100 and that for the pulley system is $27,430. The firm's cost of capital is Problem 10-09 NPVS, IRRS, and HTRRS for Independent Projects Fidelman Engineering is considering including two pieces of equlament, a truck and an overhead pullay system, In this year's capital budget. The projects are independent. The cash out 14%. After-tax cash flons, induding depreciation, are as follows: Year Truck Pulley $5.100 $7,500 5,100 7,500 5,100 5.100 7.500 5,100 7,500 a. Calculate the IRR...
Score: /12 Attempts: 11. Problem 10-08 eBook Problem 10-08 NPVS, IRRs, and MIRRs for Independent Projects Edelman Engineering is considering including two pieces of equipment, a truck and an overhead pulley system, in tax cash flows, including depreciation, are as follows: Pulley $7,500 Year Truck $5,100 5,100 5,100 5,100 5,100 7,sv0 7,500 7,500 7,500 a. Calculate the IRR for each project Round your answers to two decimal places. Truck: what is the correct accept/reject decision for this project? Pulley: What...
8. A project has an initial cost of $71,950, expected net cash inflows of $9,000 per year for 6 years, and a cost of capital of 10%. What is the project's PI? Do not round your intermediate calculations. Round your answer to two decimal places. 9. A project has an initial cost of $54,925, expected net cash inflows of $12,000 per year for 8 years, and a cost of capital of 11%. What is the project's payback period? Round your...