Question

Skylark has forecast production for the next three months as follows: July 4.900 units, August 6,600...

Skylark has forecast production for the next three months as follows: July 4.900 units, August 6,600 units, September 7,500 units. Monthly manufacturing overhead is budgeted to be $17,000 plus $6 per unit produced. What is budgeted manufacturing overhead for August ?

a) $ 39,600
b) $56,600
c) $17,000
d) $62,000
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer = Skylark Has Forecast Production

August = 6,600 units

Monthly manufacturing Overhead is Budgeted = $17,000 Plus $ 6 Per Unit Produced

Budgeted Manufacturing Overhead for August = $17,000 + ( $6*6,600 )

= $17,000 + $39,600

Answer :- Budgeted Manufacturing Overhead for August = $56,600

Hence, The option (B) is Correct $56,600 and other options are incorrect.

Add a comment
Know the answer?
Add Answer to:
Skylark has forecast production for the next three months as follows: July 4.900 units, August 6,600...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Larken has forecast sales for the next three months as follows: July 4,000 units, August 6,000...

    Larken has forecast sales for the next three months as follows: July 4,000 units, August 6,000 units, September 7,500 units. Larken’s policy is to have an ending inventory of 40% of the next month's sales needs on hand. July 1 inventory is projected to be 1,600 units. Monthly manufacturing overhead is budgeted to be $17,000 plus $5 per unit produced. What is budgeted manufacturing overhead for July? $41,500 $24,500 $47,000 $27,000

  • Marlow Company produces hand tools. A production budget for the next four months is as follows:...

    Marlow Company produces hand tools. A production budget for the next four months is as follows: March 10,300 units, April 13,300, May 16,500, and June 21,800. Marlow Company's ending finished goods inventory policy is 10 % of the following month's sales. Meadow plans to sell 16,000 units in May How many units will be sold in April? Multiple Choice 13,000 12,380 13.570 13,620 Skylark has forecast production for the next three months as follows: July 4,900 units, August 6,600 units,...

  • Pacific has forecast sales for the next three months as follows: July 4,000 units, August 6,000...

    Pacific has forecast sales for the next three months as follows: July 4,000 units, August 6,000 units, September 7,500 units. Pacific's policy is to have an ending inventory of 40% of the next month's sales needs on hand. July 1 inventory is projected to be 1,500 units. Monthly costs are budgeted as follows: Fixed manufacturing costs $ 17,000 Fixed selling costs $ 10,000 Fixed administrative costs $ 8,300 Variable manufacturing costs $ 5 per unit produced Variable selling costs $...

  • Skybird has forecast sales for the next three months as follows: 4.000 units, August 6.000 units,...

    Skybird has forecast sales for the next three months as follows: 4.000 units, August 6.000 units, September 7.500 is projected to be 1500 units, Morthy costs are budgeted as follows . Skybudspolicy is to have an ending hertory of 40% of the next more on hand try $17.000 $10.00 Fixed manufacturing costs Fixed selling costs Fixed administrative costs Variable manufacturing costs Variable selling costs 8,00 $6 per unit produced What is budgeted manufacturing overhead cout for July? M Choice 0...

  • Bengal Co. provides the following sales forecast for the next three months: Sales units July August...

    Bengal Co. provides the following sales forecast for the next three months: Sales units July August September 7,500 8,200 6,600 The company wants to end each month with ending finished goods inventory equal to 25% of the next month's sales. Finished goods inventory on June 30 is 1,875 units. The budgeted production units for August are: Multiple Choice 6,375 units 9,850 units. 6,550 units 10.075 units

  • Bengal Co. provides the following unit sales forecast for the next three months: July August September...

    Bengal Co. provides the following unit sales forecast for the next three months: July August September Sales units 5,000 5,700 5,560 The company wants to end each month with ending finished goods inventory equal to 25% of the next month's sales. Finished goods inventory on June 30 is 1,250 units. The budgeted production units for July are: Multiple Choice 2,500 units. 3,750 units. 6,425 units. 5,175 units. 6,250 units.

  • The production budget for Manner Company shows units to be produced as follows: July, 670; August,...

    The production budget for Manner Company shows units to be produced as follows: July, 670; August, 730; and September, 590. Each unit produced requires three hours of direct labor. The direct labor rate is currently $15 per hour but is predicted to be $15.75 per hour in September Prepare a direct labor budget for the months July, August, and September. MANNER COMPANY Direct Labor Budget For July, August, and September July August 670 730 September 590 units Budgeted production (units)...

  • Bengal Co. provides the following sales forecast for the next three months: July August September Sales...

    Bengal Co. provides the following sales forecast for the next three months: July August September Sales units 12,000 12,700 6,300 The company wants to end each month with ending finished goods inventory equal to 25% of the next month's sales. Finished goods inventory on June 30 is 3,000 units. The budgeted production units for August are: Multiple Choice 15,700 units. 11,125 units. 14,275 units. 11,100 units. 10,950 units.

  • The production budget for Manner Company shows units to be produced as follows: July, 620; August,...

    The production budget for Manner Company shows units to be produced as follows: July, 620; August, 680; and September, 540. Each unit produced requires two hours of direct labor. The direct labor rate is currently $20 per hour but is predicted to be $21 per hour in September. Augustus is predicted to be 25 Prepare a direct labor budget for the months July, August, and September. MANNER COMPANY Direct Labor Budget For July, August, and September July August 620 680...

  • The production budget for Manner Company shows units to be produced as follows: July, 590; August, 650; and Septemb...

    The production budget for Manner Company shows units to be produced as follows: July, 590; August, 650; and September, 510. Each unit produced requires one hour of direct labor. The direct labor rate is currently $16 per hour but is predicted to be $16.75 per hour in September Prepare a direct labor budget for the months July, August, and September. MANNER COMPANY Direct Labor Budget For July, August, and September July August 590 Budgeted production (units) September 510 units Total...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT