Question

Activity-Based Quality Costing Abernathy, Inc., produces two different generators and is concerned about their quality. The c

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Generator A Generator B
Activities Cost $ Cost Driver Usage Activity Rate $ Cost Driver Usage Cost $ Cost Driver Usage Cost $
Performing warranty work 810730 2510 323 1710 552330 800 258400
Scrapping units 612020 4310 142 3430 487060 880 124960
Inspecting 318060 5130 62 3380 209560 1750 108500
Quality training 82328 164 502 82 41164 82 41164
Total cost $ 1823138 1290114 533024
Divide by: Number of units produced 167400 347700
Unit cost $ 7.71 1.53

Answer: Generator A

Generator A seems to have the lowest quality since the unit cost of quality for Generator A is higher at $7.71 than for Generator B at $1.53.

Add a comment
Know the answer?
Add Answer to:
Activity-Based Quality Costing Abernathy, Inc., produces two different generators and is concerned about their quality. The...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Activity-Based Quality Costing Abernathy, Inc., produces two different generators and is concerned about their quality....

    Activity-Based Quality Costing Abernathy, Inc., produces two different generators and is concerned about their quality. The company has identified the following quality activities and costs associated with the two products: Generator A Generator B 349,900 860 Units produced Warranty work (units) Scrapped units (number) Inspection (hours) Quality training (hours) 167,900 1,750 3,430 3,470 820 1,680 86 Activities: $832,590 633,250 Performing warranty work Scrapping units Inspecting Quality training 303,850 85,140 Required: 1. Calculate the quality cost per unit for each product,...

  • Exercise 14.11 Activity-Based Quality Costing Abernathy, Inc., produces two different generators and is concerned about their...

    Exercise 14.11 Activity-Based Quality Costing Abernathy, Inc., produces two different generators and is concerned about their quality The company has identified the following quality activities and costs associated with the two products: Generator A Generator B 170,000 1,700 3,400 3,400 85 340.000 850 850 1,700 85 Units produced Warranty work (units) Scrapped units (number) Inspection (hours) Quality training (hours) Activities: Performing warranty work Scrapping units Inspecting Quality training $816,000 612,000 306,000 85,000 Required: 1. Calculate the quality cost per unit...

  • External Linkages, Activity-Based Supplier Costing Jackson, Inc., manufactures motorcycles. Jackson produces all the components necessary for...

    External Linkages, Activity-Based Supplier Costing Jackson, Inc., manufactures motorcycles. Jackson produces all the components necessary for the production of the cycles except for one (a carburetor). This component is purchased from two local suppliers: Harvey Parts and Curtis, Inc. Harvey sells the component for $63 per unit, while Curtis sells the same component for $56. Because of the lower price, Jackson purchases 75 percent of its components from Curtis Jackson purchases the remaining 25 percent from Harvey to ensure an...

  • External Linkages, Activity-Based Supplier Costing Jackson, Inc., manufactures motorcycles. Jackson produces all the components necessary for...

    External Linkages, Activity-Based Supplier Costing Jackson, Inc., manufactures motorcycles. Jackson produces all the components necessary for the production of the cycles except for one (a carburetor). This component is purchased from two local suppliers: Harvey Parts and Curtis, Inc. Harvey sells the component for $67 per unit, while Curtis sells the same component for $61. Because of the lower price, Jackson purchases 75 percent of its components from Curtis. Jackson purchases the remaining 25 percent from Harvey to ensure an...

  • Activity-Based Supplier Costing Bowman Company manufactures cooling systems. Bowman produces all the parts necessary for its...

    Activity-Based Supplier Costing Bowman Company manufactures cooling systems. Bowman produces all the parts necessary for its product except for one electronic component, which is purchased from two local suppliers: Manzer Inc. and Buckner Company. Both suppliers are reliable and seldom deliver late; however, Manzer sells the component for $89 per unit, while Buckner sells the same component for $86. Bowman purchases 80% of its components from Buckner because of its lower price. The total annual demand is 4,000,000 components. To...

  • Activity-Based Supplier Costing Bowman Company manufactures cooling systems. Bowman produces all the parts necessary for its...

    Activity-Based Supplier Costing Bowman Company manufactures cooling systems. Bowman produces all the parts necessary for its product except for one electronic component, which is purchased from two local suppliers: Manzer Inc. and Buckner Company. Both suppliers are reliable and seldom deliver late; however, Manzer sells the component for $89 per unit, while Buckner sells the same component for $86. Bowman purchases 80% of its components from Buckner because of its lower price. The total annual demand is 4,000,000 components. To...

  • eBook Calculator Activity-Based Product Costing Roberts Company produces two weed eaters: basic and advanced. The company...

    eBook Calculator Activity-Based Product Costing Roberts Company produces two weed eaters: basic and advanced. The company has four activities: machining, engineering, receiving, and inspection. Information on these activities and their drivers is given below. Basic Advanced Total Units produced 150,000 450,000 Prime costs $12,600,000 $45,000,000 $57,600,000 900,000 Machine hours 150,000 750,000 500 4,500 5,000 Engineering hours Receiving orders Inspection hours 200 600 800 800 1,600 2,400 Overhead costs: Machining Engineering $9,000,000 2,100,000 320,000 Receiving Inspecting products 480,000 Required: 1. Calculate...

  • Activity Rates and Product Costs using Activity-Based Costing Lonsdale Inc. manufactures entry and dining room lighting...

    Activity Rates and Product Costs using Activity-Based Costing Lonsdale Inc. manufactures entry and dining room lighting fixtures. Five activities are used in manufacturing the fixtures. These activities and their associated budgeted activity costs and activity bases are as follows: Budgeted Activity Activity Cost Activity Base Casting $238,510 Machine hours Assembly 200,940 Direct labor hours Inspecting 31,360 Number of inspections Setup 51,840 Number of setups Materials handling 35,200 Number of loads Corporate records were obtained to estimate the amount of activity...

  • eBook Calculator Activity-Based Product Costing Roberts Company produces two weed eaters: basic and advanced. The company...

    eBook Calculator Activity-Based Product Costing Roberts Company produces two weed eaters: basic and advanced. The company has four activities: machining, engineering, receiving, and inspection. Information on these activities and their drivers is given below. Basic Advanced Total Units produced 300,000 100,000 $8,000,000 Prime costs $30,000,000 $38,000,000 Machine hours 100,000 500,000 600,000 Engineering hours 400 3,600 4,000 Receiving orders 400 1,200 1,600 Inspection hours 800 1,600 2,400 Overhead costs: Machining Engineering Receiving Inspecting products $6,000,000 2,000,000 560,000 360,000 Required: 1. Calculate...

  • eBook Calculator Activity-Based Product Costing Roberts Company produces two weed eaters: basic and advanced. The company...

    eBook Calculator Activity-Based Product Costing Roberts Company produces two weed eaters: basic and advanced. The company has four activities: machining, engineering, receiving and inspection. Information on these activities and their drivers is given below. Basic Advanced Total Units produced 100,000 300,000 Prime costs $8,000,000 $30,000,000 $38,000,000 Machine hours 100,000 500,000 600,000 Engineering hours 400 3.600 4,000 Receiving orders 400 1,600 2.400 800 Inspection hours 1,200 1,600 Overhead costs: Machining Engineering Receiving Inspecting products Required: $6,000,000 2,000,000 560,000 360,000 х Removing...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT