Pls find below the steps, workings and answer;
Answer: 7.57%
(Numbers in parentheses are negative) These two projects are independent. Year Cash Flow of A Cash...
Question 6 5 pts (Numbers in parentheses are negative) These two projects are independent. Year Cash Flow of A Cash Flow of B 0 ($5000) ($2000) 1 $1000 $1000 2 $2000 $1000 3 $2000 $2000 4. $2000 $1000 5 $1000 ($1000) What is the approximate crossover point between the two projects if the required rate of return is 9.5%? 12.39% O 7.24% There is no crossover point in this case. 0 7.57% O 6.12% Question 7 5 pts (Numbers in...
(Numbers in parentheses are negative) These two projects are independent. Year Cash Flow of A Cash Flow of B o ($5000) ($2000) 1 $1000 $1000 $2000 $1000 3 $2000 $2000 4 $2000 $1000 5 $1000 ($1000) N What is the approximate profitability index for project B if the required rate of return is 9.5%? O (1.27) (1.32) O 1.32 O 1.51 O 1.27
(Numbers in parentheses are negative cash flows) These two projects are independent. Year Cash Flow of A Cash Flow of B 0 ($5000) ($2000) 1 $1000 $1000 2 $2000 $1000 3 $2000 $2000 4 $2000 $1000 5 $1000 ($1000) What is the approximate NPV of project A if the required rate of return is 9.5%? $390 $572 $581 $1131 $3000
(Numbers in parentheses are negative cash flows) These two projects are independent. Year Cash Flow of A Cash Flow of B 0 ($5000) ($2000) $1000 $1000 2 $2000 $1000 3 $2000 $2000 4 $2000 $1000 5 $1000 ($1000) 1 What is the approximate IRR of project A if the required rate of return is 9.5%? 40.97% O 17.74% 15.84% O 14.85% O 15.34%
(Numbers in parentheses are negative) These two projects are independent. Year Cash Flow of A Cash Flow of B 0 ($5000) ($2000) 1 $1000 $1000 2 $2000 $1000 3 $2000 $2000 4 $2000 $1000 5 $1000 ($1000) Based on the firms' NPV profiles which project should be taken if the required rate of return is 9.5%? Project B because it will raise the value of the firm by the greatest amount based on NPV. Both projects should be taken because...
select the right answer.
Question 4 5 pts (Numbers in parentheses are negative cash flows) These two projects are independent. Year Cash Flow of A Cash Flow of B 0 ($5000) ($2000) $1000 $1000 2 $2000 $1000 3 $2000 $2000 4 $2000 $1000 5 $1000 ($1000) 1 What is the approximate payback of project B if the required rate of return is 9.5%? 4.00 years The payback cannot be calculated. 0 2.00 years O 3.00 years O 3.50 years Question...
6. Use the following after-tax cash flows for project A and B to answer the following question: (Numbers in parentheses are negative cash flows). These two projects are independent. Year Cash Flow of A Cash Flow of B 0 ($2,400) ($4,500) 1 $999 $800 2 $950 $950 3 ( $150) $950 4 $910 $800 5 $990 $900 6 ( $500) $1980 What is the approximate IRR of project A if the required rate of...
Question 7 5 pts Use the following after-tax cash flows for project A and B to answer the following question: (Numbers in parentheses are negative cash flows). These two projects are independent Year Cash Flow of A Cash Flow of B 0 ($2,400) ($4,500) 1 $999 $800 2 $950 $950 3 ($150) $950 $910 $800 5 $990 $900 6 ($500) $1980 What is the approximate payback of project B if the required rate of return is 10%? 4.56 years 6...
ABC Inc. is considering a project with following cash flow. Cash flow in parentheses denote negative flows: Year Cash Flow (200,000) 120,000 120,000 ? 120,000 K is 10 percent.The project’s modified internal rate of return (MIRR) is 16.38%. What is the expected cash flow in year 3? What is NPV of proeject?
Question 9 5 pts Use the following after-tax cash flows for project A and B to answer the following question: (Numbers in parentheses are negative cash flows). These two projects are independent Year Cash Flow of A Cash Flow of B 0 ($2,400) ($4,500) 1 $999 $800 2 $950 $950 3 ($150) $950 4 $910 $800 5 $990 $900 6 ($500) $1980 Which project should be taken if the required rate of return is 10%? o Take both projects o...