NPV will be
=initial investment including issue costs+CF/(ke-g)
=(-900-15)+100/(10%-3%)
=513.57 million
Ford Motors expects a new hybrid-engine project to produce incremental cash flows of $100 million each...
Ford Motors expects a new hybrid-engine project to produce incremental cash flows of $45 million each year, and expects these to grow at 3% each year. The upfront project costs are $380 million and Ford's weighted average cost of capital is 10%. If the issuance costs for external finances are $10 million, what is the net present value (NPV) of the project? O A. $278 million O B. $253 million O C. $266 million OD. $228 million
Ford Motors expects a new hybrid-engine project to produce incremental cash flows of $60 million each year, and expects these to grow at 4% each year. The upfront project costs are $420 million and Ford's weighted average cost of capital is 10%. If the issuance costs for external finances are $15 million, what is the net present value (NPV) of the project? O A. $509 million OB. $565 million O C. $593 million OD. $622 million
Ford Motors expects a new hybrid-engine project to produce incremental cash flows of $50 million each year, and expects those to grow at 5% each year. The uplront project costs are $420 million and Ford's weighted average cost of capital is 9% If the issuance costs for external finances are $15 million, what is the not present value (NPV) of the project? O A. $734 million OB. 5856 million O C. $897 million OD. $815 million Consider the following average...
New Flyer Industries has decided to expand its production of hybrid transit buses. The firm expects incremental cash flows of $40 million per year for the next 10 years. The upfront cost of the expansion is $150 million and there are additional issuance costs for external financing of $15 million. If the New Flyer's WACC is 7.5%, what is the NPV of the project? O A. S125 million O B. S110 million O C. $219 million O D. $95 million...
The cash flows associated with an investment project are an immediate cost of $2300 and benefits of $1200 in one year, $800 in two years, and $2000 in three years. The cost of capital (WACC) is 10%. What is the project's NPV? Your Answer: Answer Hide hint for Question 6 NPV is the sum of the discounted cash flows. A firm is considering a potential investment project that would result in an immediate loss in free cash flow of $116...
A project requires a $12 million initial investment and has expected after-tax cash flows of $2 million in perpetuity. The weighted-average cost of capital is 15%. what is the project's net present value (NPV)? a. $13.33 million b. $93.33 million c. $66.67 million d. $1.33 million
If an independent project with conventional, or normal, cash flows is being analyzed, the net present value (NPV) and internal rate of return (IRR) methods agree Projects Y and Z are mutually exclusive projects. Their cash flows and NPV profiles are shown as follows. NPV (Dollars Year Project Y Project Z 800 -$1,500 -$1,500 0 $200 $900 1 600 Project Y $400 $600 2 $600 $300 400 $1,000 $200 4 Project Z 200 If the weighted average cost of capital...
1) A machinery upgrade project will cost $14 million, and produce cost savings of $1 million in perpetuity. What is the project NPV if the required rate of return is 11%? Enter answer in millions, to two decimal places. 2) Your company is considering a project that requires an initial investment of $12 million, and is expected to produce cash flows of $4 million each year for 10 years. At the end of year 11, the project will require site...
Project S has a cost of $15,000 and is expected to produce benefits (cash flows) of $3,000 per year for 6 years. Calculate the project's Net Present Value (NPV) assuming a cost of capital of 15%. -$5,734 -$1,675 -$3,647 -$814 $3,000
4. Project S has a cost of $10,000 and is expected to produce cash flows of $3000 per year for 5 years. Project L has a cost of $25,000 and is expected to produce cash flows of $7400 for 5 years. Calculate the NPV and IRR of the two projects assuming a cost of capital of 12%. Which project would you select, assuming they are mutually exclusive, using each ranking method?