Answer #1

Answer: 12

Lead time = 7 minutes = 7/60 = 0.11667 hours

No. of Kanbans (N) = Demand per hour * Lead time / Container Size = 4903*(7/60)/50 = 11.44 ~ 12 (Always Round up)

Add a comment
Know the answer?
Add Answer to:
weston 15 35 3 points Mr. C decided to quit teaching and open wings business calls...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 3 points A local retailer purchased inventory from an overseas per and believes the won of...

    3 points A local retailer purchased inventory from an overseas per and believes the won of the model wamewably will Data from the constant show and demand (11907 ordering cost (5) 342 per order and holding cool (M) S4 per un per year how many times per year wil she replenish her inventory of this material? Tany orders will be place in one year) Demand ordering cost holding cost Excel ACESS 11.087 per year 542 per order 54 per unit...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT