Please answer the two questions with details
I will give a rating up
1.
Ans:
Potential Failure Mode | Potential Failure Effects | SEV | Potential Causes | OCC | Current Control | DET | RPN | Actions Taken | SEV | OCC | DET | RPN |
Patients wait long time for getting treatment |
.- Customer satisfaction level getting
down - Clinic impression is going down - Few patients suffering with pain during long waiting duration - Doctors are overburdened with work due to which they fails to prodive 100% service to the customers |
5 | .- Lack of appropriate number of doctors for providing the treatment | 7 | .- Doctors are pressurised to treat fastly | 5 | 175 | .- New doctors appointed after study the arrival rate and service rate of patients | 5 | 3 | 5 | 75 |
Patients leave clinic due to lossing patience | ||||||||||||
Serious patients not getting immediate treatment just agter reaching at clinic |
.- Some times patients dies due to
delay in processes - Clinic impression going down |
9 |
.- Poor communication medium - Improper trainning has given to the staff |
2 | .- After reach at the clinic the patients' condition ckecked and actions take | 2 | 36 | .- In case of arriving serious patients, the ambulance driver or others are trained to inform the patient condition to the clinic just 15-20 mins before reaching at clinic so that the hospital staff will make ready the equipments | 9 | 1 | 1 |
9 |
2.
Answer:
SMED means single minute exchange of dies. It means reduce the setup time dramatically during changing of manufacturing from one product to another product. It has following steps to minimize the setup time:
1. Do the pilot study: It includes equipment selection, team member selection, and set the time for accomplishing the certain activity.
2. List all the activities: Do a video of the entire process and list all individual activities and the duration to accomplish it
3. Categorise the activities: The individual activities need to be categorise into two groups’ i.e external and internal activities.
4. Convert the internal to external activities: It is very much essential to reduce the external time in the production area. Because the value of external time is very high.
5. Systematically arrange the remaining activities.
In this way the setup time / change over time can be reducible up to great extent.