answer quickly plz
10 points Please refer to the figure below. Calculate the quantity of total...
10 points Please refer to the figure below. Calculate the quantity of total brickwork in super structure, plinth and two steps of foundation and select the nearest from the following options. A B B 3.5m 0.3m 0.3m Plan 45 m 0.4m Section at A-A' and B-B' Thickness of footing and foundation is 30 cm each -0.5m -0.6m -0.9m 120 cu-m 50 cu-m 95 cu-m 150 cu-m 190 cu-m