An industrial customer is fined if the power factor of the plant falls below 0.85. The equivalent loads of the plant are: 30 lamps of 400 W, an Electric Oven with an impedance of (2.4 + j3.2) and a load of 80 kW due to an engine block. The three charges are in parallel. Induction motors have a power factor of 0.8 and a performance of 0.98. The customer has a 600V, 60Hz supply.
a) Calculate the average power and total reactive power.
b) Size the necessary condenser that is required so that the client
is not fined.
c) As a consequence of installing the capacitor calculated in b),
say if the network is released with respect to the total load. In
how many amps is the network released?
An industrial customer is fined if the power factor of the plant falls below 0.85. The...
A small industrial plant has a 1okw heating load with unity power factor and a 20KVA inductive load due toa bank of induction motors with power factor o.7 lagging. If the supply is 1200V at 60Hz, determine the capacitive element required to raise the power factor to 95%. And compare the levels of current drawn from the power supply
An Inductive load 1 phase pulling power 6 kW on power factor 0.85 lagging and voltage 230 V. Find : a) Reactive power and Apparent power consumed by the load b) Load impedance c) Draw the triangle power of the load
An industrial plant consisting primarily of induction motor loads absorbs 1200kW at 0.65 power factor lagging. Compute the required kVA rating of a shunt capacitor to improve the power factor to 0.95 leading.
(b) The daily design load curve of a residential area is given in the table below. The hydropower facility providing the power has an effective head of 15 m and a plant efficiency of 0.85. What is the minimum daily flow (m3/s) that could meet the demand? What is the minimum required storage capacity (within-day storage) to meet the peak load? If the daily flowrate were 320m3/s, what would be the minimum required storage capacity? Would there be some water...