6. Your project is expected to run for three consecutive years. Your organization is introducing earned value management as p

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution:

We need to determine four critical terms: BAC, PV, AC , and EV.

BAC is the project budget Php 50,000

PV is the measure of how much work should be complete.From the question, we can say that we 18 months into a project . This means half of the work should be complete.

So PV=0.5 X Php 50,000 =25,000

Then AC is a measure of how much money has been spent to date.From the question, we can say that 30%of the budget has been spent.

So AC=0.3 X Php 50,000 =15,0000

EV is the measure of how much work has been completed.We have 40% of work complete,

EV=0.4 X Php 50,000 =20,000

Therefore Schedule Variance, SV = EV-PV

SV=20,000 - 25,000

SV= - 5,000 which means that project is behind schedule since SV negative.

Cost Variance, CV=EV- AC

CV=20,000 - 15,000

CV= Php 5000

Since CV is positive the project is running under budget.

Add a comment
Know the answer?
Add Answer to:
6. Your project is expected to run for three consecutive years. Your organization is introducing earned...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 2. Suppose you are considering a new project for your firm. The project is expected to run for five years The end deliv...

    2. Suppose you are considering a new project for your firm. The project is expected to run for five years The end deliverable for the project is that it produces a widget. The widget is expected to be brand new to the market and, as such, will have great demand at first. That demand wll die away as competition enters the market. The firm projects the following price points and units sold for each of the five years Xear rice...

  • 1. You have been working as engineer for many years in your organization. One year ago,...

    1. You have been working as engineer for many years in your organization. One year ago, you were promoted to a project management role and assigned a very large project. Your team has over 400 team members from around the world. Your technical background did not prepare you for the work you are doing today. Most of your team members are virtual. Your current focus is on negotiating for the team members you already have been working with. In what...

  • Keflavik Paper Company In recent years, Keflavik Paper Company has been having problems with its project...

    Keflavik Paper Company In recent years, Keflavik Paper Company has been having problems with its project management process. A number of commercial projects, for example, have come in late and well over budget, and product performance has been inconsistent. A comprehensive analysis of the process has traced many of the problems back to faulty project selection methods. Keflavik is a medium-sized corporation that manufactures a variety of paper products, including specialty papers and the coated papers used in the photography...

  • Imagine you work for a real estate developer. Three years ago, the developer spent $50 million on a plot of land, which is now valued at $60 million. However, the building project has been held up in...

    Imagine you work for a real estate developer. Three years ago, the developer spent $50 million on a plot of land, which is now valued at $60 million. However, the building project has been held up in red tape until now, and the company has paid $3 million in interest on its initial loans. Three years ago they thought they could build 100 condos for a total of $30 million and sell them for a total of $100 million. Now,...

  • You have been selected as the project manager for the Global Treps project. You helped to...

    You have been selected as the project manager for the Global Treps project. You helped to run a local shark tank like event at your college last year as part of a class project, so you have a general idea of what is involved. The schedule goal is six months, and the budget is $120,000. Your favorite professor, Dr. K., and a few of her associates have agreed to fund the project. Your strengths are your organizational and leadership skills....

  • Standing in the showroom of a local appliance store, you realise the problem almost immediately. Virtually...

    Standing in the showroom of a local appliance store, you realise the problem almost immediately. Virtually all of the washers, dryers, refrigerators, freezers and dishwashers are white. It is tough to tell one company’s product from another, and the biggest signs in the place announce the low prices on this versus that model. This is the exact reason that Vortex’s senior management team developed the ‘brand-focused value creation’ strategy: to create innovative, branded solutions that consumers will find appealing, that...

  • Performance Improvement programs and effective project management require an understanding of the four phases of the...

    Performance Improvement programs and effective project management require an understanding of the four phases of the project life-cycle: initiation, planning, execution/implementation, and closure. It is important to have each phase of the project mapped on a timeline and to be sure the project team has the appropriate members with the right skills to ensure a successful program. Using a case study from the text, students will demonstrate their ability to review and evaluate a performance improvement program by arranging the...

  • (Use the case of “Global Treps”) You have been selected as the project manager for the Global Tre...

    (Use the case of “Global Treps”) You have been selected as the project manager for the Global Treps project. You helped to run a local shark tank like event at your college last year as part of a class project, so you have a general idea of what is involved. The schedule goal is six months, and the budget is $120,000. Your favorite professor, Dr. K., and a few of her associates have agreed to fund the project. Your strengths...

  • STEP 1: In your own words define problem employees and the categories they may fall into....

    STEP 1: In your own words define problem employees and the categories they may fall into. For the second or last paragraph provide your opinion on which employee type is the most difficult. DEFINITION : I think that "problem employees" are employees that either directly or indirectly hinder the organization's mission or vision, and break down into roughly four categories. In general, problem employees can be classified into two broad categories - employees creating problems for the organization and employees...

  • Select two of the discussion questions and analyze the case study using project management principles. Apply...

    Select two of the discussion questions and analyze the case study using project management principles. Apply your knowledge of project management to the facts presented in the case study to describe how you would proceed. We only need to answer one of the questions. A thorough answer will probably require 300 to 500 words for each question.   Feel free to use text bullets, tables, or graphics to summarize your points. Questions Q1: Make or Buy decision – Describe the make...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT