a Calculation of direct material used
Particulars | $ |
Direct materials purchased | 3,500,000 |
Add beginning direct materials | 384,000 |
Direct materials available for production | 3,884,000 |
Less Ending direct materials | (275,200) |
Direct materials used | 3,608,800 |
$3,608,800 is the raw materials used for production.
b Calculations of Total manufacturing cost
Particulars | $ | $ |
Direct materials used | 3,608,800 | |
Direct manufacturing labour | 2,176,000 | |
Prime cost | 5,784,800 | |
Add Manufacturing overhead: | ||
Material handling | 320,000 | |
Depreciation of equipment | 224,000 | |
Coolant & lubricants | 42,400 | |
Property tax equipment | 32,000 | |
Leasing cost plant | 384,000 | |
Fire insurance equipment | 16,000 | |
Indirect manufacturing labour | 275,200 | |
Sand paper | 32,000 | |
Total manufacturing overhead | 1,325,600 | |
Total manufacturing cost | 7,110,400 |
Total manufacturing cost added to work in process inventory is $7,110,400.
c Calculation of cost of goods manufactured
Particulars | $ |
Beginning work in process | 86,000 |
Add total manufacturing cost | 7,110,400 |
7,196,400 | |
Less Ending work in process | (64,000) |
Cost of goods manufactured | 7,132,400 |
$7,132,400 is the cost of goods manufactured
d Calculation of Cost of goods sold
Particulars | $ |
Beginning finished goods inventory | 650,000 |
Add cost of goods manufactured | 7,132,400 |
Cost of goods available for sales | 7,782,400 |
Less Ending finished goods inventory | (1,280,000) |
Cost of goods sold | 6,502,400 |
$6,502,400 is the cost of goods sold.
The above are the separate and detailed calculations of direct material used, total manufacturing cost, cost of goods manufactured and cost of goods sold in 2020.
If YOU are like the answer please upvote.
JAG Sporting Goods Company manufactured 100,000 units in 2020 and reported the following costs: Sandpaper $...
Show ALL calculations to receive partial credit JAG Sporting Goods Company manufactured 100,000 units in 2020 and reported the following costs: Sandpaper Materials handling Coolants & lubricants Indirect manufacturing labor Direct manufacturing labor Direct materials, 1/1/16 Finished goods, 1/1/16 Finished goods, 12/31/16 Work-in-process, 1/1/16 Work-in-process, 12/31/16 $ 32.000 320.000 22.400 275.200 2. 176,000 384.000 672.000 1.280,000 96,000 64,000 Leasing costs-plant Depreciation equipment Property taxes-equipment Fire Insurance-equipment Direct material purchases Direct materials, 12/31/16 Sales revenue Sales commissions Sales salaries Advertising costs...
ORT ANSWER. Write the word or phrase that best comple Write the word or phrase that best completes each statement or answers the question. 41) Millworks Company manufactured 100,000 units in 2018 and reported the following costs: Sandpaper Materials handling Coolants & lubricants Indirect manufacturing labor Direct manufacturing labor Direct materials, 1/1/18 Finished goods, 1/1/18 Finished goods, 12/31/18 Work-in-process, 1/1/18 Work-in-process, 12/31/18 $ 32,000 320,000 22,400 275,200 2,176,000 348,000 672,000 1,280,000 96,000 64,000 Leasing costs-plant Depreciation-equipment Property taxes-equipment Fire insurance-equipment...
I cant figure out this problem. also i want to see everything written out so i know how exactly to do it Millworks Company manufactured 100,000 units in 2018 and reported the following costs: 0 to .00 Sandpaper $32,000 Materials handling 320,000 Coolants & lubricants Indirect manufacturing labor 275,200 Direct manufacturing labor 2,176,000 Direct materials, 1/1/18 348,000 Finished goods, 1/1/18 672,000 Finished goods, 12/31/18 1,280,000 Work-in-process, 1/1/18 96,000 Work-in-process, 12/31/18 64,000 Leasing costs-plant $384,000 Depreciation equipment 224,000 Property taxes-equipment 32,000...
Consider the following data of the campbell company for the year 2016: sandpaper: $2000 materials handling costs: $70000 lubricants and coolants: $5000 Miscellaneous and manufacturing labor: $40000 Direct manufacturing labor: $300,000 Direct materials, Jan 1 2016; $40,000 Finished goods Jan 1, 2016: $100,000 Finished goods Dec 31, 2016: $150,000 Work in process Jan 1,2016: $10,000 Work in process Dec 31,2016: $14,000 plant leasing costs: $54,000 Depreciation plant equipment: 36,000 property taxes on plant equipment: 4000 fire insurance on plant equipment:...
c. Chantilly Lace Company manufactured 200,000 units in 2019 and reported the following costs: Indirect manufacturing labour Supplies Heat, light & electricity Depreciation-plant Depreciation equipment Direct materials, 1/1/19 Finished goods, 1/1/19 Finished goods, 31/12/19 Work-in-process, 1/1/19 Work-in-process, 31/12/19 Leasing costs-plant Direct material purchase Direct materials, 31/12/19 Direct labour $ 270,000.00 $ 67,000.00 S 63,500.00 $ 25,884.00 $ 34,621.00 $ 78,423.00 $ 255,643.00 $ 245,789.00 $ 213,456.00 $ 218,796.00 $ 24,100.00 $ 236,548.00 $ 89,655.00 $ 357,890.00 - Calculate the (i)...
Calculate XYZ Company's: A)Cost of Goods Manufactured for 2020 B)Conversion costs for 2020 C)Sales Commission for 2020 XYZ Company recorded the following information related to their inventory accounts for 2020: Direct materials Work in process Finished goods January 1, 2020 50,000 38,000 32,000 December 31, 2020 37,000 41,000 34,000 The following costs were taken from XYZ Company's accounting records for 2020: $129,000 37,000 590,000 30,000 Sales revenue ......................................... : : Direct materials purchased ....... .................. Depreciation, factory equipment ......................... Sales...
Calculate XYZ Company's: A)Cost of Goods Manufactured for 2020 B)Conversion costs for 2020 C)Sales Commission for 2020 XYZ Company recorded the following information related to their inventory accounts for 2020: Direct materials Work in process Finished goods January 1, 2020 50,000 38,000 32,000 December 31, 2020 37,000 41,000 34,000 The following costs were taken from XYZ Company's accounting records for 2020: $129,000 37,000 590,000 30,000 Sales revenue ......................................... : : Direct materials purchased ....... .................. Depreciation, factory equipment ......................... Sales...
compute cost ok f goods manufactured during the year. b- compute operating income ( income from operations) for the year. c- compute cost of direct materials used during the year. d- compute cost of goods sold during the year. please send me the answers. thanks. The following information pertains to Zillow Manufacturing Company for year 2019. Sales revenue $ 1.800.000 1.200.000 250.000 162.000 Cost of goods manufactured Direct manufacturing labor Administrative salaries Sales commissions Sales salaries Materials handling Indirect manufacturing...
pute cost of goods manufactured. Aikman Company Cost of Goods Manufactured Schedule Nork-in-Process Inventory. 1/1 1612 Direct Materials Raw Materials Inventory. 1/1 23680 Materials Purchased 153280 Materials Available for Use 176960 Less Raw Materials inventory. 12/31 31650 Direct Materials Used 1410 Direct Labor 221550 Manufacturing Overhead Tot Manufacturing Costs 551410 Toul Cost of Work in Process o ry Less Wort Process inventory. 12/31 n Arrompts: 1017 used The following information is available for Aikman Company. 2020 dings January 1, 2020...
Exercise 14-14 a-c The following information is available for Aikman Company January 1, 2020 2020 Raw materials inventory $26,010 Work in process inventory 18,560 Finished goods inventory 28,900 Materials purchased $155,770 Direct labor 224,700 Manufacturing overhead 182,460 Sales revenue 905,040 December 31, 2020 $34,130 19,620 24,050 Your answer is partially correct. Try again. Compute cost of goods manufactured. Alkman Company Cost of Goods Manufactured Schedule 18560 work-in -Process Inventory, 1/2 "Direct Materials Raw Materials Inventory, 1/1 Materials Purchased Materials Available...