Consider the generic ABC graphic below, for a standard two-step allocation process. ON Pool 1 ON Poola ON Pool 3 Adity 1 Mili
Total Assume that the costs incurred in the OH cost pools are / were $47,000 for OH Pool 1; $122,000 for OH Pool 2; and $16,0
0 0
Add a comment Improve this question Transcribed image text
Answer #1
Costs Divided by: Total of cost driver POHR
Overhead pool 1 Cost driver 4 $             47,000                                 55 $       854.54545
Overhead pool 2 Cost driver 1 $           122,000                         12,760 $            9.56113
Overhead pool 3 Cost driver 5 $             16,000                           1,523 $          10.50558
Overhead pool 1 Activity 1 Activity 2 Activity 3 Activity 4
Predermined overhead rate $      854.54545 $      854.54545 $              854.54545 $       854.54545
Multiply: Cost driver 4                          35                          12                                  -                               8
Allocated overhead pool 1 $       29,909.09 $       10,254.55 $                              -   $           6,836.36
Overhead pool 2 Activity 1 Activity 2 Activity 3 Activity 4
Predermined overhead rate $           9.56113 $           9.56113 $                  9.56113 $            9.56113
Multiply: Cost driver 1                    4,350                           -                             2,270                     6,140
Allocated overhead pool 2 $       41,590.91 $                       -   $               21,703.76 $        58,705.33
Overhead pool 3 Activity 1 Activity 2 Activity 3 Activity 4
Predermined overhead rate $        10.50558 $         10.50558 $                10.50558 $          10.50558
Multiply: Cost driver 5                       820                        155                               108                         440
Allocated overhead pool 3 $         8,614.58 $          1,628.37 $                 1,134.60 $           4,622.46
Final answers: Activity 1 Activity 2 Activity 3 Activity 4
Allocated overhead pool 1 $       29,909.09 $       10,254.55 $                              -   $           6,836.36
Allocated overhead pool 2 $       41,590.91 $                       -   $               21,703.76 $        58,705.33
Allocated overhead pool 3 $         8,614.58 $          1,628.37 $                 1,134.60 $           4,622.46
Allocated overhead costs $       80,114.58 $       11,882.91 $               22,838.36 $        70,164.15
Allocated overhead costs (rounded) $             80,115 $             11,883 $                     22,838 $              70,164
Add a comment
Know the answer?
Add Answer to:
Consider the generic ABC graphic below, for a standard two-step allocation process. ON Pool 1 ON...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT