1 | Activity | Activity Rate | |
Machining | $3.20 | Per Machine Hour | |
($208,960/65,300) | |||
Design Costs | $8.50 | Per Design Hour | |
($53,125/6,250) | |||
Setup | $142.50 | Per Batch | |
($68,400/480) | |||
2 | Machining | Unit level | |
Design Costs | Product level | ||
Setup | Batch level | ||
saved Saved Help Save & Exit Submit Check my work Required information Gable Company uses three...
Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $183,300 Number of machine hours 47,725 Number of design hours 71,150 Number of batches Estimated Cost Driver 61,100 5,750 500 Required: 1. Compute the activity rate for each activity. 2. Classify each activity as facility, product, batch, or unit level. Complete this question by entering your...
Check my work 1 Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: 1 points Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $345, 220 Number of machine hours 79,900 Number of design hours 70,983 Number of batches Estimated Cost Driver 84,200 8,500 495 eBook Hint Required: 1. Compute the activity rate for each activity. 2. Classify each activity as facility, product, batch,...
Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $ 250,680 Number of machine hours 61,600 Number of design hours 66,482 Number of batches Estimated Cost Driver 71,600 7.ee 465 Required: 1. Compute the activity rate for each activity 2. Classify each activity as facility, product, batch, or unit level. Complete this question by entering...
Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $171,100 Number of machine hours 45,100 Number of design hours 66,123 Number of batches Estimated Cost Driver 59,000 5,500 465 Required: 1. Compute the activity rate for each activity. 2. Classify each activity as facility, product, batch, or unit level. Complete this question by entering your...
Required Information Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $312,eee Number of machine hours 73,6ee Number of design hours 71,600 Number of batches Estimated Cost Driver Be, evo 8, eae 500 Re 1. red: mpute the activity rate for each activity. 1551fy each activity as facility, product, batch, or unit level. complete this question by...
Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $280,460 Number of machine hours 67,500 Number of design hours 70,070 Number of batches Estimated Cost Driver 75,800 7,500 490 Required: 1. Compute the activity rate for each activity. 2. Classify each activity as facility, product, batch, or unit level. Complete this question by entering your answers in...
Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $312,000 Number of machine hours 73,600 Number of design hours 71,600 Number of batches Estimated Cost Driver 80,000 8,000 500 Required: 1. Compute the activity rate for each activity. (Round your answers to 2 decimal places.) Activity Rate per Machine Hour Activity Machining Design Costs Setup per Design...
Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $312,000 Number of machine hours 73,600 Number of design hours 71,600 Number of batches Estimated Cost Driver 80,000 8,000 500 Required: 1. Compute the activity rate for each activity. (Round your answers to 2 decimal places.) Activity Rate per Machine Hour Activity Machining Design Costs Setup per Design...
Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $312,000 Number of machine hours 73,600 Number of design hours 71,600 Number of batches Estimated Cost Driver 80,000 8,000 500 Required: 1. Compute the activity rate for each activity. 2. Classify each activity as facility, product, batch, or unit level. Complete this question by entering your...
Please show how to work these out. Thanks! 61 Required Information Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Part 1 of 3 Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $398,280 Number of machine hours 89,725 Number of design hours 79,413 Number of batches Estimated Cost Driver 99, see 9,250 490 0.07 points eBook Hint Print Required: 1. Compute the activity rate for...