Solution:
Job No. 50 | |||
Date | Direct Materials | Direct Labor | Manufacturing Overhead |
Beg. | $30,000 | $15,200 | $20,200 |
Jan. | $12,500 | $7,000 | $14,630 |
$42,500 | $22,200 | $34,830 | |
Cost Of Completed job | |||
Direct Material | $42,500 | ||
Direct Labor | $22,200 | ||
Manufacturing Overhead | $34,830 | ||
Total Cost | $99,530 |
Job No. 51 | |||
Date | Direct Materials | Direct Labor | Manufacturing Overhead |
Jan. | $42,400 | $28,100 | $58,729 |
$42,400 | $28,100 | $58,729 | |
Cost Of Completed job | |||
Direct Material | $42,400 | ||
Direct Labor | $28,100 | ||
Manufacturing Overhead | $58,729 | ||
Total Cost | $1,29,229 |
Question 5 Bertrand Manufacturing uses a job-order cost system and applies overhead to production on the...
Question 5 Bertrand Manufacturing uses a job-order cost system and applies overhead to production on the basis of direct labour costs. On January 1, 2020, Job No. 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $30,000, direct labour $15,200, and manufacturing overhead $20,200. As of January 1, Job No. 49 had been completed at a cost of $120,200 and was part of finished goods inventory. There...
Question 5 Bertrand Manufacturing uses a job-order cost system and applies overhead to production on the basis of direct labour costs. On January 1, 2020, Job No. 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $30,000, direct labour $15, and manufacturing overhead $20,200. As of January 1, Job No. 49 had been completed at a cost of $120,200 and was part of finished goods inventory. There...
Question 5 Bertrand Manufacturing uses a job-order cost system and applies overhead to production on the basis of direct labour costs. On January 1, 2020, Job No. 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $30,000, direct labour $15,200, and manufacturing overhead $20,200. As of January 1, Job No. 49 had been completed at a cost of $120,200 and was part of finished goods inventory. There...
Question 5 Bertrand Manufacturing uses a job-order cost system and applies overhead to production on the basis of direct labour costs. On January 1, 2020, Job No. 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $30,600, direct labour $15,300, and manufacturing overhead $20,800. As of January 1, Job No. 49 had been completed at a cost of $120,000 and was part of finished goods inventory. There...
Question 5 Bertrand Manufacturing uses a job-order cost system and applies overhead to production on the basis of direct labour costs. On January 1, 2020, Job No. 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $30,600, direct labour $15,300, and manufacturing overhead $20,800. As of January 1, Job No. 49 had been completed at a cost of $120,000 and was part of finished goods inventory. There...
Question 5 Bertrand Manufacturing uses a job-order cost system and applies overhead to production on the basis of direct labour costs. On January 1, 2020, Job No. 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $30,600, direct labour $15,300, and manufacturing overhead $20,800. As of January 1, Job No. 49 had been completed at a cost of $120,000 and was part of finished goods inventory. There...
Question 5 Bertrand Manufacturing uses a job-order cost system and applies overhead to production on the basis of direct labour costs. On January 1, 2020, Job No. 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $30,000, direct labour $15,000, and manufacturing overhead $20,000. As of January 1, Job No. 49 had been completed at a cost of $120,000 and was part of finished goods inventory. There...
Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1. 2020. Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $22,200, direct labor $13,320, and manufacturing overhead $17.760. As of January 1, Job 49 had been completed at a cost of $99,900 and was part of finished goods inventory. There was a $16,650...
Question 1 Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2017, 1cb No. 50 was the only joo in process. The costs incurred prior to lanuary 1 on this job were as follows: direct materials $22.200, direct labor $13,320, and manufacturing overhead S17,760. As of January 1, Job No. 49 had been completed at a cost of $9,900 and was part of finished goods inventory....
Problem 2-1A Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2017, Job No. 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $20,200, direct labor $12,120, and manufacturing overhead $16,160. As of January 1, Job No. 49 had been completed at a cost of $90,900 and was part of finished goods inventory....