Question

Question 5 Bertrand Manufacturing uses a job-order cost system and applies overhead to production on the basis of direct labo(el) Total the job cost sheets for any job(s) completed during the month. Job Cost Sheets Job No. 50 Direct Direct Manufactur

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution:

Job No. 50
Date Direct Materials Direct Labor Manufacturing Overhead
Beg. $30,000 $15,200 $20,200
Jan. $12,500 $7,000 $14,630
$42,500 $22,200 $34,830
Cost Of Completed job
Direct Material $42,500
Direct Labor $22,200
Manufacturing Overhead $34,830
Total Cost $99,530
Job No. 51
Date Direct Materials Direct Labor Manufacturing Overhead
Jan. $42,400 $28,100 $58,729
$42,400 $28,100 $58,729
Cost Of Completed job
Direct Material $42,400
Direct Labor $28,100
Manufacturing Overhead $58,729
Total Cost $1,29,229
Add a comment
Know the answer?
Add Answer to:
Question 5 Bertrand Manufacturing uses a job-order cost system and applies overhead to production on the...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Question 5 Bertrand Manufacturing uses a job-order cost system and applies overhead to production on the...

    Question 5 Bertrand Manufacturing uses a job-order cost system and applies overhead to production on the basis of direct labour costs. On January 1, 2020, Job No. 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $30,000, direct labour $15,200, and manufacturing overhead $20,200. As of January 1, Job No. 49 had been completed at a cost of $120,200 and was part of finished goods inventory. There...

  • Question 5 Bertrand Manufacturing uses a job-order cost system and applies overhead to production on the...

    Question 5 Bertrand Manufacturing uses a job-order cost system and applies overhead to production on the basis of direct labour costs. On January 1, 2020, Job No. 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $30,000, direct labour $15, and manufacturing overhead $20,200. As of January 1, Job No. 49 had been completed at a cost of $120,200 and was part of finished goods inventory. There...

  • Question 5 Bertrand Manufacturing uses a job-order cost system and applies overhead to production on the...

    Question 5 Bertrand Manufacturing uses a job-order cost system and applies overhead to production on the basis of direct labour costs. On January 1, 2020, Job No. 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $30,000, direct labour $15,200, and manufacturing overhead $20,200. As of January 1, Job No. 49 had been completed at a cost of $120,200 and was part of finished goods inventory. There...

  • Question 5 Bertrand Manufacturing uses a job-order cost system and applies overhead to production on the...

    Question 5 Bertrand Manufacturing uses a job-order cost system and applies overhead to production on the basis of direct labour costs. On January 1, 2020, Job No. 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $30,600, direct labour $15,300, and manufacturing overhead $20,800. As of January 1, Job No. 49 had been completed at a cost of $120,000 and was part of finished goods inventory. There...

  • Question 5 Bertrand Manufacturing uses a job-order cost system and applies overhead to production on the...

    Question 5 Bertrand Manufacturing uses a job-order cost system and applies overhead to production on the basis of direct labour costs. On January 1, 2020, Job No. 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $30,600, direct labour $15,300, and manufacturing overhead $20,800. As of January 1, Job No. 49 had been completed at a cost of $120,000 and was part of finished goods inventory. There...

  • Question 5 Bertrand Manufacturing uses a job-order cost system and applies overhead to production on the...

    Question 5 Bertrand Manufacturing uses a job-order cost system and applies overhead to production on the basis of direct labour costs. On January 1, 2020, Job No. 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $30,600, direct labour $15,300, and manufacturing overhead $20,800. As of January 1, Job No. 49 had been completed at a cost of $120,000 and was part of finished goods inventory. There...

  • Question 5 Bertrand Manufacturing uses a job-order cost system and applies overhead to production on the...

    Question 5 Bertrand Manufacturing uses a job-order cost system and applies overhead to production on the basis of direct labour costs. On January 1, 2020, Job No. 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $30,000, direct labour $15,000, and manufacturing overhead $20,000. As of January 1, Job No. 49 had been completed at a cost of $120,000 and was part of finished goods inventory. There...

  • Lott Company uses a job order cost system and applies overhead to production on the basis...

    Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1. 2020. Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $22,200, direct labor $13,320, and manufacturing overhead $17.760. As of January 1, Job 49 had been completed at a cost of $99,900 and was part of finished goods inventory. There was a $16,650...

  • Question 1 Lott Company uses a job order cost system and applies overhead to production on...

    Question 1 Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2017, 1cb No. 50 was the only joo in process. The costs incurred prior to lanuary 1 on this job were as follows: direct materials $22.200, direct labor $13,320, and manufacturing overhead S17,760. As of January 1, Job No. 49 had been completed at a cost of $9,900 and was part of finished goods inventory....

  • Problem 2-1A Lott Company uses a job order cost system and applies overhead to production on...

    Problem 2-1A Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2017, Job No. 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $20,200, direct labor $12,120, and manufacturing overhead $16,160. As of January 1, Job No. 49 had been completed at a cost of $90,900 and was part of finished goods inventory....

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT