1-4 & 7 Recap Seved He 16 Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The
0 0
Add a comment Improve this question Transcribed image text
Answer #1
1)
Molding Department
Predetermined Overhead rate
     = ( Est. Fixed OH Costs / Est. Machine Hours )+ Est. Variable OH rate
     =   ($ 11,750 / 2,500 ) + $ 2.10
     =    $ 4.7 + $ 2.10
6.8 per MH
Fabrication Department
Predetermined Overhead rate
     = ( Est. Fixed OH Costs / Est. Machine Hours )+ Est. Variable OH rate
     =   ($ 16,050 / 1,500 ) + $ 2.90
     =    $ 10.70 + $ 2.90
$ 13.6 per MH
Add a comment
Know the answer?
Add Answer to:
1-4 & 7 Recap Seved He 16 Sweeten Company had no jobs in progress at the...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 14&7 Recap Help S 2 Sweeten Company had no jobs in progress at the beginning of...

    14&7 Recap Help S 2 Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments-Molding and Fabrication. It started, completed, and sold only two jobs during March Job P and Job Q. The following additional Information is available for the company as a whole and for Jobs P and Olal data and questions relate to the month of March): Molding into Estimated total machine-hours used 2,500 1,500 0.000...

  • Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories....

    Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments--Molding and Fabrication. It started, completed, and sold only two jobs during March—Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month of March): Molding Fabrication Total Estimated total machine-hours used 2,500 1,500 4,000 Estimated total fixed manufacturing...

  • Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories....

    Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments-Molding and Fabrication. It started, completed, and sold only two jobs during March- Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month of March): Estimated total machine-hours used Estimated total fixed manufacturing overhead Estimated variable manufacturing overhead...

  • Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories....

    Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments-Molding and Fabrication. It started, completed, and sold only two jobs during March-Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month of March): Estimated total machine-hours used Estimated total fixed manufacturing overhead Estimated variable manufacturing overhead per...

  • (The following information applies to the questions displayed berowy Sweeten Company had no jobs in progress...

    (The following information applies to the questions displayed berowy Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments-Molding and Fabrication. It started, completed, and sold only two jobs during March- Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month of March): Estimated total machine-hours used...

  • Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories....

    Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments—Molding and Fabrication. It started, completed, and sold only two jobs during March—Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month of March): Molding Fabrication Total Estimated total machine-hours used 2,500 1,500 4,000 Estimated total fixed manufacturing...

  • Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories....

    Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments--Molding and Fabrication. It started, completed, and sold only two jobs during March—Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month of March): Molding Fabrication Total Estimated total machine-hours used 2,500 1,500 4,000 Estimated total fixed manufacturing...

  • Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories....

    Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments--Molding and Fabrication. It started, completed, and sold only two jobs during March-Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month of March): Estimated total machine-hours used Estimated total fixed manufacturing overhead Estimated variable manufacturing overhead per...

  • 5 Sweeten Company had no jobs in progress at the beginning of March and no beginning...

    5 Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments---Molding and Fabrication. It started, completed, and sold only two jobs during March- Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month of March): Estimated total machine-hours used Estimated total fixed manufacturing overhead Estimated variable manufacturing...

  • TURUT MULUT ONE WE YULTS USEU LUM Sweeten Company had no jobs in progress at the...

    TURUT MULUT ONE WE YULTS USEU LUM Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has cation. It started, completed, and sold only two jobs during March- Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month of March): Estimated total machine-hours used Estimated total fixed manufacturing overhead Estimated...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT