Determining asset cost and recording full-year depreciation Road Runner High-Speed Online, Inc. incurred the following costs...

Determining asset cost and recording full-year depreciation

Road Runner High-Speed Online, Inc. incurred the following costs in acquiring it's property and equipment:

A. $250,000 - Purchase price of four acres of land, including an old building that will be used for a garage (75% to land and 25% to building).

B. $8,100 - Dirt and leveling of land.

C. $17,650 - Fence around the land.

D. $600 - Attorney fee for title search on the land.

E. $5,900 - Delinquent real estate taxes on the land to be paid by Road Runner.

F. $1,800 - Company signs at front of the company property.

G. $350 - Building permit for sales building.

H. $19,800 - Architect fee for the design of sales building.

I. $923,000 - Construction costs of sales building.

J. $41,800 - Renovation costs of the garage building.

K. $9,000 - Interest during construction on loan for sales building.

L. $6,400 - Trees and shrubs.

M. $52,300 - Parking lot and concrete walks.

N. $7,300 - Lights for the parking lot.

O. $107,100 - Furniture for the sales building.

P. $1,800 - Transportation and installation of furniture.

Q. $40,000 - Supervisory salary of the construction supervisor (85% to sales building; 9% to land improvements; and 6% to garage building).

Road Runner depreciates building over 40 years, land improvements over 20 years, and furniture over 8 years, all on a straight-line basis.

Salvage values are as follows: land improvements, $1,000; sales building, $50,000; garage building, $5,000; and furniture, $2,000.

Requirements:

1. Set up columns for Land, Land Improvements, Sales Building, Garage Building, and Furniture. Listing each cost's description then accounting for it in the appropriate column. Determine the total cost for each column.

2. All construction was complete and the assets were placed in service on 2019. Record full-year depreciation expense for the year ending December 31, 2019.

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Particulars Land Land Improvements Sales Building Garage Building Furniture
Purchase Price $        187,500.00 $                              -   $                 -   $       62,500.00 $                 -  
Dirt and Leveling of Land $                         -   $                  8,100.00 $                 -   $                     -   $                 -  
Fence around the land $                         -   $                17,650.00 $                 -   $                     -   $                 -  
Attorney Fee $                600.00 $                              -   $                 -   $                     -   $                 -  
Delinquent real estate taxes $             5,900.00 $                              -   $                 -   $                     -   $                 -  
Company Signs $                         -   $                  1,800.00 $                 -   $                     -   $                 -  
Building permit $                         -   $                              -   $         350.00 $                     -   $                 -  
Architect Fees $                         -   $                              -   $   19,800.00 $                     -   $                 -  
Construction Costs $                         -   $                              -   $ 923,000.00 $                     -   $                 -  
Renovation Costs $                         -   $                              -   $                 -   $       41,800.00 $                 -  
Interest on Loan $                         -   $                              -   $     9,000.00 $                     -   $                 -  
Trees and Shrubs $                         -   $                  6,400.00 $                 -   $                     -   $                 -  
Parking lot and concrete walks $                         -   $                52,300.00 $                 -   $                     -   $                 -  
Parking lot lights $                         -   $                  7,300.00 $                 -   $                     -   $                 -  
Furniture purchased $                         -   $                              -   $                 -   $                     -   $ 107,100.00
Transportation and installation of furniture $                         -   $                              -   $                 -   $                     -   $     1,800.00
Supervisor Salary $                         -   $                  3,600.00 $   34,000.00 $         2,400.00 $                 -  
Total Costs $        194,000.00 $                97,150.00 $ 986,150.00 $     106,700.00 $ 108,900.00
Salvage Value $                  1,000.00 $   50,000.00 $         5,000.00 $     2,000.00
Estimated Life (in years) 20 40 40 8
Depreciation per year = (Total Costs - Salvage Value)/Estimated Life No depreciation on land $                  4,807.50 $   23,403.75 $         2,542.50 $   13,362.50
Add a comment
Know the answer?
Add Answer to:
Determining asset cost and recording full-year depreciation Road Runner High-Speed Online, Inc. incurred the following costs...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • > Problems Group A bjectives 1, 2 P9-30A Determining asset cost and recording partial-year depreciation Park and...

    > Problems Group A bjectives 1, 2 P9-30A Determining asset cost and recording partial-year depreciation Park and Fly, near an airport, incurred the following costs to acquire land, make land improvements, and construct and furnish a small building: Bldg. 5446,100 a. Purchase price of three acres of land b. Delinquent real estate taxes on the land to be paid by Park and Fly C. Additional dirt and earthmoving d. Title insurance on the land acquisition e. Fence around the boundary...

  • Safe Parking, near an airport, incurred the following cos improvements, and construct and furnish a small...

    Safe Parking, near an airport, incurred the following cos improvements, and construct and furnish a small building he following costs to acquire land, make land a. Purchase price of three acres of land 86,000 6,300 b. Delinquent real estate taxes uent real estate taxes on the land to be paid by Safe Parking c. Additional dirt and earthmoving 8.400 3,400 d. Title insurance on the land acquisition 9.600 e. Fence around the boundary of the property 900 f. Building permit...

  • 1. set up collumns for land land improvements building and furniture show how to account for...

    1. set up collumns for land land improvements building and furniture show how to account for each cost by listing the cost under the correct account determine the total cost of each asset 2. all construction was complete and the assets were placed in service on october 1 record partial- year deprecation expence for the year ended december 31 round to the nearest dollar acquire land, make earning Objectives 1, 2 > Problems Group A P10-30A Determining asset cost and...

  • Required information Problem 8-3A Asset cost allocation; straight-line depreciation LO C1, P1 [The following information applies...

    Required information Problem 8-3A Asset cost allocation; straight-line depreciation LO C1, P1 [The following information applies to the questions displayed below.) In January 2018, Mitzu Co. pays $2,600,000 for a tract of land with two buildings on it. It plans to demolish Building 1 and build a new store in its place. Building 2 will be a company office; it is appraised at $720,000, with a useful life of 20 years and a $75,000 salvage value. A lighted parking lot...

  • On February 1, 2016, Jekel & Hyde Inc. purchased land and incurred other costs relative to...

    On February 1, 2016, Jekel & Hyde Inc. purchased land and incurred other costs relative to the construction of a new warehouse. The costs related to the purchase of the land and the construction of the building are listed below: Purchase price of the land $231,250 Title insurance for the land $1,500 Legal fees to purchase land $1,000 Cost of razing an old building on the land to be used $8,500 for the construction of the warehouse Delinquent property taxes...

  • $400,000 PR 9-1A Allocating payments and receipts to fixed asset accounts Obj. 1 The following payments...

    $400,000 PR 9-1A Allocating payments and receipts to fixed asset accounts Obj. 1 The following payments and receipts are related to land, land improvements, and buildings acquired for use in a wholesale ceramic business. The receipts are identified by an asterisk. A Fee paid to attorney for title search .. .......... B. Cost of real estate acquired as a plant site: Land........ Building (to be demolished)........... C. Delinquent real estate taxes on property, assumed by purchaser... D. Cost of razing...

  • Allocating payment xed asset accounts The following payents and receipts are related to land, land improvements,...

    Allocating payment xed asset accounts The following payents and receipts are related to land, land improvements, and buildings acquired for use in a wholesale ceramic business. The receipts are identified by an asteris a. Fee paid to attorney for title seardch $2,500 b. Cost of real estate acquired as a plant site: Land 285,000 Building (to be demolished) 55,000 c. Delinquent real estate taxes on property, assumed by purchaser 15,500 d. Cost of razing and removing building acquired in (b)...

  • Assume Martin's Moving & Storage Ltd. (MMS) of Regina, Saskatchewan, incurred the following costs in acquiring...

    Assume Martin's Moving & Storage Ltd. (MMS) of Regina, Saskatchewan, incurred the following costs in acquiring land, making land improvements, and constructing and furnishing its own storage warehouse: (Click the icon to view the costs of items a. to i.) (Click the icon to view the costs of items j. to q.) Requirements Requirement 1. Show how to account for each of MMS's costs by listing the cost under the correct account. Determine the total cost of each asset. Start...

  • Help me please. #1: Benedict Company incurred the following costs. 1. Sales tax on factory machinery...

    Help me please. #1: Benedict Company incurred the following costs. 1. Sales tax on factory machinery purchased $ 5,000 2. Painting of and lettering on truck immediately upon purchase 700 3. Installation and testing of factory machinery 2,000 4. Real estate broker’s commission on land purchased 3,500 5. Insurance premium paid for fi rst year’s insurance on new truck 880 6. Cost of landscaping on property purchased 7,200 7. Cost of paving parking lot for new building constructed 17,900 8....

  • In October 2019, Old City Antiques onened a new checking account at Barnett Bank. The bank statement dated Oct...

    In October 2019, Old City Antiques onened a new checking account at Barnett Bank. The bank statement dated October 31, 2019, for Old City Antiques follows: Beginning Balance, October 1, 2019 Deposits and other credits Oct. 2 10 17 19 $36,000 800 14,000 52,000 450 50 103,300 20 24. EFT St. Augustine Hotel 31. Interest revenue Checks and other debits: Oct. 2 EFT to FPL (utilities) 6 Ck#325 10 Ck#327 10 Ck#326 27 Ck#329 27 EFT to ATT 28 Ck#340...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT