Geary Manufacturing has assembled the data appearing in the next column pertaining to two products. Past experience has shown that the unavoidable fixed manufacturing overhead included in the cost per machine hour averages $10. Geary has a policy of filling all sales orders, even if it means purchasing units from outside suppliers. Total machine capacity is 50,000 hours.
Electric |
||||
Blender |
Mixer |
|||
|
|
|||
Direct materials |
$ 6 |
$11 |
||
Direct labor |
4 |
9 |
||
Manufacturing overhead |
||||
at $16 per hour |
16 |
32 |
||
Cost if purchased from an |
||||
outside supplier |
20 |
38 |
||
Annual demand (units) |
20,000 |
28,000 |
Question
If 50,000 machine hours are available and Geary Manufacturing desires to follow an optimal strategy, it should
A.Produce 25,000 electric mixers and purchase all other units as needed.
B.Produce 20,000 blenders and 15,000 electric mixers, and purchase all other units as needed.
C.Produce 20,000 blenders and purchase all other units as needed.
D.Produce 28,000 electric mixers and purchase all other units as needed.
To find the correct answer, we need to calculate the necessary machine hours per unit.
Blender requires 1 hour per unit. (16/16)
Mixer requires 2 hours per unit. (32/16)
So, with 50,000 machine hours, it can either produce 50000 blenders or 25,000 mixers or a combination but some units will still need to be purchased.
Now, to separate fixed portion of OH cost which averages $10 per machine hour,
Variable portion of OH for Blender = (16 * 1) - (10 * 1) = $6 per unit
Variable portion of OH for Mixer = (16 * 2) - (10 * 2) = $12 per unit
Total VC for blender = 6 + 4 + 6 = $16 per unit
Total VC for mixer = 11 + 9 + 12 = $32 per unit
The purchase price from outside supplier of blender is $20. So, cost savings = $20 - $16 = $4. Cost savings per machine hour = $4 / 1 mach hr per unit = $4 per machine hour
The purchase price from outside supplier of mixer is $38. So, cost savings = $38 - $32 = $6. Cost savings per machine hour = $6 / 2 mach hr per unit = $3 per machine hour
As the cost savings of blenders is more, company should produce blenders. As the annual demand is 20,000 blenders, it should produce 20,000 blenders. It would consume 20,000 machine hours.
Remaining machine hours = 50,000 - 20,000 = 30,000 hours
Mixers that can be produced = 30,000 hrs/ 2 hrs per unit = 15,000 units.
So, correct answer = B.Produce 20,000 blenders and 15,000 electric mixers, and purchase all other units as needed.
Geary Manufacturing has assembled the data appearing in the next column pertaining to two products. Past...
Kitchen Magician, Inc. has assembled the following data pertaining to its two most popular products. Electric Mixer Blender $ 25 43 19 Direct material Direct labor Manufacturing overhead @ $52 per machine hour Cost if purchased from an outside supplier Annual demand (units) 52 32 104 115 32,000 67 27,000 Past experience has shown that the fixed manufacturing overhead component included in the cost per machine hour averages $40. Kitchen Magician's management has a policy of filling all sales orders,...
Check my work Kitchen Magician, Inc. has assembled the following data pertaining to its two most popular products. Electric Mixer Blender $ 25 19 43 points Direct material Direct labor Manufacturing overhead @ $52 per machine hour Cost if purchased from an outside supplier Annual demand (units) 52 32 104 115 32,000 67 27,000 eBook Print Past experience has shown that the fixed manufacturing overhead component included in the cost per machine hour averages $40. Kitchen Magician's management has a...
# 42 Chef Gourmet, Inc., has assembled the following data pertaining to its two most popular products. Blender Food Processor Direct material $ 24 $ 41 Direct labor 18 31 Manufacturing overhead @ $50 per machine hour 50 100 Cost if purchased from an outside supplier 66 114 Annual demand (units) 26,000 30,000 Past experience has shown that the fixed manufacturing overhead component included in the cost per machine hour averages $36. Management has a policy of filling all sales...
TI Blender Electric Mixer $ $ Direct material 15 28 Direct labor 36 Manufacturing overhead@ $40 per machine hour Cost if purchased from an outside supplier Annual demand (units) 40 80 62 130 31,000 40,000 Past experience has shown that the fixed manufacturing overhead component included in the cost per machine hour averages $20. Kitchen Magician's management has a policy of filling all sales orders, even if it means purchasing units from outside suppliers. Required: 1. If 66,000 machine hours...
Tyson Corner Manufacturing produces two bearings: C15 and C19. Data regarding these two bearings follow. C15 C19 Machine hours required per unit 2.00 2.50 Standard cost per unit Direct material $2.50 $4.00 Direct labor 5.00 4.00 Manufacturing overhead: Variable* 3.00 2.50 Fixed** 4.00 5.00 Total $14.50 $15.50 * Applied on the basis of direct labor hours ** Applied on the basis of machine hours The company requires 8,000 units of C15 and 11,000 units of...
Please show all calculations. Tyson Corner Manufacturing produces two bearings: C15 and C19. Data regarding these two bearings follow C15 C19 2.00 2.50 Machine hours required per unit Standard cost per unit Direct material $2.50 $4.00 Direct labor 5.00 4.00 Manufacturing overhead: Variable 3.00 2.50 Fixed** 4.00 5.00 Total $14.50 $15.50 * Applied on the basis of direct labor hours Applied on the basis of machine hours ** The company requires 8,000 units of C15 and 11,000 units of C19....
Delph Company uses a job-order costing system and has two manufacturing departments-Molding and Fabrication. The company provided the following estimates at the beginning of the year: Total 66,000 Molding Fabrication Machine-hours Fixed manufacturing overhead costs Variable manufacturing overhead cost per machine-hour 28,000 38,000 260,000 $1,000,000 $ 740,000 $ 6.00$ 6.00 During the year, the company had no beginning or ending inventories and it started, completed, and sold only two jobs- Job D-70 and Job C-200. It provided the following information...
QUESTION 19 ABC has two departments, Machining and Assembly. The following estimates are for the coming year: Machining Assembly Direct manufacturing labor-hours 10,000 50,000 Machine-hours 40,000 20,000 Manufacturing overhead $200,000 $400,000 A single indirect-cost rate based on direct manufacturing labor-hours for the entire plant is: $ 8 per direct labor-hour $10 per direct labor-hour $20 per direct labor-hour None of these answers is correct.
QUESTION 19 ABC has two departments, Machining and Assembly. The following estimates are for the coming year: Machining Assembly Direct manufacturing labor-hours 10,000 50,000 Machine-hours 40,000 20,000 Manufacturing overhead $200,000 $400,000 A single indirect-cost rate based on direct manufacturing labor-hours for the entire plant is: $ 8 per direct labor-hour $10 per direct labor-hour $20 per direct labor-hour None of these answers is correct.
Assume a company has two manufacturing departments - Assembly and Fabrication. The company considers all of its manufacturing overhead costs to be fixed costs. The first set of data below is budgeted data for the company as a whole that was estimated at the beginning of the year. The second set of data below is actual data for the company as a whole that was derived at the end of the year. The third set of data relates to one...