Question

Dallas Company uses a job order costing system. The companys executives estimated that direct labor would be 52,990,000 (230

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Ans. Option 5th $6.65 per direct labor hour

*Calculation:

Predetermined overhead rate is calculated on the basis of the estimated values.

Predetermined overhead rate = Estimated overhead cost / Estimated direct labor hours

= $1,530,000 / 230,000

= $6.65 per direct labor hour

Add a comment
Know the answer?
Add Answer to:
Dallas Company uses a job order costing system. The company's executives estimated that direct labor would...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Dallas Company uses a job order costing system. The company's executives estimated that direct labor would...

    Dallas Company uses a job order costing system. The company's executives estimated that direct labor would be $5,130,000 (190,000 hours at $27/hour) and that factory overhead would be $1,430,000 for the current period. At the end of the period, the records show that there had been 110,000 hours of direct labor and $1,130,000 of actual overhead costs. Using direct labor hours as a base, what was the predetermined overhead rate? (Round your answer to two decimal places.) Multiple Choice $7.53...

  • Dallas Company uses a job order costing system. The company's executives estimated that direct labor would...

    Dallas Company uses a job order costing system. The company's executives estimated that direct labor would be $4,590,000 (270,000 hours at $17/hour) and that factory overhead would be $1,570,000 for the current period. At the end of the period, the records show that there had been 250,000 hours of direct labor and $1,270,000 of actual overhead costs. Using direct labor hours as a base, what was the predetermined overhead rate? (Round your answer to two decimal places.) $5.37 per direct...

  • Question 28 2 pts Dallas Company uses a job order costing system. The company's executives estimated that direct...

    Question 28 2 pts Dallas Company uses a job order costing system. The company's executives estimated that direct labor would be $2,000,000 (200,000 hours at $10/hour) and that factory overhead would be $1.500,000 for the current period. At the end of the period, the records show that there had been 180,000 hours of direct labor and $1,200,000 of actual overhead costs. Using direct labor hours as base, what was the predetermined overhead rate? $6.00 per direct labor hour. $7.50 per...

  • Hunter, Inc. uses a job order costing system. The company's executives estimated that direct labor would...

    Hunter, Inc. uses a job order costing system. The company's executives estimated that direct labor would be $1,500,000 (150,000 hours at $15/hour) and that estimated factory overhead would be $3,000,000 for the current period. At the end of the period, the records show that there had been 180,000 hours of direct labor and $1,800,000 of actual overhead costs. Using direct labor dollars as a base, what was the predetermined overhead rate? HTML Editor y В І U A А IX...

  • Hahn Company uses a job-order costing system. Its plantwide predetermined overhead rate uses direct labor-hours as...

    Hahn Company uses a job-order costing system. Its plantwide predetermined overhead rate uses direct labor-hours as the allocation base. The company pays its direct laborers $15 per hour. During the year, the company started and completed only two jobs—Job Alpha, which used 54,500 direct labor-hours, and Job Omega. The job cost sheets for the these two jobs are shown below: Job Alpha Direct materials Direct labor Manufacturing overhead applied Total job cost 2 ? $1,533,500 Job Omega Direct materials Direct...

  • Hahn Company uses a job-order costing system. Its plantwide predetermined overhead rate uses direct labor-hours as...

    Hahn Company uses a job-order costing system. Its plantwide predetermined overhead rate uses direct labor-hours as the allocation base. The company pays its direct laborers $13.00 per hour. During the year, the company started and completed only two jobs—Job Alpha, which used 64,200 direct labor-hours, and Job Omega. The job cost sheets for the these two jobs are shown below: Job Alpha Direct materials ? Direct labor ? Manufacturing overhead applied ? Total job cost $ 1,620,000 Job Omega Direct...

  • Hahn Company uses a job-order costing system. Its plantwide predetermined overhead rate uses direct labor-hours as...

    Hahn Company uses a job-order costing system. Its plantwide predetermined overhead rate uses direct labor-hours as the allocation base. The company pays its direct laborers $19.50 per hour. During the year, the company started and completed only two jobs—Job Alpha, which used 55,900 direct labor-hours, and Job Omega. The job cost sheets for the these two jobs are shown below: Job Alpha Direct materials ? Direct labor ? Manufacturing overhead applied ? Total job cost $ 2,230,000 Job Omega Direct...

  • Hahn Company uses a job-order costing system. Its plantwide predetermined overhead rate uses direct labor-hours as...

    Hahn Company uses a job-order costing system. Its plantwide predetermined overhead rate uses direct labor-hours as the allocation base. The company pays its direct laborers $13.00 per hour. During the year, the company started and completed only two jobs—Job Alpha, which used 64,200 direct labor-hours, and Job Omega. The job cost sheets for the these two jobs are shown below: Job Alpha Direct materials ? Direct labor ? Manufacturing overhead applied ? Total job cost $ 1,620,000 Job Omega Direct...

  • Hahn Company uses a job-order costing system. Its plantwide predetermined overhead rate uses direct labor-hours as...

    Hahn Company uses a job-order costing system. Its plantwide predetermined overhead rate uses direct labor-hours as the allocation base. The company pays its direct laborers $13.50 per hour. During the year, the company started and completed only two jobs-Job Alpha, which used 68,700 direct labor-hours, and Job Omega. The job cost sheets for the these two jobs are shown below. Job Alpha Direct materials Direct labor Manufacturing overhead applied Total job cost $ 1,722,000 Job Omega Direct materials Direct labor...

  • Hahn Company uses a job-order costing system. Its plantwide predetermined overhead rate uses direct labor-hours as...

    Hahn Company uses a job-order costing system. Its plantwide predetermined overhead rate uses direct labor-hours as the allocation base. The company pays its direct laborers $19.50 per hour. During the year, the company started and completed only two jobs—Job Alpha, which used 55,900 direct labor-hours, and Job Omega. The job cost sheets for the these two jobs are shown below: Job Alpha Direct materials Direct labor Manufacturing overhead applied Total job cost $ 2,230,000 Job Omega Direct materials Direct labor...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT