Greenwood Company manufactures two products—14,000 units of Product Y and 6,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z:

Activity Cost Pool Activity Measure Estimated Overhead Cost Expected
Activity
Machining Machine-hours $ 203,000 10,000 MHs
Machine setups Number of setups $ 121,900 230 setups
Production design Number of products $ 87,000 2 products
General factory Direct labor-hours $ 379,500 15,000 DLHs
Activity Measure Product Y Product Z
Machining 8,300 1,700
Number of setups 50 180
Number of products 1 1
Direct labor-hours 9,500 5,500

Required:

1. What is the company’s plantwide overhead rate? (Round your answer to 2 decimal places.)

2. Using the plantwide overhead rate, how much manufacturing overhead cost is allocated to Product Y and Product Z? (Round your intermediate calculations to 2 decimal places. Round your answers to the nearest dollar amount.)

3. What is the activity rate for the Machining activity cost pool? (Round your answer to 2 decimal places.)

4. What is the activity rate for the Machine Setups activity cost pool?

5. What is the activity rate for the Product Design activity cost pool?

6. What is the activity rate for the General Factory activity cost pool? (Round your answer to 2 decimal places.)

7. Which of the four activities is a batch-level activity?

  • Machining activity

  • General factory activity

  • Product design activity

  • Machine setups activity

8. Which of the four activities is a product-level activity?

  • Machining activity

  • Product design activity

  • Machine setups activity

  • General factory activity

9. Using the ABC system, how much total manufacturing overhead cost would be assigned to Product Y? (Round your intermediate calculations to 2 decimal places. Round your answers to the nearest dollar amount.)

10. Using the ABC system, how much total manufacturing overhead cost would be assigned to Product Z? (Round your intermediate calculations to 2 decimal places. Round your answers to the nearest dollar amount.)

11. Using the plantwide overhead rate, what percentage of the total overhead cost is allocated to Product Y and Product Z? (Round your intermediate calculations to 2 decimal places. Round your answers to 2 decimal places.)

12. Using the ABC system, what percentage of the Machining costs is assigned to Product Y and Product Z? (Round your intermediate calculations to 2 decimal places. Round your answers to 2 decimal places.)

13. Using the ABC system, what percentage of Machine Setups cost is assigned to Product Y and Product Z? (Round your intermediate calculations to 2 decimal places. Round your answers to 2 decimal places.)

4. Using the ABC system, what percentage of the Product Design cost is assigned to Product Y and Product Z? (Round your answers to 2 decimal places.)

15. Using the ABC system, what percentage of the General Factory cost is assigned to Product Y and Product Z? (Round your intermediate calculations and final answers to 2 decimal places.)

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer: 1.) companys Planturide overhead Rate can be Calculated by dividing Total estimated Overhead by Total espected direc3.) Calculation of activity Rate of machining activity Cost Pood are as follows: $ 2030vo Machining Cost (²) Number of machin

As per HOMEWORKLIB POLICY, i have to answer first 4 question in case multiple questions were posted.

So, please give a thumbs up

Thankyou.........

Add a comment
Know the answer?
Add Answer to:
Greenwood Company manufactures two products—14,000 units of Product Y and 6,000 units of Product Z. The...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Required information Greenwood Company manufactures two products—14,000 units of Product Y and 6,000 units of Product...

    Required information Greenwood Company manufactures two products—14,000 units of Product Y and 6,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool Activity Measure Estimated Overhead Cost Expected Activity Machining Machine-hours $ 198,000...

  • Required information Greenwood Company manufactures two products—14,000 units of Product Y and 6,000 units of Product...

    Required information Greenwood Company manufactures two products—14,000 units of Product Y and 6,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool Activity Measure Estimated Overhead Cost Expected Activity Machining Machine-hours $ 198,000...

  • Greenwood Company manufactures two products—14,000 units of Product Y and 6,000 units of Product Z. The...

    Greenwood Company manufactures two products—14,000 units of Product Y and 6,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool Activity Measure Estimated Overhead Cost Expected Activity Machining Machine-hours $ 209,000 10,000 MHs...

  • Required information Greenwood Company manufactures two products—14,000 units of Product Y and 6,000 units of Product...

    Required information Greenwood Company manufactures two products—14,000 units of Product Y and 6,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool Machining Machine setups Production design General factory Activity Measure Machine-hours Number...

  • Required information Greenwood Company manufactures two products—14,000 units of Product Y and 6,000 units of Product...

    Required information Greenwood Company manufactures two products—14,000 units of Product Y and 6,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool Machining Machine setups Production design General factory Activity Measure Machine-hours Number...

  • Required information Greenwood Company manufactures two products—14,000 units of Product Y and 6,000 units of Product...

    Required information Greenwood Company manufactures two products—14,000 units of Product Y and 6,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool Machining Machine setups Production design General factory Activity Measure Machine-hours Number...

  • Required information Greenwood Company manufactures two products-14,000 units of Product Y and 6,000 units of Product...

    Required information Greenwood Company manufactures two products-14,000 units of Product Y and 6,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool Machining Machine setups Production design General factory Activity Measure Machine-hours Number...

  • Required information Greenwood Company manufactures two products-14,000 units of Product Y and 6,000 units of Product...

    Required information Greenwood Company manufactures two products-14,000 units of Product Y and 6,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool Machining Machine setups Production design General factory Activity Measure Machine-hours Number...

  • iment Saved Required information Greenwood Company manufactures two products-14,000 units of Product Y and 6,000 units...

    iment Saved Required information Greenwood Company manufactures two products-14,000 units of Product Y and 6,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Estimated Expected Activity Overhead Activity Cost Pool Machining Machine setups Production design...

  • Greenwood Company manufactures two products-13,000 units of Product Y and 5,000 units of Product Z. The...

    Greenwood Company manufactures two products-13,000 units of Product Y and 5,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool Machining Machine setups Production design General factory Activity Measure Machine-hours Number of setups...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT