1) Computation of fixed manufacturing overhead cost per quarter
Fixed manufacturing overhead
=Total manufacturing overhead-variable manufacturing overhead
=[$240000 - (160000*$0.30) ]
=$240000-$48000
=$192000
2) Computation of the estimated unit product cost for the fourth quarter
Estimated unit product cost for the fourth quarter
=Total manufacturing costs / Number of units produced
=$528000/120000
=$4.4 per unit
Working notes
1) Total manufacturing costs for the fourth quarter
particulars | Amount($) |
Direct materials | 210000 |
Direct labor | 90000 |
Variable Manufacturing overhead {120000*$0.30} |
36000 |
Fixed Manufacturing overhead | 192000 |
Total manufacturing costs | 528000 |
3) Cause of estimated unit product cost to fluctuate from one quarter to the next
The change in fixed portion of manufacturing overhead cost causing the estimated unit product cost to fluctuate from one quarter to the next quarter.
This is because the fixed manufacturing overhead remains same irrespective of level of production activity. If there is an increase in production output units, the average fixed cost per unit decreases and viceversa.
4) Calculation of the unit product cost for all units producing during the year
Formula:
Unut product cost
=Total manufacturing costs for the year / Total units produced
=$1888000/400000
=$4.72 per unit
Working note:
1) Total manufacturing costs for the year
particulars | Amount($) |
First quarter | 640000 |
Second quarter | 416000 |
Third quarter | 304000 |
Fourth quarter | 528000 |
Total manufacturing costs for the year | 1888000 |
2) Total units produced
Particulars | Amount($) |
First quarter | 160000 |
Second quarter | 80000 |
Third quarter | 40000 |
Fourth quarter | 120000 |
Total units produced | 400000 |
------------*------------
DO VOTE, ALL THE BEST
Kingsport Containers Company makes a single product that is subject to wide seasonal variations in demand....
Kingsport Containers Company makes a single product that is subject to wide seasonal variations in demand. The company uses a job-order costing system and computes plantwide predetermined overhead rates on a quarterly basis using the number of units to be produced as the allocation base. Its estimated costs, by quarter, for the coming year are given below: Quarter First Second Third Fourth Direct materials $240,000 $120,000 $ 60,000 $180,000 Direct labor 160,000 80,000 40,000 120,000 Manufacturing overhead 240,000 216,000 204,000...
Kingsport Containers Company makes a single product that is subject to wide seasonal variations in demand. The company uses a job-order costing system and computes plantwide predetermined overhead rates on a quarterly basis using the number of units to be produced as the allocation base. Its estimated costs, by quarter, for the coming year are given below: Quarter First Second Third Fourth Direct materials $ 240,000 $ 120,000 $ 60,000 $ 180,000 Direct labor 160,000 80,000 40,000 120,000 Manufacturing overhead...
Kingsport Containers Company makes a single product that is subject to wide seasonal variations in demand. The company uses a job-order costing system and computes plantwide predetermined overhead rates on a quarterly basis using the number of units to be produced as the allocation base. Its estimated costs, by quarter, for the coming year are given below: Exercise 2-11 (Algo) Varying Plantwide Predetermined Overhead Rates (LO2-1, LO2-2, LO2-3] Kingsport Containers Company makes a single product that is subject to wide...
Kingsport Containers Company makes a single product that is subject to wide seasonal variations in demand. The company uses a job-order costing system and computes plantwide predetermined overhead rates on a quarterly basis using the number of units to be produced as the allocation base. Its estimated costs, by quarter, for the coming year are given below: Quarter First Second Third Fourth Direct materials $ 160,000 $ 80,000 $ 40,000 $ 120,000 Direct labor 160,000 80,000 40,000 120,000...
Kingsport Containers Company makes a single product that is subject to wide seasonal variations in demand. The company uses a job-order costing system and computes plantwide predetermined overhead rates on a quarterly basis using the number of units to be produced as the allocation base. Its estimated costs, by quarter, for the coming year are given below: Quarter First Second Third Fourth Direct materials $ 280,000 $ 140,000 $ 70,000 $ 210,000 Direct labor 120,000 60,000 30,000 90,000 Manufacturing overhead...
Kingsport Containers Company makes a single product that is subject to wide seasonal variations in demand. The company uses a job-order costing system and computes plantwide predetermined overhead rates on a quarterly basis using the number of units to be produced as the allocation base. Its estimated costs, by quarter, for the coming year are given below: Quarter First Second Third Fourth Direct materials $ 280,000 $ 140,000 $ 70,000 $ 210,000 Direct labor 160,000 80,000 40,000 120,000...
Kingsport Containers Company makes a single product that is subject to wide seasonal variations in demand. The company uses a job-order costing system and computes plantwide predetermined overhead rates on a quarterly basis using the number of units to be produced as the allocation base. Its estimated costs, by quarter, for the coming year are given below: Quarter First Second Third Fourth Direct materials $ 280,000 $ 140,000 $ 70,000 $ 210,000 Direct labor 120,000 60,000 30,000 90,000 Manufacturing overhead...
Kingsport Containers Company makes a single product that is subject to wide seasonal variations in demand. The company uses a job-order costing system and computes plantwide predetermined overhead rates on a quarterly basis using the number of units to be produced as the allocation base. Its estimated costs, by quarter, for the coming year are given below: Quarter First Second Third Fourth Direct materials $ 160,000 $ 80,000 $ 40,000 $ 120,000 Direct labor 160,000 80,000 40,000 120,000 Manufacturing overhead...
Kingsport Containers Company makes a single product that is subject to wide seasonal variations in demand. The company uses a job-order costing system and computes plantwide predetermined overhead rates on a quarterly basis using the number of units to be produced as the allocation base. Its estimated costs, by quarter, for the coming year are given below: Quarter First Second Third Fourth Direct materials $ 280,000 $ 140,000 $ 70,000 $ 210,000 Direct labor 160,000 80,000 40,000 120,000...
Kingsport Containers Company makes a single product that is subject to wide seasonal variations in demand. The company uses a job-order costing system and computes plantwide predetermined overhead rates on a quarterly basis using the number of units to be produced as the allocation base. Its estimated costs, by quarter, for the coming year are given below: Quarter First Second Third Fourth Direct materials $ 200,000 $ 100,000 $ 50,000 $ 150,000 Direct labor 160,000 80,000 40,000 120,000 Manufacturing...