Question

“Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the...

“Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the Koopers job by $4,000. It seems we’re either too high to get the job or too low to make any money on half the jobs we bid.”

Teledex Company manufactures products to customers’ specifications and uses a job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply its manufacturing overhead (assumed to be all fixed) to jobs. The following estimates were made at the beginning of the year:

Department
Fabricating Machining Assembly Total Plant
Manufacturing overhead $ 383,250 $ 438,000 $ 98,550 $ 919,800
Direct labor $ 219,000 $ 109,500 $ 328,500 $ 657,000

Jobs require varying amounts of work in the three departments. The Koopers job, for example, would have required manufacturing costs in the three departments as follows:

Department
Fabricating Machining Assembly Total Plant
Direct materials $ 4,900 $ 400 $ 3,300 $ 8,600
Direct labor $ 6,600 $ 700 $ 8,100 $ 15,400
Manufacturing overhead ? ? ? ?

Required:

1. Using the company's plantwide approach:

a. Compute the plantwide predetermined rate for the current year.

b. Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job.

2. Suppose that instead of using a plantwide predetermined overhead rate, the company had used departmental predetermined overhead rates based on direct labor cost. Under these conditions:

a. Compute the predetermined overhead rate for each department for the current year.

b. Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job.

4. Assume that it is customary in the industry to bid jobs at 150% of total manufacturing cost (direct materials, direct labor, and applied overhead).

a. What was the company’s bid price on the Koopers job using a plantwide predetermined overhead rate?

b. What would the bid price have been if departmental predetermined overhead rates had been used to apply overhead cost?

0 0
Add a comment Improve this question Transcribed image text
✔ Recommended Answer
Answer #1

Answer-

1.a. Plantwide predetermined overhead rate = Total estimated manufacturing overhead / Total estimated direct labor cost = $919,800 / $657000 = 140% of direct labor cost

1.b. Manufacturing overhead cost applied to Koopers job = 140% x $15400 = $21,560

2.a. Department
Fabricating Machining Assembly
Manufacturing overhead $ 383,250 438,000 98,550
Direct labor $ 219,000 109,500 328,500
Predetermined overhead rate % 175% 400% 30%
($383,250/$219.000) ($438,000/$109,500) ($98,550/$328,500)
2.b. Koopers Job Department
Fabricating Machining Assembly Total
Direct materials $ 4900 400 3300 8600
Direct labor $ 6600 700 8100 15400
Manufacturing overhead $ 11,550 2800 2430 16780
(175% x $6600) (400% x $700) (30% x $8100)
4.a. Koopers Job - Plantwide overhead rate
Direct materials $ 8600
Direct labor $ 15400
Manufacturing overhead $ 21560
Total manufacturing cost $ 45,560
Bid price $ (150% x $45,560) 68,340
4.b. Koopers Job - Departmental overhead rate
Direct materials $ 8600
Direct labor $ 15400
Manufacturing overhead $ 16,780
Total manufacturing cost $ 40,780
Bid price $ (150% x $40,780) 61,170
Add a comment
Know the answer?
Add Answer to:
“Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
  • “Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the...

    “Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the Koopers job by $3,000. It seems we’re either too high to get the job or too low to make any money on half the jobs we bid.” Teledex Company manufactures products to customers’ specifications and uses a job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply its manufacturing overhead (assumed to be all fixed) to...

  • “Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the...

    “Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the Koopers job by $4,000. It seems we’re either too high to get the job or too low to make any money on half the jobs we bid.” Teledex Company manufactures products to customers’ specifications and uses a job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply its manufacturing overhead (assumed to be all fixed) to...

  • “Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the...

    “Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the Koopers job by $4,000. It seems we’re either too high to get the job or too low to make any money on half the jobs we bid.” Teledex Company manufactures products to customers’ specifications and uses a job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply its manufacturing overhead (assumed to be all fixed) to...

  • "Blast it!" said David Wilson, president of Teledex Company. "We've just lost the bid on the...

    "Blast it!" said David Wilson, president of Teledex Company. "We've just lost the bid on the Koopers job by $4,000. It seems we're either too high to get the job or too low to make any money on half the jobs we bid." Teledex Company manufactures products to customers' specifications and operates a job order costing system. Manufacturing overhead cost is applied to jobs on the basis of direct labor cost. The following estimates were made at the beginning of...

  • “Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the...

    “Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the Koopers job by $4,000. It seems we’re either too high to get the job or too low to make any money on half the jobs we bid.” Teledex Company manufactures products to customers’ specifications and operates a job order costing system. Manufacturing overhead cost is applied to jobs on the basis of direct labor cost. The following estimates were made at the beginning of...

  • “Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the...

    “Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the Koopers job by $3,000. It seems we’re either too high to get the job or too low to make any money on half the jobs we bid.” Teledex Company manufactures products to customers’ specifications and uses a job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply its manufacturing overhead (assumed to be all fixed) to...

  • "Blast it!" said David Wilson, president of Teledex Company. "We've just lost the bid on the...

    "Blast it!" said David Wilson, president of Teledex Company. "We've just lost the bid on the Koopers job by $3,000. It seems we're either too high to get the job or too low to make any money on half the jobs we bid." Teledex Company manufactures products to customers' specifications and uses a job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply its manufacturing overhead (assumed to be all fixed) to...

  • "Blast it!" said David Wilson, president of Teledex Company. "We've just lost the bid on the...

    "Blast it!" said David Wilson, president of Teledex Company. "We've just lost the bid on the Koopers job by $4,000. It seems we're either too high to get the job or too low to make any money on half the jobs we bid." Teledex Company manufactures products to customers' specifications and uses a job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply its manufacturing overhead (assumed to be all fixed) to...

  • "Blast it!" said David Wilson, president of Teledex Company. "We've just lost the bid on the...

    "Blast it!" said David Wilson, president of Teledex Company. "We've just lost the bid on the Koopers job by $2,000. It seems we're either too high to get the job or too low to make any money on half the jobs we bid." Teledex Company manufactures products to customers' specifications and uses a job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply its manufacturing overhead (assumed to be all fixed) to...

  • "Blast it!" said David Wilson, president of Teledex Company. "We've just lost the bid on the...

    "Blast it!" said David Wilson, president of Teledex Company. "We've just lost the bid on the Koopers job by $3,000. It seems we're either too high to get the job or too low to make any money on half the jobs we bid." Teledex Company manufactures products to customers' specifications and uses a job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply its manufacturing overhead (assumed to be all fixed) to...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT