Question

Month Labor Cost($) Employee Hours January 9,590 530 February 7,100 620 March 7,631 660 April 8,240 490 May 9,887 570 June 8,

can someone help me understand these problem please?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer 2 - 16.91

Explanation-

Variable Rate = Highest Activity Cost - Loest Activity / Highest Activity Employee Hour - Lowest  Activity Employee Hour

Variable Rate = 12,682 - 7,100 / 740 - 410

= 5,582 / 330

= $16.91 employee per hour

Answer 3- Formula

Total Labour Cost = Fixed Cost + ( Variable Rate * Employee per hour)

= $ 330 + ( $16.91 * Employee per hour)

  

Note -  Highest activity cost is in the month of July as well as highest activity unit is in the same month.

Lowest activity cost is in the month of February but lowest activity is in the month of August

* Answer 1 is already mentioned in your Image.

Add a comment
Know the answer?
Add Answer to:
can someone help me understand these problem please? Month Labor Cost($) Employee Hours January 9,590 530...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • January 9,590 February 7,100 March 7,631 April 8,240 May 9,887 June 8,590 260 July 10,526 7,600...

    January 9,590 February 7,100 March 7,631 April 8,240 May 9,887 June 8,590 260 July 10,526 7,600 430 240 August Pizza Vesuvio's controller wants to calculate the fixed and variable costs associated with labor used in the restaurant. In your calculations, round the variable rate per employee hour to the nearest cent. If required, round your final answers to Required: 1. Using the high-low method, calculate the fixed cost of labor. 2. Using the high-low method, calculate the variable rate. per...

  • Using High-Low to Calculate Fixed Cost, Calculate the Variable Rate, and Construct a Cost Function Pizza...

    Using High-Low to Calculate Fixed Cost, Calculate the Variable Rate, and Construct a Cost Function Pizza Vesuvio makes specialty pizzas. Data for the past 8 months were collected: Month Labor Cost($) Employee Hours January 9,590 550 February 7,100 630 March 7,631 670 April 8,240 500 May 9,887 590 June 8,590 460 July 13,380 760 August 7,600 420 Pizza Vesuvio's controller wants to calculate the fixed and variable costs associated with labor used in the restaurant. In your calculations, round the...

  • Using High-Low to Calculate Fixed Cost, Calculate the Variable Rate, and Construct a Cost Function Pizza...

    Using High-Low to Calculate Fixed Cost, Calculate the Variable Rate, and Construct a Cost Function Pizza Vesuvio makes specialty pizzas. Data for the past 8 months were collected: Month Labor Cost($) Employee Hours January 9,590 430 February 7,100 500 March 7,631 530 April 8,240 400 May 9,887 460 June 8,590 360 July 11,864 590 August 7,600 330 Pizza Vesuvio's controller wants to calculate the fixed and variable costs associated with labor used in the restaurant. In your calculations, round the...

  • Last year, Phillips Company produced 300,000 units and sold 280,000 units. Beginning inventory was zero. During...

    Last year, Phillips Company produced 300,000 units and sold 280,000 units. Beginning inventory was zero. During the period, the following costs were incurred: Indirect labor (variable) $900,000 Indirect materials (variable) 600,000 Other variable manufacturing overhead 1,500,000 Fixed manufacturing overhead 2,400,000 Fored administrative expenses 300,000 Fixed ng expenses 450,000 Variable selling expenses, per unit Direct labor, per unit Direct materials, per unit Required: A. Compute the dollar amount of ending inventory using the Absorption costing B. Compute the dollar amount of...

  • Pizza Vesuvio makes specialty pizzas. Data for the past 8 months were collected: Month Labor Cost($)...

    Pizza Vesuvio makes specialty pizzas. Data for the past 8 months were collected: Month Labor Cost($) Employee Hours January 9,390 480 February 6,900 560 March 7,431 590 April 440 May 8,040 9,687 8,390 520 June 410 July 12,560 670 August 7,400 370 Pizza Vesuvio's controller wants to calculate the fixed and variable costs associated with labor used In your calculations, round the variable rate per employee hour to the nearest cent. If required, ro cent. Required: 1. Using the high-low...

  • Please help with these ASAP. I don't understand what I am doing wrong. Using High-Low to...

    Please help with these ASAP. I don't understand what I am doing wrong. Using High-Low to Calculate Fixed Cost, Calculate the Variable Rate, and Construct a Cost Function Pizza Vesuvio makes specialty pizzas. Data for the past 8 months were collected: Month January Labor Cost($) Employee Hours 9,690 510 7,200 7,731 620 February 590 March April 8,340 470 May 9,987 June 8,690 July 12,846 August 7,700 390 Pizza Vesuvio's controller wants to calculate the fixed and variable costs associated with...

  • Using High-Low to Calculate Fixed Cost, Calculate the Variable Rate, and Construct a Cost Function Pizza...

    Using High-Low to Calculate Fixed Cost, Calculate the Variable Rate, and Construct a Cost Function Pizza Vesuvio makes specialty pizzas. Data for the past 8 months were collected: Month Labor Cost($) Employee Hours January 9,490 570 February 7,000 660 March 7,531 700 April 8,140 May 9,787 620 480 June 8,490 July 13,520 790 August 7,500 440 Pizza Vesuvio's controller wants to calculate the fixed and variable costs associated with labor used in the restaurant. In your calculations, round the variable...

  • Using High-Low to Calculate Fixed Cost, Calculate the Variable Rate, and Construct a Cost Function Pizza...

    Using High-Low to Calculate Fixed Cost, Calculate the Variable Rate, and Construct a Cost Function Pizza Vesuvio makes specialty pizzas. Data for the past 8 months were collected: Month   Labor Cost($)   Employee Hours     January      9,290         310     February      6,800         360     March      7,331         380     April      7,940         290     May      9,587         340     June      8,290         260     July      10,378     ...

  • Using High-Low to Calculate Fixed Cost Calculate the Variable Rate, and Construct a Cost Function Pizza...

    Using High-Low to Calculate Fixed Cost Calculate the Variable Rate, and Construct a Cost Function Pizza Vesuvio makes specialty pizzas. Data for the past 8 months were collected: Month Labor Cost($) Employee Hours January 9,490 510 February 7,000 590 March 7,531 620 April 8,140 470 May 9,787 550 June 8,490 430 July 12,708 700 August 7,500 390 Pizza Vesuvio's controller wants to calculate the fixed and variable costs associated with labor used in the restaurant. In your calculations, round the...

  • Using High-Low to Calculate Fixed Cost, Calculate the Variable Rate, and Construct a Cost Function Pizza...

    Using High-Low to Calculate Fixed Cost, Calculate the Variable Rate, and Construct a Cost Function Pizza Vesuvio makes specialty pizzas. Data for the past 8 months were collected: Month   Labor Cost($)   Employee Hours     January      9,490         380     February      7,000         440     March      7,531         460     April      8,140         350     May      9,787         410     June      8,490         320     July      11,042     ...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT