The accounting treatment is given in accordance with IFRS15
In Year 1 :
Cost incurred = $8 million
Estimated total cost = $18 million
% of completion = $8/$18 = 44.44%
Contract Revenue to be recognised = $25 million x 44.44% = $11.11 million
In Year 2 :
Cost incurred till date = $9.5 m + $8 m = $17.5 million
Total estimated cost = $20 million
% of completion = $17.5/$20 = 87.5%
Contract Revenue to be recognised till date = $25 million x 87.5% = $21.875 million
Contract Revenue recognised in previous year = $11.11 million
So Revenue recognised this year = $10.765
In Year 3 :
Total cost = $20.5 million
Total Revenue = $25 million
Revenue already recognised = $11.11m + $10.765m = $21.875 million
Revenue to be recognised in current year = $3.125 million
Journal Entries
In 20X1
Contract Costs $8 million
Cash $8 million
(Costs incurred for construction)
At end of 20X1
Cost of goods sold $8 million
Contract Costs $8 million
(Construction costs transferred to Cost of goods sold)
Contract Asset $11.11 million
Contract Revenue $11.11 million
(Progress Billings made are now accounted)
Accounts Receivable $9 million
Progress Billings $9 million
(Progress Billings of worth $9 million made)
Cash $8.5 million
Accounts Receivable $8.5 million
(Amount received from client)
In 20X2
Contract Costs $9.5 million
Cash $9.5 million
At end of 20X2
Cost of goods sold $9.5 million
Contract Costs $9.5 million
Contract Asset $10.765 million
Contract Revenue $10.765 million
Accounts Receivable $10 million
Progress Billings $10 million
Cash $9.5 million
Accounts Receivable $9.5 million
In 20X3
Contract Costs $3 million
Cash $3 million
At end of 20X3
Cost of Goods Sold $3 million
Contract Costs $3 million
Contract Asset $3.125 million
Contract Revenue $3.125 million
Accounts Receivable $6 million
Progess Billings $6 million
Cash $7 million
Accounts Receivable $7 million
At the year end in balance sheet, the net off Contract Asset and Progress Billings is shown on assets side along with Accounts Receivable.
Note :
In the above entries, instead of "contract asset" we can also use "Construction WIP"
Narrations will be similar for year 2, year 3. Hence not repeated
Revenue Recognition Percentage Complete: Cost Basis, Test #1 The City of Denver, Colorado contracted with Wenwegetoit...
Percentage complete, Cost Basis. I need help figuring out the percentages to date and percentages yearly. I initially did 44% but since it says round to two decimal places I changed it to 44.44 and got different numbers. Please help! ($ millions) $ 25.00 Expected Revenue (contract amount in millions of dollars) $ millions) Project Started 20X1 20X2 18.00 $ 20.00 $ 8.00 $ 9.50 $ 9.00 $ 10.00 $ 8.50 $ 9.50 $ Estimated Total Cost (per Engineering) Actual...
Bright Future signed a $700,000 contract to an d the project required three years to complete. Bright Future estimated that total contract coswabe SGD 000 The financial information during 2031 203 related to the construction contracts as the following 2002 2003 Costs incurred to date $200.000 $370,000 $610,000 Estimated costs to complete 400 000 250.000 Progress bilings made during the year 210,000 315.000 175.000 Collections of billings during the year 200,000 320,000 180,000 Additional information: 1) The customer does not...
Case Study Revenue Recognition For this case, you are the lead analyst for a team considering the potential acquisition of three separate projects of a single company, Gasco. You are to determine if your team will acquire one, two, all three of the projects; or none of them. The team intends to acquire any project it deems profitable over the duration of the project. For purposes of this case, ignore purchase price of the projects. Gasco is a natural gas...
1.Which of the following statements is true regarding the new ASC Topic 606 for revenue recognition? Multiple Choice The focus is on when the firm has earned the consideration to which it is entitled. Early adoption is not allowed. The new rules are more rules-based than principle-oriented. Under IFRS, both public and non-public firms must adopt by 2018 2.Assuming the requirements for recognizing revenue over time are met, the measure of completion is computed by dividing Multiple Choice profits earned...
MULTIPLE-CHOICE questions E1-1.ABC Engineering use cost method to cart engineering use cost method to calculate the stage of completion of its construction act. Total estimated contract costs of their contract are $100 million. In the first year of their contract, ABC Engineering has incurred the following costs: Cost of purchase of raw materials worth $10 million ($5 million of which are unused by the year end) 2. Payment of salaries and wages of $5 million ($1 million of accrued salaries...
a. Suppose Greenfield chooses to allocate indirect cost based on direct cost. 1. What cost would be allocated to the two units (Corporate and Government)? 2. What total revenue would they expect to collect next year? b. Suppose Greenfield chooses to allocate indirect cost based on direct contract hours worked 1. What cost would be allocated to the two units (Corporate and Government)? 2. What total revenue would they expect to collect next year? Complete this question by entering your...
Please explain in detail how you reach each answer. Problem 2-67 (Static) Cost Allocation and Pricing (LO 2-3) points Greenfield Consultants conducts analyses of public policy issues. The company has two units: Government with various US government agencies as the only clients) and Corporate with several corporations as clients). Government business is charged based on the total costs (direct and indirect) plus a 15 percent fee (profit). Corporate clients are charged a fixed fee negotiated at the beginning of the...
Required: 1. What is the amount of Apple’s accounts receivable as of September 30, 2017? 2. Compute Apple’s accounts receivable turnover as of September 30, 2017. 3. How long does it take, on average, for the company to collect receivables for fiscal year ended September 30, 2017? 4. Apple’s most liquid assets include (a) cash and cash equivalents, (b) short-term marketable securities, (c) accounts receivable, and (d) inventory. Compute the percentage that these liquid assets (in total) make up of...