Question

You have been assigned for reviewing the actual and budgeted figures of the variable manufacturing overhead of straight umbre

0 0
Add a comment Improve this question Transcribed image text
Answer #1

a)

Static budget variance

Fixed budgeted Variable manufacturing overhead                  = 100 units x 5 hours x $20 = $10000

Actual Variable manufacturing overhead                                  =                                                  $12000

Variance        = 10000 – 12000 = -2000 Adverse                                                  

Flexible budget variance

Flexed budgeted Variable manufacturing overhead               = 95 units x 5 hours x $20 = $9500

Actual Variable manufacturing overhead                                  =                                                $12000

Variance        = 9500 – 12000 = -2500 Adverse           

Sales Volume variance

                                             = (Budgeted Units of sales – Actual Units of sales) x Budgeted price per unit

                                             = (100 – 95 )     x Budgeted price (?Not given in the question)            

Variable overhead spending variance        

                                                = Actual hours x (Standard Rate – Actual Rate)

Actual hours = 490 hours

Actual Rate    = $12000/490 hours = $24.49           

Standard Rate =   $20                           

Spending Variance = 490 (20 – 24.49) = -2200 Adverse          

Variable overhead efficiency variance      

                                              = Standard overhead rate x (Standard hours – Actual hours)

Standard hours for actual production = 95 x 5 = 475 hours

                                Efficiency variance             = $20 x (475 hours – 490 hours) = $300 Adv

b) Static budget variance calculation is always will not give correct variance as we are not able to compare like with like. It calculates only the differences between budgeted figure and actual figures. The actual activity level may vary and the actual amount of overhead expenditure will not be the same as budget. Static budget variance is the difference between what a company it would spend in its budget versus what it actually it did.   In this case it showed an adverse variance of 2000 but actually there is a difference of 2500 when the budget is flexed. For producing 95 units they should take 475 hours and $20 per hour means the variable should have been $9500. Instead of it actual amount of overhead was $12000. Resulting into an adverse variance of 2500.

Efficiency variance is the difference between actual and budgeted hours worked measured in standard hours. Actually worked 490 hours against the budget of 475 hours (95 x5). Extra 15 hours worked than the standard. So there is an adverse variance of (15 x $20) $300.

So the management is not always correct with their static budget variances. Better to consider flexible budget variances for correct decisions.

Add a comment
Know the answer?
Add Answer to:
You have been assigned for reviewing the actual and budgeted figures of the variable manufacturing overhead...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Norwall Company’s budgeted variable manufacturing overhead cost is $1.30 per machine-hour and its budgeted fixed manufacturing...

    Norwall Company’s budgeted variable manufacturing overhead cost is $1.30 per machine-hour and its budgeted fixed manufacturing overhead is $30,624 per month. The following information is available for a recent month: The denominator activity of 9,570 machine-hours is used to compute the predetermined overhead rate. At a denominator activity of 9,570 machine-hours, the company should produce 3,300 units of product. The company’s actual operating results were: Number of units produced 4,570 Actual machine-hours 10,090 Actual variable manufacturing overhead cost $ 14,630...

  • Norwall Company’s budgeted variable manufacturing overhead cost is $1.95 per machine-hour and its budgeted fixed manufacturing...

    Norwall Company’s budgeted variable manufacturing overhead cost is $1.95 per machine-hour and its budgeted fixed manufacturing overhead is $36,036 per month. The following information is available for a recent month: The denominator activity of 18,480 machine-hours is used to compute the predetermined overhead rate. At a denominator activity of 18,480 machine-hours, the company should produce 6,600 units of product. The company’s actual operating results were: Number of units produced 7,550 Actual machine-hours 19,630 Actual variable manufacturing overhead cost $ 41,223...

  • Norwall Company's budgeted variable manufacturing overhead cost is $1.40 per machine-hour and its budgeted fixed manufacturing...

    Norwall Company's budgeted variable manufacturing overhead cost is $1.40 per machine-hour and its budgeted fixed manufacturing overhead is $77,350 per month. The following information is available for a recent month: a. The denominator activity of 22,750 machine-hours is used to compute the predetermined overhead rate. b. At a denominator activity of 22,750 machine-hours, the company should produce 9,100 units of product. c. The company's actual operating results were: Number of units produced Actual machine-hours Actual variable manufacturing overhead cost Actual...

  • Norwall Company's budgeted variable manufacturing overhead cost is $1.30 per machine-hour and its budgeted fixed manufacturing...

    Norwall Company's budgeted variable manufacturing overhead cost is $1.30 per machine-hour and its budgeted fixed manufacturing overhead is $30,624 per month. The following information is available for a recent month: a. The denominator activity of 9,570 machine-hours is used to compute the predetermined overhead rate. b. At a denominator activity of 9,570 machine-hours, the company should produce 3,300 units of product. c. The company's actual operating results were: Number of units produced Actual machine-hours Actual variable manufacturing overhead cost Actual...

  • Norwall Company's budgeted variable manufacturing overhead cost is $1.90 per machine-hour and its budgeted fixed manufacturing...

    Norwall Company's budgeted variable manufacturing overhead cost is $1.90 per machine-hour and its budgeted fixed manufacturing overhead is $87,000 per month. The following information is available for a recent month: a. The denominator activity of 34,800 machine-hours is used to compute the predetermined overhead rate. b. At a denominator activity of 34,800 machine-hours, the company should produce 12,000 units of product. c. The company's actual operating results were: Number of units produced Actual machine-hours Actual variable manufacturing overhead cost Actual...

  • Norwall Company's budgeted variable manufacturing overhead cost is $1.20 per machine-hour and its budgeted fixed manufacturing...

    Norwall Company's budgeted variable manufacturing overhead cost is $1.20 per machine-hour and its budgeted fixed manufacturing overhead is $105,966 per month. The following information is available for a recent month: a. The denominator activity of 33,640 machine-hours is used to compute the predetermined overhead rate. b. At a denominator activity of 33,640 machine-hours, the company should produce 11,600 units of product. c. The company's actual operating results were: Number of units produced Actual machine-hours Actual variable manufacturing overhead cost Actual...

  • Norwall Company's budgeted variable manufacturing overhead cost is $1.80 per machine-hour and its budgeted fixed manufacturing...

    Norwall Company's budgeted variable manufacturing overhead cost is $1.80 per machine-hour and its budgeted fixed manufacturing overhead is $54,868 per month. The following information is available for a recent month: a. The denominator activity of 25,520 machine-hours is used to compute the predetermined overhead rate. b. At a denominator activity of 25,520 machine-hours, the company should produce 11,600 units of product. c. The company's actual operating results were: Number of units produced Actual machine-hours Actual variable manufacturing overhead cost Actual...

  • Norwall Company's budgeted variable manufacturing overhead cost is $1.90 per machine-hour and its budgeted fixed manufacturing...

    Norwall Company's budgeted variable manufacturing overhead cost is $1.90 per machine-hour and its budgeted fixed manufacturing overhead is $87,000 per month. The following information is available for a recent month: a. The denominator activity of 34,800 machine-hours is used to compute the predetermined overhead rate. b. At a denominator activity of 34,800 machine-hours, the company should produce 12,000 units of product. c. The company's actual operating results were: Number of units produced Actual machine-hours Actual variable manufacturing overhead cost Actual...

  • Norwall Company's budgeted variable manufacturing overhead cost is $1.90 per machine-hour and its budgeted fixed manufacturing...

    Norwall Company's budgeted variable manufacturing overhead cost is $1.90 per machine-hour and its budgeted fixed manufacturing overhead is $87,000 per month. The following information is available for a recent month a. The denominator activity of 34,800 machine-hours is used to compute the predetermined overhead rate b. At a denominator activity of 34,800 machine-hours, the company should produce 12,000 units of product. c. The company's actual operating results were Number of units produced Actual machine-hours Actual variable manufacturing overhead cost Actual...

  • 17 Norwall Company's budgeted variable manufacturing overhead cost is $3.00 per machine hour and its budgeted...

    17 Norwall Company's budgeted variable manufacturing overhead cost is $3.00 per machine hour and its budgeted fixed manufacturing overhead is $300,000 per month 0.72 points The following information is available for a recent month: a The denominator activity of 60,000 machine hours is used to compute the predetermined overhead rate. b. At a denominator activity of 60,000 machine hours, the company should produce 40,000 units of product c. The company's actual operating results were: Number of units produced Actual machine-hours...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT