13) | Unit product cost | = | $ 1,027 | ($ 30800 / 30) | ||
15) | Cost of Goods sold | = | $ 81,300.00 | ($ 50500 + $ 30800) |
Workings:
Computation of departmental overhead rates | |||||
Particulars | Molding | Fabrication | |||
Estimated total fixed manufacturing OH | $ 10,000.00 | $ 15,000.00 | |||
Estimated total machine hours | 2500 | 1500 | |||
Fixed manufacturing OH per machine hour | $ 4.00 | $ 10.00 | |||
Variable manufacturing OH per machine hour | $ 1.40 | $ 2.20 | |||
Departmental overhead rates | $ 5.40 | $ 12.20 |
Computation of manufacturing cost | ||||
Particulars | Job P | Job Q | ||
Direct Materials | $ 13,000.00 | $ 8,000.00 | ||
Direct Labor | $ 21,000.00 | $ 7,500.00 | ||
Manufacturing OH: | ||||
Molding | $ 9,180.00 | $ 4,320.00 | ||
Fabrication | $ 7,320.00 | $ 10,980.00 | ||
Total manufacturing cost | $ 50,500.00 | $ 30,800.00 |
Please let me know if you find this incorrect. Thank you
[The following information applies to the questions displayed below.) Sweeten Company had no jobs in progress...
[The following information applies to the questions displayed below.) Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments-Molding and Fabrication. It started, completed, and sold only two jobs during March- Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month of March): Estimated total machine-hours used...
[The following information applies to the questions displayed below.) Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments--Molding and Fabrication. It started, completed, and sold only two jobs during March-Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month of March); Estimated total machine-hours used Estimated...
The following information applies to the questions displayed below Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments-Molding and Fabrication. It started, completed, and sold only two jobs during March- Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month of March): Molding Fabrication Total 2,500...
[The following information applies to the questions displayed below.) Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments-Molding and Fabrication. It started, completed, and sold only two jobs during March-Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month of March): Molding Fabrication Total 2.500 1,500...
(The following information applies to the questions displayed below.) Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments-Molding and Fabrication. It started, completed, and sold only two jobs during March- Job P and Job Q. The following additional Information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month of March): Molding Fabrication Total Estimated...
[The following information applies to the questions displayed below.) Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments-Molding and Fabrication. It started, completed, and sold only two jobs during March- Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month of March): Estimated total machine-hours used...
[The following information applies to the questions displayed below.) Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments-Molding and Fabrication. It started, completed, and sold only two jobs during March- Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month of March): Estimated total machine-hours used...
The following information applies to the questions displayed below) Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments-Molding and Fabrication. It started, completed, and sold only two jobs during March- Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month of March): Estimated total machine-hours used...
[The following information applies to the questions displayed below.] Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments--Molding and Fabrication. It started, completed, and sold only two jobs during March—Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month of March): Molding Fabrication Total Estimated total...
fine following information applies to the questions displayed below Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments --Molding and Fabrication. It started, completed, and sold only two jobs during March-Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month of March): Estimated total machine-hours used...