Requirement 1:
a.
Fixed manufacturing overhead | $ 784,000 | |
Direct labor hours required to support estimated production | 140000 | |
Variable manufacturing overhead cost per direct labor hour | $ 2.00 | |
Total direct labor [140000*2] | $ 280,000 | |
Estimated total manufacturing overhead [784000+280000] | $ 1,064,000 | |
Plantwide Predetermined overhead rate [1064000/140000] | $ 7.60 | Per DLH |
Plantwide Predetermined overhead rate = Estimated total manufacturing overhead/ Estimated direct labor hours |
b.
Direct materials | $ 175 |
Direct labor | $ 225 |
Manufacturing overhead applied [15*7.60] | $ 114 |
Total manufacturing cost of Job 550 | $ 514 |
c.
Total manufacturing cost | $ 514 |
Mark up [ 514*200%] | $ 1,028 |
Selling price of Job 550 | $ 1,542 |
Requirement 2
a.
Fixed manufacturing overhead | $ 784,000 | |
Machine labor hours required to support estimated production | 70000 | |
Variable manufacturing overhead cost per direct labor hour | $ 4.00 | |
Total Machine cost [70000*4] | $ 280,000 | |
Estimated total manufacturing overhead [784000+280000] | $ 1,064,000 | |
Plantwide Predetermined overhead rate [1064000/70000] | $ 15.20 | Per MH |
b.
Direct materials | $ 175 |
Direct labor | $ 225 |
Manufacturing overhead applied [5*15.20] | $ 76 |
Total manufacturing cost of Job 550 | $ 476 |
c.
Total manufacturing cost | $ 476 |
Mark up [ 476*200%] | $ 952 |
Selling price of Job 550 | $ 1,428 |
Problem 2-16 (Static) Plantwide Predetermined Overhead Rates; Pricing [LO2-1, LO2-2, LO2-3] Landen Corporation uses a job-order...
Problem 2-16 (Static) Plantwide Predetermined Overhead Rates; Pricing (LO2-1, LO2-2, LO2-3] Landen Corporation uses a job-order costing system. At the beginning of the year, the company made the following estimates: Direct labor-hours required to support estimated production Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per direct labor-hour Variable manufacturing overhead cost per machine-hour 140,000 70,000 $784,000 $ 2.00 $ 4.00 During the year, Job 550 was started and completed. The following information is...
Problem 2-16 (Static) Plantwide Predetermined Overhead Rates; Pricing (LO2-1, LO2-2, LO2-3] Landen Corporation uses a job-order costing system. At the beginning of the year, the company made the following estimates: Direct labor-hours required to support estimated production Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per direct labor-hour Variable manufacturing overhead cost per machine-hour 140,000 70,000 $784,000 $ 2.00 $ 4.00 During the year, Job 550 was started and completed. The following information is...
Problem 2-16 Plantwide Predetermined Overhead Rates; Pricing (LO2-1, LO2-2, LO2-3] 0.66 Landen Corporation uses a job-order costing system. At the beginning of the year, the company made the following estimates: points eBook Direct labor-hours required to support estimated production Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per direct labor-hour Variable manufacturing overhead cost per machine-hour 140,000 70,000 $784,000 $ 2.00 $ 4.00 Print References During the year, Job 550 was started and completed....
Problem 2-16 Plantwide Predetermined Overhead Rates; Pricing (LO2-1, LO2-2, LO2-3) Landen Corporation uses a job-order costing system. At the beginning of the year, the company made the following estimates: Direct labor-hours required to support estimated production Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per direct labor-hour Variable manufacturing overhead cost per machine-hour 80,000 40,000 $240.000 $ 1.80 $ 3.60 During the year, Job 550 was started and completed. The following information is available...
Problem 2-16 Plantwide Predetermined Overhead Rates; Pricing [LO2-1, LO2-2, LO2-3] Landen Corporation uses a job-order costing system. At the beginning of the year, the company made the following estimates: Direct labor-hours required to support estimated production 140,000 Machine-hours required to support estimated production 70,000 Fixed manufacturing overhead cost $ 784,000 Variable manufacturing overhead cost per direct labor-hour $ 2.00 Variable manufacturing overhead cost per machine-hour $ 4.00 During the year, Job 550 was started and completed. The following information is...
Problem 2-16 Plantwide Predetermined Overhead Rates; Pricing [LO2-1, LO2-2, LO2-3] Landen Corporation uses a job-order costing system. At the beginning of the year, the company made the following estimates Direct labor-hours required to support estimated production Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per direct labor-hour Variable manufacturing overhead cost per machine-hour 60,000 30,000 $180,000 $ 1.00 $ 2.00 During the year, Job 550 was started and completed. The following information is available...
Problem 2-16 Plantwide Predetermined Overhead Rates; Pricing (LO2-1, LO2-2, LO2-3] Landen Corporation uses a job-order costing system. At the beginning of the year, the company made the following estimates: hours required to support estimated production Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per direct labor-hour Variable manufacturing overhead cost per machine-hour 120,000 60,000 $336,000 $ 3.60 $ 7.20 During the year, Job 550 was started and completed. The following information is available with...
Problem 2-16 Plantwide Predetermined Overhead Rates; Pricing (L02-1, LO2-2, LO2-3) Landen Corporation uses a job-order costing system. At the beginning of the year, the company made the following estimates: Direct labor-hours required to support estimated production Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per direct labor-hour Variable manufacturing overhead cost per machine-hour 1 40,000 70,000 $784, eee $ 2.00 $ 4.00 During the year, Job 550 was started and completed. The following information...
Problem 2-16 Plantwide Predetermined Overhead Rates; Pricing [LO2-1, LO2-2, LO2-3] Landen Corporation uses a job-order costing system. At the beginning of the year, the company made the following estimates: Direct labor-hours required to support estimated production Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per direct labor-hour Variable manufacturing overhead cost per machine-hour 80,000 40,000 $ 240,000 $ 1.80 $ 3.60 During the year, Job 550 was started and completed. The following information is...
Problem 2-16 Plantwide Predetermined Overhead Rates; Pricing (LO2-1, LO2-2, LO2-3) Landen Corporation uses a job-order costing system. At the beginning of the year, the company made the following estimates: Direct labor-hours required to support estimated production Machine-hours required to support estimated production Fixed Manufacturing overhead cost Variable manufacturing overhead cont per direct labor-hour Variable manufacturing overhead cost per machine-hour 95,000 47,500 $266,000 $ 2.60 $ 5.20 During the year, Job 550 was started and completed. The following information is available...