Question

Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct...

Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: Direct materials: 5 kg at $9.00 per kg $ 45.00 Direct labour: 3 hours at $14 per hour 42.00 Variable overhead: 3 hours at $9 per hour 27.00 Total standard cost per unit $ 114.00 The company planned to produce and sell 20,000 units in March. However, during March the company actually produced and sold 24,800 units and incurred the following costs: Purchased 155,000 kg of raw materials at a cost of $7.20 per kg. All of this material was used in production. Direct labour: 65,000 hours at a rate of $15 per hour. Total variable manufacturing overhead for the month was $612,300. 2. What is the materials quantity variance for March? (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance.).)

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Formula for Calculation of Materials Quantity Variance = (Standard Quantity of Material for Actual Output - Actual Quantity Used) * Standard Material Rate

Standard Quantity of Material for Actual Output = Actual Output * Standard Quantity of Material for One Unit of Production

Actual Output = 24,800 Units

Standard Quantity of Material for One Unit = 5 Kg

Standard Quantity of Material for Actual Output = 24,800 * 5

Standard Quantity of Material for Actual Output = 124,000 Kgs

Standard Material Rate per KG = $ 9

Actual Quantity of Material Used = 155,000 Kgs

Material Quantity Variance for March = (124,000 - 155,000) * 9

Material Quantity Variance = (31,000) * 9

Material Quantity Variance = ($ 279,000)

Material Quantity Variance = $ 279,000 Unfavorable Variance

Add a comment
Know the answer?
Add Answer to:
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct...

    Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows:   Direct materials: 5 kg at $9.00 per kg $ 45.00     Direct labour: 3 hours at $14 per hour 42.00     Variable overhead: 3 hours at $9 per hour 27.00     Total standard cost per unit $ 114.00   The company planned to produce and sell 20,000 units in March. However, during March the company actually produced and...

  • Ultration of 6 (The following information applies to the questions displayed below.) Preble Company manufactures one...

    Ultration of 6 (The following information applies to the questions displayed below.) Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: 53:01 Direct materials: 5 kg at $9.00 per kg Direct labour: 3 hours at $14 per hour Variable overhead: 3 hours at $9 per hour $ 45.00 42.00 27.00 t Total standard cost per unit $ 114.00 The company planned to produce...

  • Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct...

    Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: Direct materials: 6 kg at $9.00 per kg Direct labour: 3 hours at $15 per hour Variable overhead: 3 hours at $5 per hour $ 54.00 45.00 15.00 Total standard cost per unit $ 114.00 The company planned to produce and sell 20,000 units in March. However, during March the company actually produced and...

  • Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct...

    Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows:   Direct materials: 4 kg at $9.00 per kg $ 36.00     Direct labour: 3 hours at $12 per hour 36.00     Variable overhead: 3 hours at $8 per hour 24.00     Total standard cost per unit $ 96.00   The company planned to produce and sell 28,000 units in March. However, during March the company actually produced and...

  • Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct...

    Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: Direct materials: 6 kg at $8.00 per kg $ 48.00 Direct labour: 4 hours at $13 per hour 52.00 Variable overhead: 4 hours at $5 per hour 20.00 Total standard cost per unit $ 120.00 The company planned to produce and sell 20,000 units in March. However, during March the company actually produced and...

  • Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct...

    Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: Direct materials: 6 kg at $8.00 per kg $ 48.00 Direct labour: 4 hours at $13 per hour 52.00 Variable overhead: 4 hours at $5 per hour 20.00 Total standard cost per unit $ 120.00 The company planned to produce and sell 20,000 units in March. However, during March the company actually produced and...

  • Help Save 6 Required information [The following information applies to the questions displayed below.) Preble Company...

    Help Save 6 Required information [The following information applies to the questions displayed below.) Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: 0:47 Direct materials: 5 kg at $9.00 per kg Direct labour: 3 hours at $14 per hour Variable overhead: 3 hours at $9 per hour $ 45.00 42.00 27.00 Total standard cost per unit $ 114.00 The company planned to...

  • Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct...

    Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: Direct materials: 6 kg at $8.00 per kg $ 48.00 Direct labour: 4 hours at $13 per hour 52.00 Variable overhead: 4 hours at $5 per hour 20.00 Total standard cost per unit $ 120.00 The company planned to produce and sell 20,000 units in March. However, during March the company actually produced and...

  • Check my Work Preble Company manufactures one product. Its variable manufacturing overhead is applied to production...

    Check my Work Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labor-hours and its standard cost card per unit is as follows: $ 45 Direct materials: 5 pounds at $9 per pound Direct labor: 3 hours at $14 per hour Variable overhead: 3 hours at $9 per hour Total standard cost per unit 2 $ 114 The planning budget for March was based on producing and selling 20,000 units. However, during March...

  • Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct...

    Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: 55.00 36.00 Direct materials: 5 $ kg at $11.00 per kg Direct labour: 3 hours at $12 per hour Variable overhead: 3 hours at $7 per hour 21.00 $ 112.00 Total standard cost per unit The company planned to produce and sell The company planned to produce and sell 21,000 units in March. However,...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT