Estimated total machine-hours used Estimated total fixed manufacturing overhead Estimated variable manufacturing overhead per
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution:

Predetermined overhead rate = Estimated total overhead / Estimated machine hours = (2500*$1.40 + 1500*$2.20 + $25,000) / 4000

= $7.95 per machine hour

Computation of overhead applied - Plantwide overhead rate
Particulars Job Q
Actual machine hours 1700
Overhead rate $7.95
Overhead applied to jobs $13,515.00
Particulars Job Q
Direct Material $8,000
Direct Labor $7,500
Manufacturing overhead $13,515
Total Manufacturing cost $29,015
Particulars Job Q
Total Manufacturing cost $29,015.00
Nos of units 30
Unit product cost $967
Add a comment
Know the answer?
Add Answer to:
Estimated total machine-hours used Estimated total fixed manufacturing overhead Estimated variable manufacturing overhead per machine-hour Molding...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT