Question

Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Predetermined overhead rate= Estimated total manufacturing overhead costs/Estimated direct labor costs

= $907200/756000

= 120% of direct labor cost

Predetemined overhead rate 120%

NOTE:- Please rate the answer and for any problem regarding the answer please ask in the comment section.

Add a comment
Know the answer?
Add Answer to:
Lott Company uses a job order cost system and applies overhead to production on the basis...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Lott Company uses a job order cost system and applies overhead to production on the basis...

    Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $21,600, direct labor $12,960, and manufacturing overhead $17,280. As of January 1, Job 49 had been completed at a cost of $97,200 and was part of finished goods inventory. There was a $16,200...

  • Problem 15-01A Lott Company uses a job order cost system and applies overhead to production on...

    Problem 15-01A Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $21,600, direct labor $12,960, and manufacturing overhead $17,280. As of January 1, Job 49 had been completed at a cost of $97,200 and was part of finished goods inventory. There was...

  • Lott Company uses a job order cost system and applies overhead to production on the basis...

    Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $23,200, direct labor $13,920, and manufacturing overhead $18,560. As of January 1, Job 49 had been completed at a cost of $104,400 and was part of finished goods inventory. There was a $17,400...

  • Lott Company uses a job order cost system and applies overhead to production on the basis...

    Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $23,400, direct labor $14,040, and manufacturing overhead $18,720. As of January 1, Job 49 had been completed at a cost of $105,300 and was part of finished goods inventory. There was a $17,550...

  • Lott Company uses a job order cost system and applies overhead to production on the basis...

    Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $23,400, direct labor $14,040, and manufacturing overhead $18,720. As of January 1, Job 49 had been completed at a cost of $105,300 and was part of finished goods inventory. There was a $17,550...

  • Lott Company uses a job order cost system and applies overhead to production on the basis...

    Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $21,200, direct labor $12,720, and manufacturing overhead $16,960. As of January 1, Job 49 had been completed at a cost of $95,400 and was part of finished goods inventory. There was a $15,900...

  • Lott Company uses a job order cost system and applies overhead to production on the basis...

    Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $22,600, direct labor $13,560, and manufacturing overhead $18,080. As of January 1, Job 49 had been completed at a cost of $101,700 and was part of finished goods inventory. There was a $16,950...

  • Lott Company uses a job order cost system and applies overhead to production on the basis...

    Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $20,000, direct labor $12,000, and manufacturing overhead $16,000. As of January 1, Job 49 had been completed at a cost of $90,000 and was part of finished goods inventory. There was a $15,000...

  • Lott Company uses a job order cost system and applies overhead to production on the basis...

    Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $23,200, direct labor $13,920, and manufacturing overhead $18,560. As of January 1, Job 49 had been completed at a cost of $104,400 and was part of finished goods inventory. There was a $17,400...

  • Lott Company uses a job order cost system and applies overhead to production on the basis...

    Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $23,400, direct labor $14,040, and manufacturing overhead $18,720. As of January 1, Job 49 had been completed at a cost of $105,300 and was part of finished goods inventory. There was a $17,550...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT