Here, we have to eliminate cztegory with least value and high cost.
Feature category |
Value index per category |
Cost per category |
Cumilative cost('000) |
Service pages, insurance,financing | 10*20=200 | 10*5=50 | 50 |
Credit card checkout | 1*200=200 | 1*12=12 | 62 |
Cart | 1*150=150 | 1*10=10 | 82 |
Product pages | 100*10=300 | 100*3=30 | 112 |
Web architecture/design | 10*50=500 | 10*5=50 | 162 |
Summary product description | 500 | 100 | 260 |
Competitive product comparison pages | 150 | 120 | 382 |
Website architecture | 1000 | 25 | 407 |
Product zoom | 100 | 40 | 447 |
Detailed product discription | 100-1=99 | 200-2=198 | 647-2 |
Website search engine | 60 | 8 | 655-2 |
Menubar | 60 | 3 | 658-2 |
Toolbar A | 50 | 2 | 700-2 |
Toolbar B | 30 | 8 | 708-2=706. |
Since the budget is 707k and the total cumilative cost of the project is 708k we have to eliminate category to the cost of 1k, [ ie, 708-707=1]
Here Detailed product description has least value of all items, so we eliminate / decrease the cost of detailed product description upto 1k.
Value =1 per unit
cost= 2k
So we can eliminate 1 unit of Detailed product description to reduce 2k cost to arrive within our budget.
The scenario is this. You have a budget for this web page project of $707k. The...
Suppose I am asked to write a 50-page document. I have looked at the requirements and determine that I can write five pages per day for 10 days. I explain to the customer that I earn $10 per hour, and we agree that I will work 10 hours per day. However, I am paid for the number of hours I work and I report the number of pages I write each day, the hours worked, and the cost. Day #1-->...
needs to be in excel and need formulas shown
WACC & Capital Budget Analysis Based on the inputs below prepare a capital budget analysis for this Base Case using the Net Present Value, Internal Rate of Return, Profitability Index and Payback in years methods, determining whether the project is feasible. Please show your spreadsheet calculations and your final determinations of "go" or "no go" on the project. AND explain your answer. Use your Investment Return Analysis as an example for...
CVP Modeling project The purpose of this project is to give you experience creating a multiproduct profitability analysis that can be used to determine the effects of changing business conditions on the client's financial position. Your goal will be to use Excel in such a way that any changes to the assumptions will correctly ripple through the entire profitability analysis. If executed properly, the client should be able to use this spreadsheet over and over, using different "what if" assumptions....
(Related to Checkpoint 12.1) (Comprehensive problem-calculating project cash flows, NPV, PI, and IRR) Traid Winds Corporation, a firm in the 30 percent marginal tax bracket with a required rate of return or discount rate of 10 percent, is considering a new project. This project involves the introduction of a new product. The project is expected to last 5 years and then, because this is somewhat of a fad product, it will be terminated. Given the following information, determine the free...
(Related to Checkpoint 12.1) (Comprehensive problem-calculating project cash flows, NPV, PI, and IRR) Traid Winds Corporation, a firm in the 30 percent marginal tax bracket with a required rate of return or discount rate of 10 percent, is considering a new project. This project involves the introduction of a new product. The project is expected to last 5 years and then, because this is somewhat of a fad product, it will be terminated. Given the following information, determine the free...
Below is the time-phased baseline budget for a project and a table showing the progress as of End of Period 7. Baseline PV Task Total PV Time Period 0 1 2 3 4 5 6 7 8 9 10 11 A 30 15 15 B 40 20 20 C 80 10 10 10 10 20 20 D 30 5 5 5 5 10 E 20 5 5 5 5 F 40 10 20 5 5 G 10 5 5 PV...
1. Prepare the sales budget for the
year.
2. Prepare the production budget for the year.
3. Prepare the direct materials budget for the year.
4. Prepare the direct labor budget for the year. (Round
Direct labor time per unit answers to 1 decimal place, e.g.
52.5.)
5. Prepare the budegeted multiple-step income statement for the
year. (Note: income taxes are not allocated to the
products).
Ayayai Inc. is preparing its annual budgets for the year ending December 31, 2017....
(Comprehensive problem) The Shome Corporation, a firm in the 32 percent marginal tax bracket with a required rate of return or cost of capital of 16 percent, is considering a new project. The project involves the introduction of a new product. This project is expected to last 5 years and then, because this is somewhat of a fad product, be terminated. Given the following information, determine the free cash flows associated with the project, the project's net present value, the...
CVP Modeling project Directions The purpose of this project is to give you experience creating a multiproduct profitability analysis that can be used to determine the effects of changing business conditions on the client's financial position. Your goal will be to use Excel in such a way that any changes to the assumptions will correctly ripple through the entire profitability analysis. You have been hired by Jake to build a CVP model that will help him understand the impact of...
(Related to Checkpoint 12.1) (Comprehensive problem-calculating project cash flows, NPV, PI, and IRR) Traid Winds Corporation, a firm in the 31 percent marginal tax bracket with a required rate of return or discount rate of 12 percent, is considering a new project. This project involves the introduction of a new product. The project is expected to last 5 years and then, because this is somewhat of a fad product, it will be terminated. Given the following information, , determine the...