1 Answer
5.8 Per Direct labour hours
Particulars | Amount |
Estimated fixed manufacturing overhead | 15600 |
estimated variable manufacturing overhead | |
1.80*3900 | 7020 |
Estimated Total manufacturing overhead | 22620 |
The pre determinde overgead rate | |
Estimated Total manufacturing overhead | 22620 |
Estimated total direct labour hours | 3900 |
Predeterminde overhead rate | |
22620/3900 | 5.8 Per Direct labour hours |
me end of March. The company uses a plantwide predetermined overhead rate based on direct labor-hours....
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. It started only two jobs during March—Job P and Job Q. Job P was completed and sold by the end of March and Job Q was incomplete at the end of March. The company uses a plantwide predetermined overhead rate based on direct labor-hours. The following additional information is available for the company as a whole and for Jobs P and Q (all data...
sweeten company naa no jobs in progress at the beginning of March and no beginning inventones. It started only two jobs during March-Job P and Job Q. Job P was completed and sold by the end of March and Job Q was incomplete at the end of March. The company uses a plantwide predetermined overhead rate based on direct labor-hours. The following additional information is available for the company as a whole and for Jobs P and Q (all data...
Required information [The following information applies to the questions displayed below.) Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. It started only two jobs during March-Job P and Job Q. Job P was completed and sold by the end of March and Job Q was incomplete at the end of March. The company uses a plantwide predetermined overhead rate based on direct labor-hours. The following additional information is available for the company...
Harris Fabrics computes its plantwide predetermined overhead rate annually on the basis of direct labor-hours. At the beginning of the year, it estimated that 30,000 direct labor-hours would be required for the period's estimated level of production. The company also estimated $590,000 of fixed manufacturing overhead cost for the coming period and variable manufacturing overhead of $3.00 per direct labor-hour. Harris's actual manufacturing overhead cost for the year was $743,183 and its actual total direct labor was 30,500 hours. Required:...
Harris Fabrics computes its plantwide predetermined overhead rate annually on the basis of direct labor-hours. At the beginning of the year, it estimated that 36,000 direct labor-hours would be required for the period's estimated level of production. The company also estimated $553,000 of fixed manufacturing overhead cost for the coming period and variable manufacturing overhead of $4.00 per direct labor-hour. Harris's actual manufacturing overhead cost for the year was $763,256 and its actual total direct labor was 36,500 hours. Compute...
Harris Fabrics computes its plantwide predetermined overhead rate annually on the basis of direct labor-hours. At the beginning of the year, it estimated that 34,000 direct labor-hours would be required for the period’s estimated level of production. The company also estimated $505,000 of fixed manufacturing overhead cost for the coming period and variable manufacturing overhead of $2.00 per direct labor-hour. Harris’s actual manufacturing overhead cost for the year was $638,351 and its actual total direct labor was 34,500 hours. Exercise...
Harris Fabrics computes its plantwide predetermined overhead rate annually on the basis of direct labor-hours. At the beginning of the year, it estimated that 20,000 direct labor-hours would be required for the period's estimated level of production. The company also estimated $94,000 of fixed manufacturing overhead cost for the coming period and variable manufacturing overhead of $2.00 per direct labor-hour. Harris's actual manufacturing overhead cost for the year was $123,900 and its actual total direct labor was 21,000 hours. Required:...
Hahn Company uses a job-order costing system. Its plantwide predetermined overhead rate uses direct labor-hours as the allocation base. The company pays its direct laborers $15 per hour. During the year, the company started and completed only two jobs—Job Alpha, which used 54,500 direct labor-hours, and Job Omega. The job cost sheets for the these two jobs are shown below: Job Alpha Direct materials Direct labor Manufacturing overhead applied Total job cost 2 ? $1,533,500 Job Omega Direct materials Direct...
Harris Fabrics computes its plantwide predetermined overhead rate annually on the basis of direct labor-hours. At the beginning of the year, it estimated that 30,000 direct labor-hours would be required for the period's estimated level of production. The company also estimated $547,000 of fixed manufacturing overhead cost for the coming period and variable manufacturing overhead of $4.00 per direct labor-hour. Harris's actual manufacturing overhead cost for the year was $725,392 and its actual total direct labor was 30,500 hours. Required:...
Harris Fabrics computes its plantwide predetermined overhead rate annually on the basis of direct labor-hours. At the beginning of the year, it estimated that 33,000 direct labor-hours would be required for the period’s estimated level of production. The company also estimated $572,000 of fixed manufacturing overhead cost for the coming period and variable manufacturing overhead of $2.00 per direct labor-hour. Harris’s actual manufacturing overhead cost for the year was $702,942 and its actual total direct labor was 33,500 hours. Required:...