Let the IRR be x.
Now , Present Value of Cash Outflows=Present Value of Cash Inflows
1500 =550/(1.0x) +630/ (1.0x)^2 +620/(1.0x)^3+ 400 /(1.0x)^4+200/(1.0x)^5
Or x= 20.949%
Hence the IRR is 20.95%
--------
Answer: Accepted.
Note: Since the IRR is greater than the cost of capital, the project must be accepted.
Compute the IRR static for Project E. The appropriate cost of capital is 9 percent. (Do...
Compute the IRR static for Project E. The appropriate cost of capital is 9 percent. (Do not round intermediate calculations. Round your final answer to 2 decimal places.) Project E Time: 0 1 2 3 4 5 Cash flow –$1,800 $670 $720 $680 $460 $260 IRR % Should the project be accepted or rejected? Rejected Accepted
Compute the IRR static for Project E. The appropriate cost of capital is 9 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project E Time: 0 -$2,900 1 $910 2 $900 3 $800 4 $580 5 $380 Cash flow IRR % Should the project be accepted or rejected? O rejected O accepted
Compute the IRR static for Project E. The appropriate cost of capital is 8 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project E Time: -$1,000 $350 $480 $520 $300 $100 Cash flow: IRR : :% Should the project be accepted or rejected? O accepted O rejected
Compute the IRR static for Project E. The appropriate cost of capital is 8 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project E Time: Cash flow 0 $1,300 1 $470 2 $570 3 $580 4 $360 5 $160 IRR IRR C % Should the project be accepted or rejected? O accepted O rejected
Compute the IRR static for Project E. The appropriate cost of capital is 7 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project E Time: 0 1 2 3 4 5 Cash flow –$1,100 $390 $510 $540 $320 $120 IRR= _____% Should the project be accepted or rejected?
Compute the IRR for Project F. The appropriate cost of capital is 11 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project F Time: Cash flow:-$10,100 $3,850 $4,680 $2,020 $2,650 IRR % Should the project be accepted or rejected? rejected O accepted Compute the IRR static for Project E. The appropriate cost of capital is 7 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project E...
Compute the IRR for Project F. The appropriate cost of capital is 13 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project F Time: 2 4 Cash flow: -$9,900 $3,7s0 $4,580 $1,920 $2,550 IRR Should the project be accepted or rejected? ассepted Orejected Compute the IRR static for Project E. The appropriate cost of capital is 7 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project...
Problem 13-9 IRR (LG13-4) Compute the IRR static for Project E. The appropriate cost of capital is 9 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project E Time : Cash flow -$2,600 $790 $740 $520 $320 IRR % Should the project be accepted or rejected? O rejected O accepted 5 of 10 Next >
Compute the IRR statistic for Project E. The appropriate cost of capital is 9 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project E Time: 0 1 2 3 4 5 Cash flow −$1,800 $670 $720 $680 $460 $260 IRR? Should the project be accepted or rejected?
Week 4 Homework Assignment i Saved Compute the IRR statistic for Project E. The appropriate cost of capital is 9 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) 2.16 points Project E Time: Cash flow 0 1 -$1,500 $550 2 $630 3 $620 4 $400 5 $200 Skipped IRR % eBook Print References Should the project be accepted or rejected? O accepted O rejected Week 5 Homework Assignment i Saved Suppose a firm...