1
Plantwide overhead rate = (Total Estimated overhead
costs / Direct labor hours)
=> ($2660000 / 125000 hours)
=> $21.28
Direct labor hours = 125000 hours
Overhead = (Handling materials + Inspecting product + Processing
purchase order + Paying supplies + Insuring factory + Designing
packaging)
=> ($705000 + $980000 + $185000 + $255000 + $380000 +
$155000)
=> $2660000
2
Overhead cost allocation
Model | Direct labor hours | Plantwide overhead rate | Overhead allocated |
Deluxe | 2500 | $21.28 | $53200 ($21.28 X 2500 hours) |
Basic | 6000 | $21.28 | $127680 ($21.28 X 6000 hours) |
(If there are any questions, kindly let me know in comments. If the solution is to your satisfaction, a thumbs up would be appreciated. Thank You)
Activity Handling materials Inspecting product Processing purchase orders Paying suppliers Insuring the factory Designing packaging Expected...
Xie Company identified the following activities, costs, and activity drivers for this year. The company manufactures two types of go-karts: Deluxe and Basic Retivity Handling materiale Inspecting product Processing purchase orders Paying suppliers Insuring the factory Designing packaging Expected Costs 5625,000 900,000 105,000 175,000 300.000 75,000 Expected Activity 100,000 parts 1,500 batches 700 orders 500 invoices 40.000 #quare feet 2 models Required: 1. Compute a single plantwide overhead rate for the year, assuming that the company assigns overhead based on...
Xie Company identified the following activities, costs, and activity drivers for this year. The company manufactures two types of go- karts: Deluxe and Basic. Activity Handling materials Inspecting product Processing purchase orders Paying suppliers Insuring the factory Designing packaging Expected Costs $635,000 910,000 115,000 185,000 310,000 85,000 Expected Activity 100,000 parts 1,500 batches 700 orders 500 invoices 40,000 square feet 2 models Required: 1. Compute a single plantwide overhead rate for the year, assuming that the company assigns overhead based...
Xie Company identified the following activities, costs, and activity drivers for this year. The company manufactures two types of go- karts: Deluxe and Basic Activity Handling materials Inspecting product Processing purchase orders Paying suppliers Insuring the factory Designing packaging Expected Costs $ 670,000 945,000 150,000 220,000 345,000 120,000 Expected Activity 100,000 parts 1,500 batches 700 orders 500 invoices 40,000 square feet 2 models Required: 1. Compute a single plantwide overhead rate for the year, assuming that the company assigns overhead...
Xie Company identified the following activities, costs, and activity drivers for this year. The company manufactures two types of go- karts: Deluxe and Basic. Activity Handling materials Inspecting product Processing purchase orders Paying suppliers Insuring the factory Designing packaging Expected Costs $ 650,000 925,000 130,000 200,000 325,000 100,000 Expected Activity 100,000 parts 1,500 batches 700 orders 500 invoices 40,000 square feet 2 models Required: 1. Compute a single plantwide overhead rate for the year, assuming that the company assigns overhead...
Xie Company identified the following activities, costs, and activity drivers for this year. The company manufactures two types of go- karts: Deluxe and Basic Activity Handling materials Inspecting product Processing purchase orders Paying suppliers Insuring the factory Designing packaging Expected Costs $630, cee 905,000 110,000 180,eee 385,000 89, eee Expected Activity 189,800 parts 1,500 batches 700 orders Se invoices 40,000 square feet 2 models Required: 1. Compute a single plantwide overhead rate for the year, assuming that the company assigns...
Xie Company identified the following activities, costs, and activity drivers for 2017. The company manufactures two types of go-karts: Deluxe and Basic. Expected Activity 100,000 parts 1,500 batches 700 orders 500 invoices 40,000 square feet 2 models Expected Costs $625,000 900,000 Activity Handling materials Inspecting product Processing purchase orders Paying Buppliers Insuring the factory Designing packaging 105,000 175,000 300,000 oped 75,000 Book Required: 1. Compute a single plantwide overhead rate, assuming that the company assigns overhead based on 125,000 budgeted...
Exercise 17-3 Computing plantwide overhead rates LO P1 Xie Company identified the following activities, costs, and activity drivers for this year. The company manufactures two types of go-karts: Deluxe and Basic Activity Handling materials Inspecting product Processing purchase orders Paying suppliers Insuring the factory Designing packaging Expected Costs $ 625,000 900,000 105,000 175,000 300,000 75,000 Expected Activity 100,000 parts 1,500 batches 700 orders 500 invoices 40,000 square feet 2 models Required: 1. Compute a single plantwide overhead rate for the...
16 Xie Company identified the following activities, costs, and activity drivers for this year. The company manufactures two types of go karts Deluxe and Basic Expected Activity Activity Handling materials Inspecting product Processing purchase orders Paying suppliers Insuring the factory Designing packaging Expected Costs $625,000 900,000 105,000 175,000 388,888 75,000 100,000 parts 1,500 batches 789 orders 500 invoices 40,800 square feet 2 models Required: 1. Compute a single plantwide overhead rate for the year, assuming that the company assigns overhead...
Xie Company identified the following activities, costs, and activity drivers for 2017. The company manufactures two types of go-karts: Deluxe and Basic Activity Handling materials Inspecting product Processing purchase orders Paying suppliers Insuring the factory Designing packaging Expected Costs $625,000 900,000 105,000 175,000 300,000 75,000 Expected Activity 100,000 parts 1,500 batches 700 orders 500 invoices 40,000 square feet 2 models References Required: 1. Compute a single plantwide overhead rate, assuming that the company assigns overhead based on 125,000 budgeted direct...
Xie Company identified the following activities, costs, and activity drivers for this year. The company manufactures two types of go- karts: Deluxe and Basic. Activity Handling materials Inspecting product Processing purchase orders Paying suppliers Insuring the factory Designing packaging Expected Costs $720,000 995,000 200,000 270,000 395,000 170,000 Expected Activity 100,000 parts 1,500 batches 700 orders 500 invoices 40,000 square feet 2 models Required: 1. Compute a single plantwide overhead rate for the year, assuming that the company assigns overhead based...