Given k = 2x10-6 ft/s, yw = 62.4 lbf/ft?, Ysat = 112 lbf/ft?, and the flow...
Given k = 2x10-6 ft/s, yw = 62.4 lbf/ft?, Ysat = 112 lbf/ft?, and the flow net below: Streamline Equipotential line --- 1714 8x12 ft + 4 ft IL TV5 1 VILLI 16A 00 30 ft 21 til 15 10 ft 5 13 12 11 10 9 8 7 Wild 100 ft- Compute: 1) The total and pressure head and the pore pressure at points A and B. 2) Hydraulic gradient at point C and the factor of safety against boiling. 3) The total flow rate per unit length of the dam. 4) The profile of uplift pressure under the dam.