Question

Masulis Inc. is considering a project that has the following cash flow and WACC data. What is the projects discounted paybac

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Ans a) 2.14 years

Year Project Cash Flows (i) DF@ 10% (ii) PV of Project A ( (i) * (ii) ) Cumulative Cash Flow
0 -925 1                                (925.00)                   (925.00)
1 525 0.909                                  477.27                   (447.73)
2 485 0.826                                  400.83                     (46.90)
3 445 0.751                                  334.34                     287.43
4 405 0.683                                  276.62                     564.05
NPV                                  564.05
Discounted Payback Period = 2 years + 46.90 / 334.34
2.14 years
Add a comment
Know the answer?
Add Answer to:
Masulis Inc. is considering a project that has the following cash flow and WACC data. What...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT