Solution
Mercer Asbestos Removal Company
First-stage allocation of costs to the activity cost pools:
Mercer Asbestos Removal Company |
|||||
First-stage allocation of costs to the activity cost pools: |
|||||
Removing Asbestos |
Estimating and Job Setup |
Working on non-routine jobs |
Other |
Total |
|
Wages and Salaries |
$210,000 |
$63,000 |
$84,000 |
$63,000 |
$420,000 |
Disposal Fees |
$488,400 |
$0 |
$325,600 |
$0 |
$814,000 |
Equipment Depreciation |
$38,400 |
$4,800 |
$19,200 |
$33,600 |
$96,000 |
On-site Supplies |
$37,200 |
$18,600 |
$6,200 |
$0 |
$62,000 |
Office Expenses |
$48,000 |
$112,000 |
$64,000 |
$96,000 |
$320,000 |
Licensing and Insurance |
$130,000 |
$0 |
$312,000 |
$78,000 |
$520,000 |
Total Cost |
$952,000 |
$198,400 |
$811,000 |
$270,600 |
$2,232,000 |
Note: the allocation of overhead costs is done based on percentage consumption across activities.
Computation of activity rates for the activity cost pool:
Activity Cost |
Activity Cost Pool |
Activity rate |
|
Removing Asbestos |
$952,000 |
800,000 square feet |
$1.19 per square feet |
Estimating and job setup |
$198,400 |
400 jobs |
$496 per job |
Working on non-routine jobs |
$811,000 |
100 non-routine jobs |
$8,110 non-routine jobs |
Routine 1,000 sq. ft job |
Routine 2,000 squar feet |
Nonroutine 2 |
|
Total cost of job |
$1,686 |
$1,438 |
$5,493 |
Computations:
Total cost of routine 1,000 sq. ft. job = total cost/number thousand square feet
Total cost = cost of removing asbestos + cost of estimating and job setup
= ($1.19) x 1,000 + $496 = $1,686
Average cost = total cost/number of thousand square feet
= $1,686/1 = $1,686
Total cost of routine 2,000 square feet asbestos removal job:
(1.19 x 2,000) + 496 = $2,876
Average cost = $2,876/2 = $1,438
Total cost of non-routine 2,000 square feet asbestos removal job:
Total cost = cost of removing asbestos + cost of estimating and job setup + cost of working on non-routine jobs
= ($1.19 x 2,000) + 496 + 8,110 = $10,986
Average cost = 10,986/2 = $5,493
3. Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There...
Mercer Asbestos Removal Company removes potentially toxic
asbestos insulation and related products from buildings. There has
been a long-simmering dispute between the company’s estimator and
the work supervisors. The on-site supervisors claim that the
estimators do not adequately distinguish between routine work, such
as removal of asbestos insulation around heating pipes in older
homes, and nonroutine work, such as removing asbestos-contaminated
ceiling plaster in industrial buildings. The on-site supervisors
believe that nonroutine work is far more expensive than routine
work...
Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has been a long-simmering dispute between the company’s estimator and the work supervisors. The on-site supervisors claim that the estimators do not adequately distinguish between routine work, such as removal of asbestos insulation around heating pipes in older homes, and nonroutine work, such as removing asbestos-contaminated ceiling plaster in industrial buildings. The on-site supervisors believe that nonroutine work is far more expensive than routine work...
Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has been a long-simmering dispute between the company’s estimator and the work supervisors. The on-site supervisors claim that the estimators do not adequately distinguish between routine work, such as removal of asbestos insulation around heating pipes in older homes, and nonroutine work, such as removing asbestos-contaminated ceiling plaster in industrial buildings. The on-site supervisors believe that nonroutine work is far more expensive than routine work...
Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has been a long-simmering dispute between the company's estimator and the work supervisors. The on-site supervisors claim that the estimators do not adequately distinguish between routine work, such as removal of asbestos insulation around heating pipes in older homes, and nonroutine work, such as removing asbestos-contaminated ceiling plaster in industrial buildings. The on-site supervisors believe that nonroutine work is far more expensive than routine work...
Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has been a long-simmering dispute between the company's estimator and the work supervisors. The on-site supervisors claim that the estimators do not adequately distinguish between routine work, such as removal of asbestos insulation around heating pipes in older homes, and nonroutine work, such as removing asbestos-contaminated ceiling plaster in industrial buildings. The on-site supervisors believe that nonroutine work is far more expensive than routine work...
Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has been a long-simmering dispute between the company's estimator and the work supervisors. The on-site supervisors claim that the estimators do not adequately distinguish between routine work, such as removal of asbestos insulation around heating pipes in older homes, and nonroutine work, such as removing asbestos-contaminated ceiling plaster in industrial buildings. The on-site supervisors believe that nonroutine work is far more expensive than routine work...
Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has been a long-simmering dispute between the company's estimator and the work supervisors. The on-site supervisors claim that the estimators do not adequately distinguish between routine work such as removal of asbestos insulation around heating pipes in older homes and nonroutine work such as removing asbestos contaminated ceiling plaster in industrial buildings. The on-site supervisors believe that nonroutine work is far more expensive than routine...
Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has been a long-simmering dispute between the company's estimator and the work supervisors. The on-site supervisors claim that the estimators do not adequately distinguish between routine work, such as removal of asbestos insulation around heating pipes in older homes, and nonroutine work, such as removing asbestos-contaminated ceiling plaster in industrial buildings. The on-site supervisors believe that nonroutine work is far more expensive than routine work...
Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has been a long-simmering dispute between the company's estimator and the work supervisors. The on-site supervisors claim that the estimators do not adequately distinguish between routine work, such as removal of asbestos insulation around heating pipes in older homes, and nonroutine work, such as removing asbestos contaminated ceiling plaster in industrial buildings. The on-site supervisors believe that nonroutine work is far more expensive than routine...
1.34 points Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has been a long-simmering dispute between the company's estimator and the work supervisors. The on-site supervisors claim that the estimators do not adequately distinguish between routine work, such as removal of asbestos insulation around heating pipes in older homes, and nonroutine work, such as removing asbestos-contaminated ceiling plaster in industrial buildings. The on-site supervisors believe that nonroutine work is far more expensive than...