Question

a company has 10 machines working 16 hours a day in a standard 5 day work week. They work 50 weeks every year. An analysis sh
0 0
Add a comment Improve this question Transcribed image text
Answer #1

d. 40000

Let the available hours to work = X

Then,

X * (90/100) = 36000

X = 36000/0.9

= 40000

Add a comment
Know the answer?
Add Answer to:
a company has 10 machines working 16 hours a day in a standard 5 day work...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • a. A work center at the Mechanical Lyold Company has 4 machines and each machine is...

    a. A work center at the Mechanical Lyold Company has 4 machines and each machine is operated 8.5 hours a day, 6 days a week. Last week, the work center operated for a total 158 hours and produced 140 hours of work. Calculate the i. The efficiency of the work center ii. The utilization of the work center iii. what is the rated capacity of the workcenter

  • LLC employs only salaried exempt individuals, who work a standard eight hours per day. One of...

    LLC employs only salaried exempt individuals, who work a standard eight hours per day. One of its employees worked more than eight hours on Monday, Wednesday, and Thursday, but did not work more than a total of 40 works during that week. What does FLSA say about the additional hours the employee worked on those single days? The employee will not be paid over time for the extra hours worked on Monday, Wednesday, and Thursday The employee must be paid...

  • 3. Show on work-leisure diagram a low wage worker working 8 hours per day. Assume the...

    3. Show on work-leisure diagram a low wage worker working 8 hours per day. Assume the government wants to help this worker by giving them a $300 grant to help with their weekly expenses. Show the labor supply impact this would have on the workers. Instead, show the impact on this worker if the government added an extra dollar amount for every additional hour the person worked.

  • Create an Assumptions page, Sales budget, cash collections schedule, production budget, direct materials budget, direct labor...

    Create an Assumptions page, Sales budget, cash collections schedule, production budget, direct materials budget, direct labor budget, ending finished goods schedule per unit, sales and administrative budget, Cash budget, income statement and balance sheet for the quarter ended. 1 2 3 Instructions: Prepare all schedules on the following tabs for the below problem If you do this correctly, your balance sheet will balance. You must create an input tab for this project, and the link all numbers on the other...

  • cost estimation PROB #2: LearningCurve An activity to produce 100 units was planned for 40 working days of 8 hours each, for one 5 person crew at KD 10 per hour per person. Because of owner requir...

    cost estimation PROB #2: LearningCurve An activity to produce 100 units was planned for 40 working days of 8 hours each, for one 5 person crew at KD 10 per hour per person. Because of owner required acceleration, the contractor worked with 2 crews of 5 people each for 10 hour per day. The contractor had to pay KD 15 per hour per person for the overtime hours above 8 hr day. For this work, LP 85% ( for learning...

  • 16. (10 points, show your work): Under Armour, Inc. is considering two potential investments. The probability...

    16. (10 points, show your work): Under Armour, Inc. is considering two potential investments. The probability distributions of annual end-of-year cash flows for the respective projects are: Project A Project B Probability Outcome Probability Outcome .25 $20,000 S30,000 $40,000 .25 .50 .25 $24,000 $30,000 $36,000 .50 25 Both projects will require an initial outlay of $100,000 and will have an estimated life of 6 years. Project A is considered a riskier investment and will have a risk- adjusted required rate...

  • 3:01 AM Thu Jan 16 85% 5 TODO + BO Assignment 2 Name: Problem 1 A...

    3:01 AM Thu Jan 16 85% 5 TODO + BO Assignment 2 Name: Problem 1 A production company A, made JITD strategic alliance with a distribution company B. The content of alliance is, Company A executes work for company B's inventory management and all the inventory cost caused from B is responsible on A. The decision for inventory replenishment is made on every Saturday, An order quantity is arrived every Sunday night after the delivery-process from A to B. The...

  • Jackson Company applies overhead to products using direct labor hours as the activity level. During 2019,...

    Jackson Company applies overhead to products using direct labor hours as the activity level. During 2019, Jackson Company had the following estimated costs: Direct materials .................... $258,000 Direct labor ........................ 255,000 Advertising ......................... 35,000 Rent on factory building ............ 36,000 Depreciation .................... ... 60,000 Indirect materials .................. 32,000 Sales commissions ................... 50,000 Production supervisor's salary ...... 40,000 Insurance on factory equipment ...... 18,000 CEO's salary ........................ 95,000 The following additional information is available: 1. 30% of the depreciation relates to...

  • A manufacturing company's weekly payroll is $80,000 for a 5-day work week beginning each Monday and...

    A manufacturing company's weekly payroll is $80,000 for a 5-day work week beginning each Monday and ending each Friday. The last time salaries and wages were recorded was Friday, December 26. What adjustment is needed on December 31, the last day of the company's fiscal period? a. No adjustment is necessary since the next payday will not occur until the following year. Ob. Decrease cash by $48,000. c. Increase wages expense by $48,000. Od. Decrease wages payable by $48,000. Klinc...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT