Question

1. Chapter 10: Revenue Expenditures vs Capital Expenditures gali A) DETERMINING COST OF PLANT ASSETS 1- Land Ex Assume that H

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer)

Calculation of cost of Land

Particulars

Amount (In $)

Cash cost of property

                                       100,000

Net cost of razing of old warehouse

                                            6,000

Attorney's fees

                                            1,000

Real estate broker's commission

                                            8,000

Total cost

                                       115,000

Therefore total cost of property is $ 115,000

Note: The cost of Plant assets includes all expenses (i.e. purchase price and other related expenses) that are incurred to make the asset ready for intended use. It will thus include all site preparation expenses (razing expenses of old warehouse in this example), all legal expenses and sales commission paid to acquire the property.

Add a comment
Know the answer?
Add Answer to:
1. Chapter 10: Revenue Expenditures vs Capital Expenditures gali A) DETERMINING COST OF PLANT ASSETS 1-...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Exercise 1: On March 1, 2008, Penner Company acquired real estate on which it planned to...

    Exercise 1: On March 1, 2008, Penner Company acquired real estate on which it planned to construct a small office building. The company paid $80,000 in cash. An old warehouse on the property was razed at a cost of $8,600; the salvaged materials were sold for $1.700. Additional expenditures before construction began included $1,100 attorney's fee for work concerning the land purchase, $5,000 real estate broker's fee, $7,800 architect's fee. Instruction: Compute and journalize the acquisition cost for the land....

  • On March 1, 2017, Blossom Company acquired real estate, on which it planned to construct a...

    On March 1, 2017, Blossom Company acquired real estate, on which it planned to construct a small office building, by paying $75,000 in cash. An old warehouse on the property was demolished at a cost of $7,200; the salvaged materials were sold for $1,500. Additional expenditures before construction began included $1,000 attorney's fee for work concerning the land purchase, $4,000 real estate broker's fee, $8,500 architect's fee, and $13,000 to put in driveways and a parking lot. (a) Determine the...

  • Exercise 9-03 a * Your answer is incorrect. Try again. On March 1, 2022, Sunland Company...

    Exercise 9-03 a * Your answer is incorrect. Try again. On March 1, 2022, Sunland Company acquired real estate, on which it planned to construct a small office building, by paying $84,000 in cash. An old warehouse on the property was demolished at a cost of $9,000; the salvaged materials were sold for $1,860. Additional expenditures before construction began included $1,360 attorney's fee for work concerning the land purchase, $4,900 real estate broker's fee, $8,860 architect's fee, and $14,800 to...

  • On March 1, 2019, Cullumber Company acquired real estate on which it planned to construct a...

    On March 1, 2019, Cullumber Company acquired real estate on which it planned to construct a small office building. The company paid $75,000 in cash. An old warehouse on the property was razed at a cost of $8,000; the salvaged materials were sold for $1,500. Additional expenditures before construction began included $1,000 attorney’s fee for work concerning the land purchase, $4,000 real estate broker’s fee, $7,000 architect’s fee, and $13,000 to put in driveways and a parking lot. (a) Determine...

  • Exercise 9-03 a x Your answer is incorrect. Try again. On March 1, 2022, Sunland Company...

    Exercise 9-03 a x Your answer is incorrect. Try again. On March 1, 2022, Sunland Company acquired real estate, on which it planned to construct a small office building, by paying $84,000 in cash. An old warehouse on the property was demolished at a cost of $9,000; the salvaged materials were sold for $1,860. Additional expenditures before construction began included $1,360 attorney's fee for work concerning the land purchase, $4,900 real estate broker's fee, $8,860 architect's fee, and $14,800 to...

  • Handout 8: Accounting for Plant assets Exercise 1: On March 1, 2008, Penner Company acquired real...

    Handout 8: Accounting for Plant assets Exercise 1: On March 1, 2008, Penner Company acquired real estate on which it planned to construct a small office building. The company paid $80,000 in cash. An old warehouse on the property was razed at a cost of $8,600; the salvaged materials were sold for $1,700. Additional expenditures before construction began included $1,100 attorney's fee for work concerning the land purchase, $5,000 real estate broker's fee, $7,800 architect's fee. Land price 8,600 Instruction:...

  • F10.1 (LO 1) (Acquisition Costs of Realty) The following expenditures and receipts are related to land,...

    F10.1 (LO 1) (Acquisition Costs of Realty) The following expenditures and receipts are related to land, land improvements, and buildings acquired for use in a business enterprise. The receipts are enclosed in parentheses. a. Money borrowed to pay building contractor (signed a note) $(275,000) b. Payment for construction from note proceeds 275,000 c. Cost of land fill and clearing 8,000 d. Delinquent real estate taxes on property assumed by purchaser 7,000 e. Premium on 6-month insurance policy during construction 6,000...

  • s101(LO 1) (Acquisition Costs of Realty) The following expenditures and receipts are related o land, land...

    s101(LO 1) (Acquisition Costs of Realty) The following expenditures and receipts are related o land, land improvements, and buildings acquired for use in a business enterprise. The receipts are enclosed in parentheses. . Money borrowed to pay building contractor (signed a note) h Payment for construction from note proceeds $(275,000) 275,000 c. Cost of land fill and clearing d. Delinquent real estate taxes on property assumed by purchaser e. Premium on 6-month insurance policy during construction fRefund of 1-month insurance...

  • Exercises 533 EXERCISES provence 0-1 (201) (Acquis buildings acquired (a) Money borrowed ( Payment for Cost...

    Exercises 533 EXERCISES provence 0-1 (201) (Acquis buildings acquired (a) Money borrowed ( Payment for Cost of land fill and clearing Acquisition C0515 Realty! The following expenditures and receipts are related to land, land red for use in a business enterprise. The receipts are enclosed in parentheses. orrowed to pay building contractor (signed a note) S(275,000) ent for construction from note proceeds 275,000 8,000 ent real estate taxes on property assumed by purchaser 7,000 um on 6-month insurance policy during...

  • Exercise 10-1 The expenditures and receipts below are related to land, land improvements, and buildings acquired...

    Exercise 10-1 The expenditures and receipts below are related to land, land improvements, and buildings acquired for use in a business enterprise. The receipts are enclosed in parentheses. (a) Money borrowed to pay building contractor (signed a note) $(290,100 ) (b) Payment for construction from note proceeds 290,100 (c) Cost of land fill and clearing 10,580 (d) Delinquent real estate taxes on property assumed by purchaser 7,410 (e) Premium on 6-month insurance policy during construction 12,240 (f) Refund of 1-month...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT