SCENARIO ANALYSIS

Huang Industries is considering a proposed project whose estimated NPV is $12 million. This estimate assumes that economic conditions will be "average." However, the CFO realizes that conditions could be better or worse, so she performed a scenario analysis and obtained these results:

Economic Scenario Probability of Outcome NPV
Recession 0.05 ($78 million)
Below average 0.20 (24 million)
Average 0.50 12 million
Above average 0.20 18 million
Boom 0.05 40 million

Calculate the project's expected NPV, standard deviation, and coefficient of variation. Round your answers to two decimal places. Enter your answers for the project's expected NPV and standard deviation in millions. For example, an answer of $13,000,000 should be entered as 13.

E(NPV) = $ million
σNPV = $ million
CV =
0 0
Add a comment Improve this question Transcribed image text
Request Professional Answer

Request Answer!

We need at least 10 more requests to produce the answer.

0 / 10 have requested this problem solution

The more requests, the faster the answer.

Request! (Login Required)


All students who have requested the answer will be notified once they are available.
Know the answer?
Add Answer to:
SCENARIO ANALYSIS Huang Industries is considering a proposed project whose estimated NPV is $12 million. This...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
  • Huang Industries is considering a proposed project whose estimated NPV is $12 million. This estimate assumes...

    Huang Industries is considering a proposed project whose estimated NPV is $12 million. This estimate assumes that economic conditions will be "average." However, the CFO realizes that conditions could be better or worse, so she performed a scenario analysis and obtained these results: Economic Scenario Probability of Outcome NPV Recession 0.05 ($66 million) Below average 0.20 (16 million) Average 0.50 12 million Above average 0.20 18 million Boom 0.05 34 million Calculate the project's expected NPV, standard deviation, and coefficient...

  • Huang Industries is considering a proposed project whose estimated NPV is $12 million. This estimate assumes that economic conditions will be "average." However, the CFO realizes that conditio...

    Huang Industries is considering a proposed project whose estimated NPV is $12 million. This estimate assumes that economic conditions will be "average." However, the CFO realizes that conditions could be better or worse, so she performed a scenario analysis and obtained these results: Economic Scenario Probability of Outcome NPV Recession 0.05 ($42 million) Below average 0.20 (26 million) Average 0.50 12 million Above average 0.20 24 million Boom 0.05 34 million Calculate the project's expected NPV, standard deviation, and coefficient...

  • Huang Industries is considering a proposed project whose estimated NPV is $12 million. This estimate assumes...

    Huang Industries is considering a proposed project whose estimated NPV is $12 million. This estimate assumes that economic conditions will be "average." However the CFO realizes that conditions could be better or worse, so she performed a scenario analysis and obtained these results: Economic Scenario Probability of Outcome NPV 0.05 0.20 0.50 0.20 0.05 - $54 million - $18 million 12 mlion 18 milion 30 million Recession Below average Average Above average Boom Calculate the project's expected NPV, standard deviation,...

  • Click here to read the eBook: Measuring Stand-Alone Risk SCENARIO ANALYSIS Huang Industries is considering a...

    Click here to read the eBook: Measuring Stand-Alone Risk SCENARIO ANALYSIS Huang Industries is considering a proposed project whose estimated NPV is $12 million. This estimate assumes that economic conditions will be "average. However, the CFO realizes that conditions could be better or worse, so she performed a scenario analysis and obtained these results Economic Scenario Probability of Outcome NPV Recession Below average Average Above average Boom Calculate the project's expected NPV, standard deviation, and coefficient of variation. Round your...

  • Scenario Analysis Shao Industries is considering a proposed project for its capital budget. The company estimates...

    Scenario Analysis Shao Industries is considering a proposed project for its capital budget. The company estimates the project's NPV is $12 million. This estimate assumes that the economy and market conditions will be average over the next few years. The company's CFO, however, forecasts there is only a 50% chance that the economy will be average. Recognizing this uncertainty, she has also performed the following scenario analysis: Economic Scenario Probability of Outcome NPV Recession 0.05 -$90 million Below average 0.20...

  • Shao Industries is considering a proposed project for its capital budget. The company estimates the project's NPV is $12...

    Shao Industries is considering a proposed project for its capital budget. The company estimates the project's NPV is $12 million. This estimate assumes that the economy and market conditions will be average over the next few years. The company's CFO, however, forecasts there is only a 50% chance that the economy will be average. Recognizing this uncertainty, she has also performed the following scenario analysis: Economic Scenario Probability of Outcome NPV Recession 0.05 -$80 million     Below average 0.20 -24 million    ...

  • Scenario Analysis Shao Industries is considering a proposed project for its capital budget, The company estimates...

    Scenario Analysis Shao Industries is considering a proposed project for its capital budget, The company estimates the project's NPV is $12 million. This estimate assumes that the economy and market conditions will be average over the next few years. The company's CFO, however, forecasts there is only a 50% chance that the economy will be average. Recognizing this uncertainty, she has also performed the following scenario analysis: Economic Scenario Probability of Outcome NPV Recession -$84 million 0.05 0.20 Below average...

  • Scenario Analysis Shao Industries is considering a proposed project for its capital budget. The company estimates...

    Scenario Analysis Shao Industries is considering a proposed project for its capital budget. The company estimates the project's NPV is $12 million. This estimate assumes that the economy and market conditions will be average over the next few years. The company's CFO, however, forecasts there is only a 50% chance that the economy will be average. Recognizing this uncertainty, she has also performed the following scenario analysis: Economic Scenario Probability of Outcome NPV Recession 0.05 -$54 million Below average 0.20...

  • Problem 13-11 Scenario Analysis Shao Industries is considering a proposed project for its capital budget. The...

    Problem 13-11 Scenario Analysis Shao Industries is considering a proposed project for its capital budget. The company estimates the project's NPV is $12 million. This estimate assumes that the economy and market conditions will be average over the next few years. The company's CFO, however, forecasts there is only a 50% chance that the economy will be average. Recognizing this uncertainty, she has also performed the following scenario analysis: Economic Scenario Probability of Outcome NPV Recession 0.05 - $ 70...

  • Fundamentals of Financial Management (14th Edition) Chapter 12, Problem 7 Solution Not Available. Please calculate with...

    Fundamentals of Financial Management (14th Edition) Chapter 12, Problem 7 Solution Not Available. Please calculate with steps. Thanks! Scenario Analysis Huang Industries is considering a proposed project whose estimated NPV is $12 million. This estimate assumes that economic conditions will be "average". However, the CFO realizes that conditions could be better or worse, so she performed a scenario analysis and obtained these results: Economic Scenario:               Probability of Outcome:                 NPV: Recession                                          0.05                                ($70 million) Below average                                   0.20                                (25 millions) Average                                             0.50                                 12 million Above...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT