Question

here is the machine and serviceman problem.

Question 9 (10 points): Consider a job shop that consists of M machines and one serviceman. Suppose that the amount of time e

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution:-

Given that

Consider a job shop that consists of M machines and one serviceman. Suppose that the amount of time each machine runs before breaking down is exponentially distributed with mean 1/\lambda ,

Suppose that the amount of time that it takes for the serviceman to fix a machine is exponentially distributed with mean 1/ . Based on given information above

In a birth and death process with birth rate \lambda and death rate \mu , the probability of system to be in state 'n' is given as

Pn λολι....λη+1 λολι...λε-1) μιμ2...μη(1 + ΣΕΙ n=1 μιμ2...μη -1 η Σ1 (1)

Where \lambda_n,\mu_n are birth and death rates for state n

(a) What is the average number of machines not in use?

For the given problem, if the state n is defined as that "n machines are not in use", then it can be modeled as a birth and death process having parameters

\mu_n=\mu\ \ n\geq 1

\lambda_n=(M-n)\lambda \ \ n\leq M

Here failing machine is regarded as a birth process and a fixed machine as a death process.

If any machine fails, serviceman rate for each state \mu_n=\mu .

For state n, if n machines are not in use, then (M-n) machines are in use and each fail at rate \lambda .

so for state n, \lambda_n=(M-n)\lambda

Putting values of \lambda_n and \mu_n in eqn (1)

we get

P_n=\frac{(M-0)\lambda:(M-1)\lambda...(M-n+1)\lambda}{\mu\mu...ntimes (1+\sum_{n=1}^{M}\frac{(M-0)\lambda(M-1)\lambda...(M-n+1)\lambda}{\mu\mu...n times})}=\frac{M(M-1)...(M-n+1)\lambda^n}{\mu^n (1+\sum_{n=1}^{M}\frac{M(M-1)...(M-n+1)\lambda^n}{\mu^n})}

P_n=\frac{(\frac{\lambda}{\mu})^n(\frac{M!}{(M-n)!})}{(1+\sum_{n=1}^{M}(\frac{\lambda}{\mu})^n(\frac{M!}{(M-n)!}))}............(2)

Average number of machines not in use

\sum_{n=0}^{M}nP_n=\sum_{n=0}^{M}\frac{(\frac{\lambda}{\mu})^n(\frac{M!}{(M-n)!})}{(1+\sum_{n=1}^{M}(\frac{\lambda}{\mu})^n(\frac{M!}{(M-n)!}))}...........(3)

(b) What proportion of time is each machine in use?

proportion of time each machine in use.

=\sum_{n=0}^{M}p(machine\ is\ working\ /n machine\ not\ working)P_n=\sum_{n=0}^{M}\frac{M-n}{M}P_n

=\sum_{n=0}^{M}(1-\frac{n}{M})P_n

=1-\frac{1}{M}\sum_{n=0}^{M}nP_n

Where

\sum_{n=0}^{M}nP_n is given by equation (3)

Thanks for supporting...

Please give positive rating...

Add a comment
Know the answer?
Add Answer to:
here is the machine and serviceman problem. Question 9 (10 points): Consider a job shop that...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 2. A printing shop has four presses and two repairmen. The amount of time a printing press work b...

    2. A printing shop has four presses and two repairmen. The amount of time a printing press work before needing service is exponential with mean of 5 hours. Suppose that the amount of time」 takes a single repairman to fix a machine is exponential with mean 4 hours. (a) What is the average number of machines not in use? (b) What is the coefficient of loss for machines? (e) During what proportion of time are both repairmen busy? (d) What...

  • 2. A printing shop has four presses and two repairmen. The amount of time a printing press works ...

    ASSUME STEADY STATE CONDITION 2. A printing shop has four presses and two repairmen. The amount of time a printing press works before needing service is exponential with mean of 5 hours. Suppose that the amount of time it takes a single repairman to fix a machine is exponential with mean 4 hours. (a) What is the average number of machines not in use? (b) What is the coefficient of loss for machines? (c) During what proportion of time are...

  • 2itng shop has four presses and two repairmen. The amount of time a printing press wor...

    2itng shop has four presses and two repairmen. The amount of time a printing press wor before needing service is exponential with mean of 5 hours. Suppose that the amount of time it takes a single repairman to fix a achine is exponential with mean 4 hours (a) What is the average number of machines not in use? (b) What is the coefficient of loss for machines? cDuring what proportion of time are both repairmen busy? (d) What is the...

  • 3. Suppose that the work assignments in Question 2 are changed so the each repairman has exclusiv...

    Please answer Q3, not Q2. Q2 is for reference only 3. Suppose that the work assignments in Question 2 are changed so the each repairman has exclusive responsibility for two macn. (a) What is the average number of machines not in use? (b) What is the coefficient of loss for machines? (c) During what proportion of time are both repairmen busy? (d) What is the coefficient of loss for repairmen? 2itng shop has four presses and two repairmen. The amount...

  • Exercise 10.10 (Job shop scheduling) A factory consists of m machines M1, , Mm, and needs to proc...

    Exercise 10.10 (Job shop scheduling) A factory consists of m machines M1, , Mm, and needs to process n jobs every day. Job j needs to be processed once by each machine in the order (M,a)M(m)). Machine M takes time Pij to process job j. A machine can only process one job at a time, and once a job is started on any machine, it must be processed to complet is to minimize the sum of the completion times of...

  • Arena Simulation. Five identical machines operate independently in a small shop. Each machine is up (i.e.,...

    Arena Simulation. Five identical machines operate independently in a small shop. Each machine is up (i.e., works) for between six and ten hours (uniformly distributes) and then breaks down. There are two repair technicians available, and it takes one technician between one and three hours (uniformly distributed) to fix a machine; only one technician can be assigned to work on a broken machine even if the other technician is idle. If more than two machines are broken down at a...

  • The Acme Machine Shop has five machines that periodically break down and require service. The average...

    The Acme Machine Shop has five machines that periodically break down and require service. The average time between breakdowns for any one machine is 4 days, distributed according to an exponential distribution. The average time to repair a machine is 1 day, distributed according to an exponential distribution. One mechanic repairs the machines in the order in which they break down. Use q.xls. a. Determine the probability that the mechanic is idle. (Hint: Pn is given in q.xls, and is...

  • Problem 2 There are three machines and two mechanics in a factory. The break time of each machine...

    Problem 2 There are three machines and two mechanics in a factory. The break time of each machine is exponentially distributed with A 1 (per day). The repair time of a broken machine is also exponentially distributed with a mean of 3 hours. (Mechanics work separately) (1). Construct the rate diagram for this queueing system. (be careful about the arrival rate A) (2). Set up the rate balance equations, then solve for pn's. (3). Compute L (4). Compute the actual...

  • (1) Consider a "two machine two repairman" problem, where each machine independently breaks down ...

    (1) Consider a "two machine two repairman" problem, where each machine independently breaks down at rate μ (that is after an exponential waiting time with parameter μ) (a) If each repairman repairs a machine at rate λ, calculate the long term proportion of time when both machines are broken. [Hint: calculate the stationary probabilities.] You can also consider 4 marks] (b) Assume that repairman Abel works at rate X, and repairman Bernard works at rate Xb. When there is only...

  • 3. Consider the following seven-job problem. Each job must be processed by two ma chines A...

    3. Consider the following seven-job problem. Each job must be processed by two ma chines A and B, first on machine A and then machine B. The operation processing times at machine A and B are as follows: Job i 1 2 3 5 6 Processing time on machine A (a9 8 5 10 6 8 5 Processing time on machine B (b) 6 5 7912 11 4 a. Suppose jobs arrived in their natural order (i.e, job before job...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT