Question

Use the following information to answer questions 17-20.

A large hospital uses a certain intravenous solution that it maintains in inventory. Assume the hospital uses reorder point method to control the inventory of this item. Pertinent data about this item are as follows:

------------------------------------------------------------

Forecast of demanda = 1,000 units per week

Forecast errora, std. dev. =100 units per week

Lead time = 4 weeks

Carrying cost = 25 % per year

Purchase price, delivered = $52 per unit

Replenishment order cost = $20 per order

Stockout cost = $10 per unit

In-stock Probability during the lead time =90%

a Normally distributed

------------------------------------------------------------

Due to possible rounding effect, please pick the closest number in the following options.

Question 17 (1 point)

Question 17 Saved

What is the reorder point?

Question 18 (1 point)

Question 18 Saved

If the hospital orders 400 units each time, what’s the expected number of units out of stock annually?

Question 18 options:

1248

2912

500

1000

Save

Use the following information to answer questions 17-20.

A large hospital uses a certain intravenous solution that it maintains in inventory. Assume the hospital uses reorder point method to control the inventory of this item. Pertinent data about this item are as follows:

------------------------------------------------------------

Forecast of demanda = 1,000 units per week

Forecast errora, std. dev. =100 units per week

Lead time = 4 weeks

Carrying cost = 25 % per year

Purchase price, delivered = $52 per unit

Replenishment order cost = $20 per order

Stockout cost = $10 per unit

In-stock Probability during the lead time =90%

a Normally distributed

------------------------------------------------------------

Due to possible rounding effect, please pick the closest number in the following options.

Question 19 (1 point)

Question 19 Saved

If the hospital orders 400 units each time, what’s the total annual costs (holding cost + ordering cost + stock-out cost) excluding purchasing costs?

Question 19 options:

10000

21008

31008

42016

Save

Use the following information to answer questions 17-20.

A large hospital uses a certain intravenous solution that it maintains in inventory. Assume the hospital uses reorder point method to control the inventory of this item. Pertinent data about this item are as follows:

------------------------------------------------------------

Forecast of demanda = 1,000 units per week

Forecast errora, std. dev. =100 units per week

Lead time = 4 weeks

Carrying cost = 25 % per year

Purchase price, delivered = $52 per unit

Replenishment order cost = $20 per order

Stockout cost = $10 per unit

In-stock Probability during the lead time =90%

a Normally distributed

------------------------------------------------------------

Due to possible rounding effect, please pick the closest number in the following options.

Question 20 (1 point)

Question 20 Saved

If the lead time is normally distributed with a mean of 4 weeks and a standard deviation of 0.5 weeks, what’s the reorder point?

Question 20 options:

4689

4129

5188

6000

Save

Previous PageNext Page

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Reorder Point = Mean Demand*Lead Time + z*SD of Demand*(Lead Time)^(1/2)

ROP = 1000*4 + 1.281552*100*2

ROP = 4256.31

ROP = 4256

_______________________________________________________________________

Normal loss function, L(Z) corresponding to 90% service level = 0.048

Expected shortage per cycle (ESC) = L(Z) * σ * (L)^(1/2) = 0.0473*100*(4)^(1/2) = 9.6

Annual shortage = ESC x no. of cycles annually = 9.6 x (52000/400) = 1248

__________________________________________________________________________

Shortage cost = Annual shortage x shortage cost per unit = 1248*10 = 12480

Order quantity, Q = 400
Holding cost per unit per annum, H = 52 * 25% = 13
Annual demand, D = 1000 x 52 = 52,000
Ordering cost, S = 20

Cycle stock holding cost = Q * H/ 2 = 400*13/2 = 2600

Ordering cost = (D/Q) * S = (52000 / 400) * 20 = 2600

Safety stock cost = Safey stock * H = 1.28*100*SQRT(4) * 13 = 3328

Total cost = $2,600 + $2,600 + $12,480 + $3,328 = $21,008

__________________________________________________________________________

L = 4
σL = 0.5

The following formula for ROP will apply.

ROP = d * L + Z * √(σ2.L + d2L2)= 1000*4 + 1.28*SQRT((100^2)*4 + (1000*0.5)^2) =4,689

Add a comment
Know the answer?
Add Answer to:
Use the following information to answer questions 17-20. A large hospital uses a certain intravenous solution...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Supply Chain 14. A large hospital uses a certain intravenous solution that it maintains in inven-...

    Supply Chain 14. A large hospital uses a certain intravenous solution that it maintains in inven- tory. Pertinent data about this item are as follows: Forecasted daily usage 60 units = 15 units =7days = 2 days = 30%) t error std. devb Average lead time Lead time std. dev.b Annual carrying cost Procurement cost per order Stockout cost Product value In-stock probabilit $15 per unit $45 per unit = 90% 365 days per year bNormally distributed During the lead...

  • Use the Continuous Inventory Model and the data below to answer these six questions. Forecast of...

    Use the Continuous Inventory Model and the data below to answer these six questions. Forecast of demanda = 36,000 units per week Forecast error, std. dev. = 800 units per week Lead time = 2.5 weeks Lead time error, std. dev = 1.2 weeks Carrying cost = 20% per year Purchase price, delivered = $65 per unit Replenishment order cost = $2,000 per order Stockout cost - $2 per unit EOQ = 24,000 units In-stock Probability during the lead time...

  • need C, D, and F completed Use the Continuous Inventory Model and the data below to...

    need C, D, and F completed Use the Continuous Inventory Model and the data below to answer these six questions. Forecast of demanda = 36,000 units per week Forecast error, std. dev. = 800 units per week Lead time = 2.5 weeks Lead time error", std. dev = 1.2 weeks Carrying cost = 20 % per year Purchase price, delivered = $65 per unit Replenishment order cost = $2,000 per order Stockout cost = $2 per unit EOQ = 24,000...

  • Given the following information, formulate a continuous-review inventory management system. The item is demanded 50 weeks...

    Given the following information, formulate a continuous-review inventory management system. The item is demanded 50 weeks a year. 2. Item cost Order cost Annual holding cost (%) Annual demand Average demand $20 $250 10% df item cost 25,000 500 per week Standard deviation of weekly demand Lead time Service probability 25 per week 1 week 95% Compute the order quantity and reorder point. For the order quantity, please provide at least one step of calculation and the correct answer for...

  • Jill's Job Shop buys two parts (Tegdiws and Widgets) for use in its production system from...

    Jill's Job Shop buys two parts (Tegdiws and Widgets) for use in its production system from two different suppliers. The parts are needed throughout the entire 52-week year. Tegdiws are used at a relatively constant rate and are ordered whenever the remaining quantity drops to the reorder level. Widgets are ordered from a supplier who stops by every five weeks. Data for both products are as follows: ITEM TEGDIW WIDGET Annual demand 14,000 9,000 Holding cost (% of item cost)...

  • Simulate the following inventory replenishment problem for 20 weeks. You will have to use the Excel...

    Simulate the following inventory replenishment problem for 20 weeks. You will have to use the Excel program to simulate. Demand is uniformly distributed between 20 and 30 units. Additional Data are given below. Inventory Cost/Week = $ 1.00 Shortage Cost/Week = $ 2.00 Lead Time = 2 weeks Beginning Stock on Hand (SOH) = 0 Supply in Week 1 = 21 units Supply in Week 2 = 22 units What is the total shortage cost at the end of 20...

  • For questions 1-4, please use the following scenario: Rocky Mountain Power (RMP) maintains an inventory of...

    For questions 1-4, please use the following scenario: Rocky Mountain Power (RMP) maintains an inventory of spare parts that is valued at nearly $8 million. This inventory is composed of thousands of different stock-keeping units (SKUs) used for power generation and utility line maintenance, and the inventory balances are updated on a computerized information system. Glass insulators (i.e., SKU 1341) have a relatively stable usage rate, averaging 20 items per week. RMP purchases these insulators from the manufacturer at a...

  • Item Cost: $8.00 Order Cost: $287 Annual Holding Cost: 33% of item cost Annual Demand: 27,400...

    Item Cost: $8.00 Order Cost: $287 Annual Holding Cost: 33% of item cost Annual Demand: 27,400 Average Weekly Demand: 548 Std. Dev. of Weekly Demand: 20/week Lead Time: 3 weeks Service Probability: 99% Previously found Info: Optimal order quantity = 2441 units. Reorder point = 1725 units. Annual Holding Cost: $3222.12. Annual Order Cost: $3221.55. Assume a price break of $55 per order was offered for purchase quantities of 2,500 or more units per order. If you took advantage of...

  • * Week5 2521/activity Saved Help Save & Exit Su Jill's Job Shop buys two parts (Tegdiws...

    * Week5 2521/activity Saved Help Save & Exit Su Jill's Job Shop buys two parts (Tegdiws and Widgets) for use in its production system from two different suppliers. The parts are needed throughout the entire 52-week year. Tegdiws are used at a relatively constant rate and are ordered whenever the remaining quantity drops to the reorder level. Widgets are ordered from a supplier who stops by every two weeks. Data for both products are as follows: ITEM Annual defand Holding,...

  • Jill's Job Shop buys two parts (Tegdiws and Widgets) for use in its production system from...

    Jill's Job Shop buys two parts (Tegdiws and Widgets) for use in its production system from two different suppliers. The parts are needed throughout the entire 52-week year. Tegdiws are used at a relatively constant rate and are ordered whenever the remaining quantity drops to the reorder level. Widgets are ordered from a supplier who stops by every two weeks. Data for both products are as follows: ITEM TEGDIW WIDGET Annual demand 9,000 9,000 Holding cost (% of item cost)...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT