    Assuming that there is no safety stock and that the present stock level is 400 components, when should the next order be placed? (Assume a 360-day year.)         


lead time= 3 days

4000units per month= 4000/31=129units per day          

reorder point= lead time demand + safety stock

                = (lead time x average daily usage) + safety stock

               = ???


0 0
Add a comment Improve this question Transcribed image text
Request Professional Answer

Request Answer!

We need at least 9 more requests to produce the answer.

1 / 10 have requested this problem solution

The more requests, the faster the answer.

Request! (Login Required)


All students who have requested the answer will be notified once they are available.
Know the answer?
Add Answer to:
reorder point
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
  • Reorder Point Shorts Company manufactures backpacks. A heavy-duty strap is one part that the company orders...

    Reorder Point Shorts Company manufactures backpacks. A heavy-duty strap is one part that the company orders from an outside supplier. Information pertaining to the strap is as follows: Economic order quantity 6,300 units Average daily usage 315 units Maximum daily usage 375 units Lead time 4 days Required: 1. What is the reorder point assuming no safety stock is carried? units 2. What is the reorder point assuming that safety stock is carried? units

  • economic order quantity

    Assuming that there is no safety stock and that the present stock level is 400 components, when should the next order be placed? (Assume a 360-day year.) (1 mark)COVID-19 Ltd produces a specialized product; LOCKDOWN which has a constant monthly demand of 4000 units. The LOCKDOWN requires a component which COVID-19 Ltd purchases from a supplier at GHS10 per unit. The component requires a three-day lead time from the date of order to the date of delivery. The ordering cost...

  • EOQ, reorder point, and safety stock Alexis Company uses 805 units of a product per year...

    EOQ, reorder point, and safety stock Alexis Company uses 805 units of a product per year on a continuous basis. The product has a fixed cost of $50 per order, and its carrying cost is $4 per unit per year. It takes 5 days to receive a shipment after an order is placed, and the firm wishes to hold 10 days' usage in inventory as a safety stock. a. Calculate the EOQ. b. Determine the average level of inventory. (Note:...

  • EOQ, reorder point, and safety stock Alexis Company uses 631 units of a product per year...

    EOQ, reorder point, and safety stock Alexis Company uses 631 units of a product per year on a continuous basis. The product has a fixed cost of $41 per order, and its carrying cost is $4 per unit per year. It takes 5 days to receive a shipment after an order is placed, and the firm wishes to hold 10 days' usage in inventory as a safety stock. a. Calculate the EOQ. b. Determine the average level of inventory. (Note:...

  • EOQ, reorder point, and safety stock Alexis Company uses 907 units of a product per year...

    EOQ, reorder point, and safety stock Alexis Company uses 907 units of a product per year on a continuous basis. The product has a fixed cost of $57 per order, and its carrying cost is $5 per unit per year It takes 5 days to receive a shipment after an order is placed, and the firm wishes to hold 10 days' usage in inventory as a safety stock. a. Calculate the EOQ. b. Determine the average level of inventory. (Note:...

  • economic order quantity

    Syarikat GU Sdn. Bhd. produces a product which has a constant monthly demand of 4000 units. The product requires a component which Syarikat GU Sdn. Bhd. purchases from a supplier at RM10 per unit. The component requires a three-day lead time from the date of order to the date of delivery. The ordering cost is RM0.60 per order and the holding cost is 10% per annum.  You are required to: (a)  (i)   Compute the economic order quantity       ...

  • The reorder point r = dm is defined as the lead-time demand for an item. In cases of long lead times, the lead-time dema...

    The reorder point r = dm is defined as the lead-time demand for an item. In cases of long lead times, the lead-time demand and thus the reorder point may exceed the economic order quantity Q*. In such cases, the inventory position will not equal the inventory on hand when an order is placed, and the reorder point may be expressed in terms of either the inventory position or the inventory on hand. Consider the economic order quantity model with...

  • Please kindly explain all the formulas and also how to find z value from service level...

    Please kindly explain all the formulas and also how to find z value from service level in steps Question 5: (5 Points) A local company uses an average of 650 items a day. The daily usage has a standard deviation of 23. The manager is willing to accept no more than a 1% chance of a stock out. The lead-time is 14 days. (Assuming the distribution of usage is normal). What is the re-order point? Question 6: (5 Points) A...

  • Using the reorder level-order quantity model, and assuming a safety stock of 800, what is the...

    Using the reorder level-order quantity model, and assuming a safety stock of 800, what is the re-order point (R) given a daily demand of 300 units, a lead time of 5 days? 300 800 1500 2300 1100 Which of the following basic types of process structures needs to keep inventory of work-in-process component parts? Assemble to Order Make to Stock O None of the above Make to Order Engineer to Order Suppose a call center has one agent answering the...

  • Compute the safety stock (S.S.) and reorder point (ROP) for the following situation: Annual Demand =...

    Compute the safety stock (S.S.) and reorder point (ROP) for the following situation: Annual Demand = 6570 units Unit Price = $11 and no quantity discounts Ordering Cost = $25/order Holding Cost = $1.50/unit Lead Time = 5 days Desired Customer Service Level = 97.5% Assume 365 days/year and that demand and lead time are constant. Safety Stock = 10; ROP = 90 Safety Stock = 0; ROP = 90 Safety Stock = 5; ROP = 150 Safety Stock =...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT